PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

135 questions found · page 6 of 6

126
PeoplePredictiveMedium

You are managing a large infrastructure project using a waterfall approach. During the execution phase, you notice that two senior engineers from different departments are having ongoing disagreements about technical specifications, causing delays in critical path activities. Both engineers are subject matter experts and report to different functional managers, not to you. The disagreements are escalating and beginning to affect team morale. What should you do first?

May 29, 2026

127
PeoplePredictiveMedium

You are managing a construction project using a traditional waterfall approach. The project is in the execution phase, and you have a geographically distributed team with members across three different time zones. You notice that team members in the remote locations seem less engaged during virtual meetings and are often unaware of important decisions made by the core team at headquarters. Productivity metrics show that deliverables from remote team members are occasionally misaligned with project requirements. How should you address this situation?

May 29, 2026

128
PeoplePredictiveMedium

You are managing a multi-year government infrastructure project using a predictive approach. Six months into execution, a key technical lead who has been with the project since initiation submits their resignation, citing a better opportunity elsewhere. This individual possesses critical knowledge about design decisions and has established relationships with several government stakeholders. Their departure is scheduled for three weeks from now. The project is currently on track, but several complex deliverables are planned for the next quarter. What is your best course of action?

May 29, 2026

129
PeoplePredictiveMedium

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

May 29, 2026

130
PeoplePredictiveMedium

You are managing a software implementation project using a waterfall methodology for a financial services client. During the design phase, you discover that one of your key business analysts, who is responsible for defining critical system requirements, lacks experience with the specific regulatory compliance requirements of the financial industry. This knowledge gap was not apparent during resource assignment. The design phase is scheduled to complete in six weeks, and this analyst is already assigned full-time to your project. What should you do?

May 29, 2026

131
ProcessPredictiveMedium

You are managing a government IT project following predictive methodologies. During a phase gate review at the end of the design phase, the project governance board expresses concern that several technical risks identified in the risk register have not been actively managed, though none have materialized yet. The board notes that risk response plans were documented during planning but asks for evidence of ongoing risk monitoring activities. Your risk register has not been updated in six weeks. How should you address this situation moving forward?

May 28, 2026

132
ProcessPredictiveMedium

You are managing a 12-month infrastructure project using a predictive approach. At the end of month 4, you review the project dashboard and notice that planned value (PV) is $400,000, earned value (EV) is $350,000, and actual cost (AC) is $380,000. Several team members report that they have been working on activities that were not originally scheduled for this period because they had available time. What is the PRIMARY issue this situation reveals about project management processes?

May 28, 2026

133
ProcessPredictiveMedium

You are leading a pharmaceutical software implementation project following a predictive approach. The project has completed the planning phase, and you have a detailed WBS, activity list, and resource assignments. During the first month of execution, three team members inform you they will be pulled away for two weeks to support an urgent regulatory audit. This was not anticipated during planning and affects activities on the critical path. What should be your FIRST action as the project manager?

May 28, 2026

134
ProcessPredictiveMedium

Your manufacturing equipment upgrade project is in the executing phase. A key vendor has submitted deliverables for the third milestone, but during the inspection process, your quality assurance team identifies that 15% of the components do not meet the specifications outlined in the procurement contract. The vendor claims the specifications were ambiguous and requests additional payment to remake the components. This is causing a potential two-week delay. What is the BEST course of action?

May 28, 2026

135
ProcessPredictiveMedium

You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?

May 28, 2026