PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

20 questions found

1
ProcessHybridEasy

You are managing a hybrid project for a marketing campaign. The creative design work is being managed using Scrum with two-week sprints, while the media buying and placement follows a predictive approach with fixed deadlines. At the end of sprint 2, the creative team has completed designs that need approval before media placement can proceed. The media buying schedule shows placement must begin in one week. What should you do to ensure both components stay coordinated?

November 14, 2026

→
2
ProcessHybridEasy

Your hybrid project includes a hardware component managed predictively and a software component managed using Kanban. The hardware team reports they are on schedule, but the software team's Kanban board shows several items stuck in the 'In Progress' column for over two weeks. The team's work-in-progress (WIP) limit is being exceeded. As the project manager, what should you do?

November 14, 2026

→
3
ProcessHybridEasy

You are leading a hybrid project where regulatory compliance activities follow a predictive approach with formal gate reviews, while user interface development follows an agile approach with two-week sprints. The compliance team has identified a new regulatory requirement that will impact the user interface. The development team is currently in the middle of sprint 3. What is the best way to handle this new requirement?

November 14, 2026

→
4
ProcessHybridEasy

Your organization is implementing a new product using a hybrid approach. The infrastructure setup follows a waterfall methodology, while feature development uses Scrum. You are creating the overall project schedule. The infrastructure team needs four months to complete their work before any development can begin. The product owner wants to see working features as soon as possible. How should you structure the project timeline?

November 14, 2026

→
5
ProcessHybridEasy

You are managing a hybrid project where the design phase follows a predictive approach and the development phase uses iterative sprints. The design team has completed their work and handed off specifications to the development team. However, the development team reports that several requirements are unclear and need clarification. The design team has already moved on to another project. What should you do first?

November 14, 2026

→
6
ProcessHybridEasy

A project team is using a hybrid approach where high-level milestones and deliverables were defined upfront, but the team uses two-week sprints to deliver increments. At the end of each sprint, the team holds a review session with stakeholders. A key stakeholder has missed the last three sprint reviews and is now complaining that the project is not meeting their expectations. What should the project manager do?

September 18, 2026

→
7
ProcessHybridEasy

A hybrid project has a fixed budget approved by the steering committee, but features are being delivered iteratively based on business value. After completing 40% of the planned iterations, the project has spent 50% of the budget due to higher than expected infrastructure costs. The remaining features in the backlog are all considered high priority by stakeholders. What should the project manager do next?

September 18, 2026

→
8
ProcessHybridEasy

A project manager is leading a hybrid project where the design phase was completed using a predictive approach, and now the team is moving into iterative development sprints. Several team members who were not involved in the design phase are confused about the project requirements. Velocity has been lower than expected in the first sprint. What should the project manager do?

September 18, 2026

→
9
ProcessHybridEasy

A project team is using a hybrid approach where requirements are gathered upfront but development is executed in two-week sprints. The product owner has just requested a new feature that was not in the original project scope. The team has completed three sprints and has five more planned. What should the project manager do first?

September 18, 2026

→
10
ProcessHybridEasy

A software development project is using a hybrid approach with a defined budget and timeline, but iterative delivery of features. During the third iteration, the team discovers that a core architectural component needs to be redesigned, which will impact the overall project schedule. The project sponsor is concerned about meeting the fixed deadline. What is the best way for the project manager to address this situation?

September 18, 2026

→
11
ProcessHybridEasy

A hybrid project has completed three sprints for its software component while the predictive infrastructure component is progressing through its execution phase. The project sponsor asks for a progress report to present to the steering committee. The sponsor wants to understand overall project status in a clear, unified way. What should the project manager provide?

August 13, 2026

→
12
ProcessHybridEasy

A project manager is overseeing a hybrid project where regulatory compliance work follows a waterfall approach and customer-facing features follow Scrum. During a sprint review, stakeholders request adding a new compliance requirement that affects both components. The compliance work requires detailed documentation and formal approval, while the Scrum team prefers to add items directly to their backlog. What is the best approach to manage this change?

August 13, 2026

→
13
ProcessHybridEasy

A product owner for a hybrid project needs to create requirements documentation. The project includes both a predictive hardware development phase and an agile software development phase. The hardware specifications must be finalized before manufacturing begins, while the software features will evolve based on user feedback. How should the project manager guide the product owner in documenting requirements?

August 13, 2026

→
14
ProcessHybridEasy

A project manager is leading a hybrid project where the infrastructure component follows a predictive approach and the software development follows an agile approach. The infrastructure team has just completed their foundation work ahead of schedule, which was a prerequisite for the software team to begin their first iteration. The software team lead asks how they should proceed with planning their upcoming sprint. What should the project manager recommend?

August 13, 2026

→
15
ProcessHybridEasy

A project team is planning a hybrid project where hardware procurement will follow a predictive approach with fixed contracts, and software configuration will follow Scrum with two-week sprints. The project manager needs to plan how the two components will integrate. The hardware delivery is scheduled for month 3, and software sprints will begin in month 1. What integration approach should the project manager establish?

August 13, 2026

→
16
ProcessHybridEasy

You are leading a project that combines agile development sprints with a traditional stage-gate approval process for major releases. The development team has completed all sprint work for the current release, but a quality gate review is scheduled for two weeks from now. The team is asking what they should work on next. What should you recommend?

July 22, 2026

→
17
ProcessHybridEasy

Your project uses Scrum for software development and a waterfall approach for regulatory compliance activities. During sprint planning, the team identifies they need a compliance review completed before they can implement a new feature. The compliance review is scheduled for next month according to the predictive plan. What is the best way to handle this situation?

July 22, 2026

→
18
ProcessHybridEasy

You are managing a hybrid project where the development team works in two-week sprints while the infrastructure team follows a predictive approach. The development team has completed their sprint and is ready to deploy, but the infrastructure team needs two more weeks to complete their planned activities. Stakeholders are asking when the feature will be available. What should you do first?

July 22, 2026

→
19
ProcessHybridEasy

You are managing a project where the design phase follows a predictive approach with detailed upfront planning, but the implementation phase uses Scrum. The design phase has just completed, and you are transitioning to implementation. Several team members who worked on design are asking how they will track progress now. What should you explain to them?

July 22, 2026

→
20
ProcessHybridEasy

Your hybrid project has a product backlog for agile work and a work breakdown structure (WBS) for predictive components. A new stakeholder requirement emerges that could impact both the agile and predictive portions of the project. The business value is clear, but implementation approach is uncertain. How should you handle adding this requirement?

July 22, 2026

→