Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
140 questions found · page 1 of 6
You are managing a pharmaceutical research project following a stage-gate process. Your project has just completed the Phase 2 clinical trials deliverable. According to the project management plan, a phase gate review is scheduled before proceeding to Phase 3 trials, which will require significant investment. During your preparation for the gate review, you discover that while the trials met their primary endpoint, two secondary endpoints showed concerning trends. The data is not conclusive but suggests potential issues. The project is currently on schedule and under budget. What should you do?
October 7, 2026
Your project team has completed the project scope statement and is now developing the work breakdown structure (WBS). One of your team members suggests creating work packages at different levels of decomposition across the WBS—some at a very detailed level that can be completed in days, and others at a higher level representing several weeks of work. The team member argues this will save time in the planning process. What is the best approach?
October 7, 2026
You are managing a software development project using a waterfall methodology. During the design phase, your technical lead identifies that implementing a requested feature will require a third-party library that introduces significant security vulnerabilities. The feature was explicitly defined in the approved scope baseline and is important to the customer. After analysis, your team proposes an alternative technical approach that provides similar functionality without the security risk but will add $15,000 to the project cost. What should you do?
October 7, 2026
Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?
October 7, 2026
You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?
October 7, 2026
You are managing a telecommunications infrastructure project using a predictive approach. The project team includes specialists from engineering, procurement, and installation departments. During project planning, you identified that the engineering team needs to complete detailed designs before procurement can begin vendor selection, and installation cannot start until equipment arrives. You've created a detailed schedule with these dependencies. However, the engineering manager informs you that his team is being pulled to support an emergency on another project and will be unavailable for three weeks, which will impact your critical path. What is the best way to handle this situation?
October 5, 2026
You are managing a manufacturing project following a predictive life cycle. During a milestone review, you discover that one of your team leads has consistently overstated the completion percentage of their work packages in status reports. Upon investigation, you find the actual progress is about 20% behind what was reported, though the work quality is acceptable. This team lead has been with the company for 15 years and is generally reliable. The project is now showing as on-track when it is actually behind schedule. What should be your first course of action?
October 5, 2026
You are leading a construction project with a detailed work breakdown structure and baseline schedule. A team member who is relatively new to the organization approaches you privately and mentions that they feel intimidated by the project's senior architect, who frequently dismisses their input during technical meetings. The team member is responsible for quality inspections and their observations are important for project success. The senior architect is known for being direct but has excellent technical expertise. How should you address this situation?
October 5, 2026
You are managing a software development project using a waterfall methodology. During the development phase, your lead developer informs you that she has received a job offer from another company and will be leaving in three weeks. She is the only team member with deep knowledge of the legacy system integration, which is critical for the next phase. The project is currently on schedule, and this phase is expected to complete in two months. What is the most effective action to take?
October 5, 2026
You are managing a large infrastructure project using a predictive approach with a team of 45 members across three locations. During the executing phase, you notice that two senior engineers from different locations are in constant disagreement about technical specifications, causing delays in deliverables. The project schedule shows this work is on the critical path. Both engineers are highly skilled and have worked on similar projects before. What should you do first to address this situation?
October 5, 2026
A manufacturing company is executing a predictive project to expand production capacity. Midway through the project, economic indicators show that the industry is entering a downturn, with projected demand decreasing by 15% over the next two years. The CFO has asked all departments to reduce discretionary spending. The project is currently on schedule and 5% under budget. The project sponsor believes the expansion is still strategically important for long-term competitiveness but asks the project manager to evaluate options for reducing project costs. What should the project manager do FIRST?
October 4, 2026
A project manager is executing a predictive software implementation project for a financial services firm. During a governance review, the compliance officer identifies that new data privacy regulations will take effect in two months, requiring all customer data to be encrypted both in transit and at rest. The current project scope includes basic security measures but not the level of encryption now required by regulation. The additional security requirements will add three weeks to the schedule and $75,000 to the budget. How should the project manager proceed?
October 4, 2026
A project manager is leading a predictive infrastructure project for a utility company. During project planning, the finance department informs the project manager that the organization is transitioning to a new enterprise resource planning (ERP) system in three months, which will change all financial reporting and procurement processes. The project has a 12-month duration and requires significant procurement activities throughout execution. What should the project manager do to address this organizational change?
October 4, 2026
A pharmaceutical company is executing a predictive project to develop a new manufacturing facility. Six months into the project, a competitor announces they are building a similar facility with advanced automation technology that will significantly reduce their production costs. The project sponsor is concerned about the project's strategic value and asks the project manager to evaluate whether the current project approach remains viable. The project is 40% complete and on track with the approved baseline. What is the MOST appropriate action for the project manager to take?
October 4, 2026
A project manager is leading a predictive construction project for a government agency when new environmental regulations are enacted that directly impact the project's waste management processes. The project is currently in the execution phase, and compliance with these regulations will require additional permits and equipment modifications. The project manager has identified the impact on cost and schedule. What should the project manager do FIRST?
October 4, 2026
You are managing a pharmaceutical research project following a stage-gate predictive methodology. Your project has just completed the design phase, and you are preparing for the gate review before entering the development phase. During preparation, you discover that one of the key assumptions documented in the project charter—that a specific research facility would be available—is no longer valid due to facility renovations. The next available equivalent facility is in a different location and would increase project costs by 8%. What should you do BEFORE the gate review?
September 29, 2026
You are managing a large infrastructure project with multiple subcontractors. One of your key vendors has completed their deliverable, and you are conducting procurement closure activities. While reviewing the final deliverable, you notice it meets all technical specifications in the contract, but the vendor failed to submit three required progress reports during execution as stipulated in the contract terms. The vendor is requesting final payment and contract closure. What is the MOST appropriate action?
September 29, 2026
You are managing a software implementation project for a financial institution using a waterfall approach. During quality testing, the QA team discovers that 12% of test cases are failing, primarily related to security authentication features. The quality management plan specified that no more than 5% of test cases should fail at this stage. The development team believes they can fix the issues within one week, but this will delay the scheduled user acceptance testing. What should you do?
September 29, 2026
Your manufacturing project is in the planning phase, and you are developing the cost baseline. You have completed bottom-up estimating for all work packages and have aggregated these costs. The finance department requires a 10% management reserve for organizational risks, and historical data shows similar projects typically experience 15% cost variance. Your project sponsor asks what the final project budget should include. What is the MOST appropriate approach?
September 29, 2026
You are managing a construction project using a predictive approach. During the execution phase, a key supplier informs you that critical materials will be delayed by three weeks due to manufacturing issues. The delay will impact the critical path and push the project completion date beyond the contractually agreed deadline. Several team members suggest crashing the schedule by adding overtime resources, while the sponsor wants to explore fast-tracking options. What should you do FIRST?
September 29, 2026
You are managing a 14-month product development project currently in month 8. The project has a documented communications management plan that specifies monthly status reports to stakeholders. A key stakeholder who rarely attended review meetings or responded to status reports suddenly expresses strong dissatisfaction with the project direction during a chance meeting with your sponsor. The sponsor is now questioning your stakeholder management approach. Upon investigation, you discover this stakeholder's engagement level has dropped from 'supportive' to 'resistant' without your awareness. What should you have done differently?
September 18, 2026
You are managing a software development project using a predictive approach. During a quality audit, the quality assurance team identifies that 15% of the deliverables from the development phase contain defects that meet the defined acceptance criteria but fall short of industry best practices for security standards. The project quality management plan specifies conformance to acceptance criteria as the measure of quality. Fixing these issues would require additional time and budget not currently allocated. What should you do?
September 18, 2026
Your manufacturing project is in the execution phase. A critical supplier informs you that a key component will be delayed by three weeks due to material shortages. This component is on the critical path and was scheduled to be delivered in two weeks. You review your risk register and find that supplier delays were identified as a risk, with a mitigation strategy to identify alternate suppliers. However, no alternate suppliers were pre-qualified. What should you do first?
September 18, 2026
You are managing a construction project with a 12-month timeline and a fixed budget of $2.5 million. During the fourth month, you conduct an earned value analysis and find that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The sponsor asks you to forecast the final project cost assuming current performance continues. What is the most appropriate estimate to provide?
September 18, 2026
Your project team has completed the work breakdown structure (WBS) for a complex infrastructure project. During the activity definition process, a senior team member suggests that some work packages are still too large and should be decomposed further into smaller activities. Another team member argues that further decomposition is unnecessary and will create excessive administrative overhead. The work packages in question represent approximately 120 hours of work each. How should you proceed?
September 18, 2026
