PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

20 questions found

1
ProcessAgileEasy

You are the project manager for an agile marketing campaign development team. During sprint planning, the team has identified 15 user stories they believe they can complete based on their average velocity of 40 story points per sprint. However, two team members will be on vacation for one week during this three-week sprint. The total story points for the 15 stories equal 40. What should the team do?

August 16, 2026

2
ProcessAgileEasy

Your organization is transitioning to agile and you are leading your first Scrum project. At the end of the first sprint, the team has completed 80% of the committed user stories, but none of them fully meet the Definition of Done due to incomplete testing. The product owner is pressuring you to accept the stories as done so they can be demonstrated to stakeholders. What should you do?

August 16, 2026

3
ProcessAgileEasy

You are facilitating a daily standup for your agile development team. One team member mentions they are blocked because they are waiting for access to a testing environment that requires approval from the IT security team. This is the third day this issue has been raised. The team member asks what they should work on while waiting. What should you do as the Scrum Master or agile project leader?

August 16, 2026

4
ProcessAgileEasy

Your agile team is planning their next iteration. During the planning session, team members are estimating user stories using story points. A new developer on the team asks why the team uses story points instead of estimating in hours or days. The team lead explains that story points help with relative sizing. What is the primary benefit of using story points for estimation in agile projects?

August 16, 2026

5
ProcessAgileEasy

You are managing a software development project using Scrum. The team has just completed their second sprint and the product owner wants to see what has been developed. Several features have been coded and unit tested, but integration testing is still pending. The product owner asks when they can review the completed work. What should you do?

August 16, 2026

6
ProcessAgileEasy

You are facilitating sprint planning for a web development team. The product owner has prioritized 15 user stories for the upcoming sprint, but based on the team's velocity from the past three sprints (averaging 34 story points), this represents 52 story points of work. Several team members express concern about overcommitment. The product owner insists all stories are important and should be included. How should you proceed?

July 20, 2026

7
ProcessAgileEasy

Your agile team is working on a healthcare application project. A critical regulatory requirement emerges mid-sprint that must be implemented before the product can be released. The team has already committed to several user stories for the current two-week sprint and is on track to complete them. The new requirement will take approximately one week of effort. What is the best approach to handle this situation?

July 20, 2026

8
ProcessAgileEasy

You are the product owner for an e-commerce platform development project. The development team has completed several user stories related to the shopping cart functionality. During the sprint review, you notice that while the features work technically, they don't fully align with the customer experience you envisioned based on recent user feedback. The team is asking you to accept the stories as done. What should you do?

July 20, 2026

9
ProcessAgileEasy

Your agile team has just completed their third sprint of a mobile app development project. During the sprint retrospective, team members express frustration that they keep discovering new technical dependencies mid-sprint, causing them to miss their sprint commitments. The team wants to improve their planning process. What should the team do first to address this issue?

July 20, 2026

10
ProcessAgileEasy

You are managing a software development project using Scrum. During the daily standup, one team member mentions they are blocked because they are waiting for clarification from the product owner on a user story acceptance criterion. The product owner is not present at the standup meeting. Another team member suggests moving forward with their best interpretation of the requirement. What should you do as the Scrum Master?

July 20, 2026

11
ProcessAgileEasy

You are facilitating a sprint planning meeting for a three-week sprint. The product owner has presented the prioritized product backlog, and the team is discussing which user stories to commit to. One experienced developer suggests committing to 15 user stories, saying the team completed 12 last sprint and should push themselves. However, two team members will be on vacation for one week during this sprint. What should you do?

June 26, 2026

12
ProcessAgileEasy

Your agile team has completed a sprint and is conducting a sprint review with stakeholders. During the review, a key stakeholder sees the working software for the first time and requests significant changes to the user interface, saying it doesn't match their expectations. The team completed all committed user stories and met the acceptance criteria as originally defined. The stakeholder insists these changes must be made immediately. How should you respond?

June 26, 2026

13
ProcessAgileEasy

You are managing an agile software development project. The product owner has created a product backlog with 50 user stories but hasn't prioritized them yet. The development team is ready to start their first sprint planning meeting tomorrow. The product owner asks you what preparation is needed before the sprint planning session. What is the most important thing the product owner should do?

June 26, 2026

14
ProcessAgileEasy

Your agile team is working on a website redesign project for a retail client. During the daily standup, one developer mentions she is blocked because she's waiting for design assets from the UI/UX designer, who is working on another high-priority task. The developer has been blocked for two days. The team has a sprint goal to complete three user stories by the end of the week. What should you do first as the Scrum Master?

June 26, 2026

15
ProcessAgileEasy

You are leading an agile project to develop a mobile banking application. The team has just completed their second sprint and is preparing for the sprint retrospective. Several team members have mentioned challenges with the current definition of done, which seems unclear for certain user stories. As the project manager, you want to ensure the retrospective is productive and leads to actionable improvements. What should be the primary focus of this retrospective meeting?

June 26, 2026

16
ProcessAgileEasy

Your agile team is building an e-commerce platform. At the sprint review, the team demonstrates a completed shopping cart feature to stakeholders. The functionality works as specified in the user story, but the product owner notices the user interface colors don't match the company's recently updated brand guidelines, which changed during the sprint. What should happen next?

June 22, 2026

17
ProcessAgileEasy

You are facilitating sprint planning for a three-week sprint. The product owner presents the prioritized backlog, and the team begins selecting user stories. After selecting six stories totaling 24 story points, three team members mention they have committed to attending a mandatory company training program that will take them away for three full days during the sprint. What should the team do?

June 22, 2026

18
ProcessAgileEasy

During a sprint retrospective for your software development project, team members identify that unclear user story acceptance criteria have caused significant rework in the past three sprints. The team estimates that 30% of their time has been spent redoing work that didn't meet unstated expectations. What should the team do to address this issue?

June 22, 2026

19
ProcessAgileEasy

Your agile team is developing a customer relationship management (CRM) system. The product owner has created a prioritized product backlog with 45 user stories. Several stakeholders are asking when specific features will be delivered. The team has completed two sprints, delivering 12 and 11 story points respectively. What is the best way to provide stakeholders with delivery expectations?

June 22, 2026

20
ProcessAgileEasy

You are leading an agile project to develop a mobile banking application. The team has just completed Sprint Planning and committed to delivering eight user stories in the upcoming two-week sprint. During the daily standup on day three, a developer mentions that one of the stories is taking much longer than estimated and may not be completed. What should you do first?

June 22, 2026