Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
25 questions found
A project manager is leading a construction project to build a new manufacturing facility. During the planning phase, the sponsor asks how the project aligns with the organization's strategic objectives. The project manager reviews the project charter and identifies that the new facility will increase production capacity by 40%, directly supporting the company's five-year growth plan to expand market share. The sponsor requests a document that formally links the project to these strategic objectives. What document should the project manager provide?
August 11, 2026
A pharmaceutical company is managing a predictive project to develop a new drug delivery system. Six months into the 18-month project, a competitor announces they will release a similar product in 12 months. The project manager realizes this external change could significantly impact the project's market advantage and business value. The project is currently on schedule and within budget. What should the project manager do first?
August 11, 2026
A project manager is assigned to lead an infrastructure upgrade project for a government agency. During initial planning, the project manager learns that new regulatory requirements for data security will take effect in three months, midway through the planned project timeline. These regulations will mandate additional security controls that were not included in the original project scope. The project is using a predictive approach with a fixed budget. What is the most appropriate action?
August 11, 2026
A manufacturing company is implementing an ERP system using a predictive project approach. The project manager notices that the IT department, which will maintain the system after go-live, has not been actively involved in the project. The IT manager mentions they were not aware of specific technical requirements being finalized. The project is 60% complete, and user acceptance testing is scheduled to begin in six weeks. What should the project manager have done differently during project planning?
August 11, 2026
A project manager is leading a software development project for a retail company using a predictive waterfall methodology. Three months into the project, the company merges with another organization, and the new executive team announces a shift in corporate strategy toward e-commerce rather than brick-and-mortar operations. The current project focuses on in-store point-of-sale systems. The project manager's system is still technically needed but may have reduced priority. What is the best course of action?
August 11, 2026
You are leading a pharmaceutical research project to develop a new drug formulation. During risk identification workshops, your team identifies a risk that a key regulatory approval might be delayed by up to 6 months due to recent policy changes. The probability is assessed at 40% and the impact on project completion would be significant. What should you do with this information?
July 13, 2026
You are managing a product development project with a fixed budget of $500,000. At the end of month 3, your earned value analysis shows: Planned Value (PV) = $150,000, Earned Value (EV) = $120,000, and Actual Cost (AC) = $130,000. The project sponsor asks for a status update. What should you report about the project performance?
July 13, 2026
Your team is developing a project schedule for a manufacturing facility upgrade. You have identified all activities, sequenced them, and estimated their durations. Several team members have been assigned to multiple concurrent activities. What should you do next to complete the schedule development process?
July 13, 2026
You are managing a software implementation project using a waterfall approach. The testing phase has just begun, and the QA team reports that 15% of test cases are failing due to missing requirements that were not included in the requirements specification document approved three months ago. The client insists these requirements are essential. What is the best course of action?
July 13, 2026
You are managing a construction project to build a new office building. During the planning phase, you identify that specialized steel beams must be ordered from an overseas supplier with a 12-week lead time. The beams are needed in week 20 of the project schedule. Your team is currently in week 2 of the project. What should you do first?
July 13, 2026
You are managing a product development project using a predictive approach. The project management plan has been approved and execution has begun. During a team meeting, you realize that several team members are unclear about their specific responsibilities and who has decision-making authority for various project activities. This confusion is beginning to cause delays. What document should you reference or update to clarify these roles and responsibilities?
July 2, 2026
You are leading a predictive infrastructure project that is currently in the executing phase. A stakeholder who was not involved in initial planning requests a significant change to the project scope that would add new deliverables. The stakeholder insists the change is critical and wants it implemented immediately. What is the most appropriate action to take?
July 2, 2026
You are managing a manufacturing project to develop a new product line. During the execution phase, one of your team members discovers that a delivered component does not meet the specifications documented in the project requirements. The supplier claims the component meets industry standards, but it clearly does not match what was agreed upon in the procurement contract. What should be your first step?
July 2, 2026
You are planning a software implementation project for a financial services company. The project sponsor has approved a budget of $500,000. During cost planning, you need to establish a performance measurement baseline that will be used to monitor and control project costs throughout execution. The baseline should integrate scope, schedule, and cost to enable earned value management. What should you create?
July 2, 2026
You are managing a construction project to build a new office building. During the planning phase, you need to determine the total project duration by analyzing the sequence of activities and their dependencies. You have identified all activities, estimated their durations, and mapped out their logical relationships. What technique should you use to calculate the longest path through the project and identify the minimum project duration?
July 2, 2026
A project manager is planning a product development project for a consumer electronics company. The marketing department has provided market research indicating that consumer preferences in the target market are shifting toward environmentally sustainable products. The original product design, already approved by the steering committee, uses traditional materials and manufacturing processes. The project is in the early planning stages, with detailed design work scheduled to begin in two weeks. What should the project manager do to address this market intelligence?
June 29, 2026
A project manager is leading an infrastructure upgrade project for a financial services company. During project planning, the compliance officer informs the project manager that new data protection regulations will take effect six months before the planned project completion date. These regulations will require specific security controls to be implemented in the new infrastructure. The project schedule shows that infrastructure deployment is planned to begin in four months. What should the project manager do to ensure regulatory compliance?
June 29, 2026
A project manager is overseeing a software development project for a healthcare organization. The organization recently merged with another healthcare provider, creating a larger network of hospitals and clinics. Senior management has announced that all projects must now consider the needs of the expanded organization, which includes different geographical markets and patient demographics. The project manager's current project is 30% complete and was originally scoped for the pre-merger organization. What is the most appropriate action for the project manager to take?
June 29, 2026
A manufacturing company is implementing a new enterprise resource planning (ERP) system. The project manager has been asked to ensure the project aligns with the organization's strategic objectives. The company's CEO has communicated that the primary strategic goal for the next three years is to reduce operational costs by 20% while maintaining quality. The ERP implementation project is expected to cost $2 million and take 18 months to complete. How should the project manager demonstrate strategic alignment?
June 29, 2026
A project manager is leading a construction project to build a new office building. During the planning phase, the project manager learns that the city government is considering new building codes that could impact the project requirements. The building codes are expected to be finalized in three months, which is after the project is scheduled to begin construction. The project manager is concerned about potential impacts to the project scope and schedule. What should the project manager do first?
June 29, 2026
You have just been assigned as project manager for a new manufacturing project. During your first review of the project documentation, you find the project charter, stakeholder register, and several technical specifications. However, you cannot locate a document that clearly defines what is included and excluded from the project, along with the acceptance criteria for deliverables. Which document are you missing?
May 31, 2026
You are managing a pharmaceutical research project with a strict regulatory timeline. During a weekly team meeting, one of your scientists mentions that a required laboratory test is taking longer than expected due to equipment calibration issues. This task is on the critical path and any delay will impact the project completion date. What should you do first?
May 31, 2026
Your team has identified a risk that a key supplier might not deliver critical components on time, which would delay your project by two weeks. After analyzing the risk, you decide to order the components from a backup supplier who can guarantee delivery within your required timeframe, even though this will cost 15% more. What risk response strategy are you implementing?
May 31, 2026
You are leading a software development project using a predictive approach. The project has been ongoing for three months, and you need to report the current status to stakeholders. You calculate that the project has completed $150,000 worth of work, but you have actually spent $175,000. The planned value at this point was $160,000. What is the cost variance (CV) for this project?
May 31, 2026
You are managing a construction project to build a new office building. During the planning phase, you need to create a detailed breakdown of all the deliverables and work required to complete the project. Your sponsor has asked you to organize this information in a hierarchical structure that will serve as the foundation for planning, scheduling, and cost estimation. What should you create?
May 31, 2026