Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
35 questions found · page 1 of 2
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
September 24, 2026
Your manufacturing project has a budget of $500,000 and is scheduled to last 10 months. You are currently at the end of month 4. According to the project management plan, you should have spent $200,000 by now, but you have actually spent $180,000. The value of the work completed is $190,000. What is the Cost Variance (CV) for this project?
September 24, 2026
You are managing a government infrastructure project with strict documentation requirements. During a planning meeting, a stakeholder questions why you need to document lessons learned throughout the project rather than just at the end. The stakeholder is concerned about the additional administrative burden. What is the primary benefit of documenting lessons learned throughout the project lifecycle?
September 24, 2026
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
September 24, 2026
You are managing a construction project to build a new office facility. During project planning, you identify that concrete foundation work cannot begin until the excavation is complete and inspected. The concrete must cure for 7 days before framing can start. You need to document these relationships in your project schedule. What type of dependency exists between excavation and foundation work?
September 24, 2026
A project manager is assigned to deliver a new customer relationship management (CRM) system for a retail company. During the planning phase, the project manager learns that a major competitor has just launched a similar system with innovative features that customers are responding to positively. The sponsor is concerned about market positioning. The project requirements have been approved and baselined. What should the project manager recommend?
September 18, 2026
A project manager is leading a government infrastructure project with a fixed contract of $5 million and a timeline of 18 months. Three months into the project, new environmental regulations are passed that will require additional permitting and compliance documentation. The sponsor asks the project manager how this will affect the project. What should the project manager do first?
September 18, 2026
A pharmaceutical company is executing a project to upgrade its laboratory information management system using a waterfall methodology. Six months into the 18-month project, a new data privacy law is enacted that requires additional security controls and audit capabilities. The compliance deadline is 10 months away. The project manager has verified that the new requirements were not anticipated in the original scope. What is the first step the project manager should take?
September 18, 2026
A project manager is leading a construction project for a new office building using a predictive approach. The local government announces plans to build a new subway station near the project site, which will begin construction in 12 months. This development is expected to significantly increase property values in the area. Several stakeholders suggest the project manager should redesign the building to add more floors to capitalize on this opportunity. The project is currently in the execution phase with 40% completion. What should the project manager do?
September 18, 2026
A manufacturing company is implementing a new enterprise resource planning (ERP) system using a waterfall approach. The CFO informs the project manager that the company's quarterly financial results show declining revenue, and there may be budget cuts across all departments next quarter. The project is currently in the design phase and is on track with its baseline. What is the most appropriate action for the project manager?
September 18, 2026
A project manager is leading a construction project to build a new manufacturing facility. During the planning phase, the sponsor asks how the project aligns with the organization's strategic objectives. The project manager reviews the project charter and identifies that the new facility will increase production capacity by 40%, directly supporting the company's five-year growth plan to expand market share. The sponsor requests a document that formally links the project to these strategic objectives. What document should the project manager provide?
August 11, 2026
A pharmaceutical company is managing a predictive project to develop a new drug delivery system. Six months into the 18-month project, a competitor announces they will release a similar product in 12 months. The project manager realizes this external change could significantly impact the project's market advantage and business value. The project is currently on schedule and within budget. What should the project manager do first?
August 11, 2026
A project manager is assigned to lead an infrastructure upgrade project for a government agency. During initial planning, the project manager learns that new regulatory requirements for data security will take effect in three months, midway through the planned project timeline. These regulations will mandate additional security controls that were not included in the original project scope. The project is using a predictive approach with a fixed budget. What is the most appropriate action?
August 11, 2026
A manufacturing company is implementing an ERP system using a predictive project approach. The project manager notices that the IT department, which will maintain the system after go-live, has not been actively involved in the project. The IT manager mentions they were not aware of specific technical requirements being finalized. The project is 60% complete, and user acceptance testing is scheduled to begin in six weeks. What should the project manager have done differently during project planning?
August 11, 2026
A project manager is leading a software development project for a retail company using a predictive waterfall methodology. Three months into the project, the company merges with another organization, and the new executive team announces a shift in corporate strategy toward e-commerce rather than brick-and-mortar operations. The current project focuses on in-store point-of-sale systems. The project manager's system is still technically needed but may have reduced priority. What is the best course of action?
August 11, 2026
You are leading a pharmaceutical research project to develop a new drug formulation. During risk identification workshops, your team identifies a risk that a key regulatory approval might be delayed by up to 6 months due to recent policy changes. The probability is assessed at 40% and the impact on project completion would be significant. What should you do with this information?
July 13, 2026
You are managing a product development project with a fixed budget of $500,000. At the end of month 3, your earned value analysis shows: Planned Value (PV) = $150,000, Earned Value (EV) = $120,000, and Actual Cost (AC) = $130,000. The project sponsor asks for a status update. What should you report about the project performance?
July 13, 2026
Your team is developing a project schedule for a manufacturing facility upgrade. You have identified all activities, sequenced them, and estimated their durations. Several team members have been assigned to multiple concurrent activities. What should you do next to complete the schedule development process?
July 13, 2026
You are managing a software implementation project using a waterfall approach. The testing phase has just begun, and the QA team reports that 15% of test cases are failing due to missing requirements that were not included in the requirements specification document approved three months ago. The client insists these requirements are essential. What is the best course of action?
July 13, 2026
You are managing a construction project to build a new office building. During the planning phase, you identify that specialized steel beams must be ordered from an overseas supplier with a 12-week lead time. The beams are needed in week 20 of the project schedule. Your team is currently in week 2 of the project. What should you do first?
July 13, 2026
You are managing a product development project using a predictive approach. The project management plan has been approved and execution has begun. During a team meeting, you realize that several team members are unclear about their specific responsibilities and who has decision-making authority for various project activities. This confusion is beginning to cause delays. What document should you reference or update to clarify these roles and responsibilities?
July 2, 2026
You are leading a predictive infrastructure project that is currently in the executing phase. A stakeholder who was not involved in initial planning requests a significant change to the project scope that would add new deliverables. The stakeholder insists the change is critical and wants it implemented immediately. What is the most appropriate action to take?
July 2, 2026
You are managing a manufacturing project to develop a new product line. During the execution phase, one of your team members discovers that a delivered component does not meet the specifications documented in the project requirements. The supplier claims the component meets industry standards, but it clearly does not match what was agreed upon in the procurement contract. What should be your first step?
July 2, 2026
You are planning a software implementation project for a financial services company. The project sponsor has approved a budget of $500,000. During cost planning, you need to establish a performance measurement baseline that will be used to monitor and control project costs throughout execution. The baseline should integrate scope, schedule, and cost to enable earned value management. What should you create?
July 2, 2026
You are managing a construction project to build a new office building. During the planning phase, you need to determine the total project duration by analyzing the sequence of activities and their dependencies. You have identified all activities, estimated their durations, and mapped out their logical relationships. What technique should you use to calculate the longest path through the project and identify the minimum project duration?
July 2, 2026