Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
55 questions found · page 1 of 3
You are managing an enterprise software implementation project following a waterfall approach. The project has a core team of eight people, including business analysts, developers, and testers. You've noticed that during team meetings, three team members consistently dominate discussions while the other five rarely contribute ideas or feedback. The quieter team members have valuable expertise that could benefit the project. What should you do to improve team participation?
November 14, 2026
You are managing a manufacturing project with a detailed project schedule and assigned resources. The project sponsor has requested that you prepare a resource management plan. You need to document how you will acquire, develop, and manage the project team throughout the project lifecycle. Which of the following should be included in this plan?
November 14, 2026
You are managing a product development project using a predictive methodology. During a weekly team meeting, one of your team members publicly criticizes another team member's work quality on a recent deliverable, stating it was 'sloppy and unprofessional.' The criticized team member becomes visibly upset and defensive. The tension in the room is affecting the rest of the meeting. How should you respond to this situation?
November 14, 2026
You are leading a construction project following a predictive approach. A new civil engineer has joined your team, replacing someone who left the company. The new engineer has strong technical credentials but has never worked on this type of infrastructure project before. Your project is currently in the execution phase, and the work breakdown structure shows that foundation work will begin in three weeks. What is the most appropriate action to help integrate this team member?
November 14, 2026
You are managing a predictive software development project with a team of 12 developers. During the planning phase, you notice that two senior developers have conflicting ideas about the technical architecture approach. The disagreement is causing delays in finalizing the technical design document, which is needed before coding can begin. The project schedule shows that the design phase should be completed in two weeks. What should you do first?
November 14, 2026
You are managing an infrastructure upgrade project using a predictive approach. During the execution phase, one of your high-performing team members requests to attend a three-day industry conference that conflicts with a critical project milestone. The team member believes the conference content would be valuable for their professional development. However, their absence could impact the milestone delivery. What should you do?
November 11, 2026
You have just been assigned as project manager for a regulatory compliance project with a fixed deadline in 12 months. The project charter has been approved and you are beginning detailed planning. You need to build your project team, but the functional managers control the resources in your organization. Several functional managers have indicated they can only provide resources with limited availability. What should you do first?
November 11, 2026
You are managing a manufacturing project following a predictive life cycle. During project execution, you notice that two team members who must collaborate closely on sequential tasks have very different communication styles. One prefers detailed written documentation while the other prefers quick verbal updates. This difference has started to cause minor delays as they struggle to coordinate effectively. What should you do?
November 11, 2026
You are leading a construction project with a detailed work breakdown structure and schedule. One of your experienced team members approaches you privately and expresses concerns that a newer team member is not following the established safety procedures documented in the project management plan. The newer team member has not caused any incidents yet, but the experienced member is worried about potential risks. What is the best course of action?
November 11, 2026
You are managing a software development project using a waterfall approach. During the planning phase, you identify that the testing team will need specialized training on new security testing tools before the testing phase begins in six months. The training vendor requires a three-month advance booking. Your team members are currently fully allocated to other projects. What should you do first?
November 11, 2026
You have just been assigned as project manager for a new manufacturing project that will use a predictive approach. The project sponsor has approved the project charter, and you are beginning to assemble the project team. Several functional managers have expressed concerns about releasing their best resources for your project. What should you do to secure the resources you need?
November 4, 2026
You are managing a government project using a waterfall approach with a team of 15 people. During the execution phase, you notice that two team members from different departments are having difficulty collaborating on a shared deliverable. They have different working styles and have begun avoiding each other, which is causing delays. What is the best way to address this situation?
November 4, 2026
You are leading a construction project with a detailed project schedule created using the critical path method. A key team member with specialized welding skills will be needed during weeks 8-12 of the project. However, this resource is currently assigned to another project and will not be available until week 10. What should you do first?
November 4, 2026
You are the project manager for a software development project following a waterfall methodology. One of your senior developers has been consistently arriving late to the daily status meetings and missing important updates. This is starting to impact the team's coordination. You have spoken to the developer informally, but the behavior continues. What is the most appropriate next step?
November 4, 2026
You are managing a large infrastructure project using a waterfall approach. During the planning phase, you need to document the roles and responsibilities for all team members and stakeholders. Several team members have overlapping skills, and you want to ensure there is no confusion about who is accountable for each deliverable. What should you create to clearly define these accountabilities?
November 4, 2026
You have just been assigned as the project manager for a bridge construction project that will take 18 months. The project charter has been signed by the sponsor, and you are beginning the planning phase. You need to identify all individuals, groups, and organizations that could impact or be impacted by the project. What process are you performing?
November 2, 2026
Your manufacturing project has been running for three months. During a quality inspection, you discover that 15% of the produced components do not meet the specifications defined in the quality management plan. Production is continuing, but you are concerned about the trend. What should be your immediate course of action?
November 2, 2026
You are managing a software implementation project for a healthcare client. During a requirements gathering session, the client's Chief Medical Officer requests a new feature that was not included in the original project scope statement or WBS. The feature would add significant value but also increase costs and timeline. What should you do first?
November 2, 2026
Your project to develop a new financial reporting system has a budget of $500,000 and is scheduled to take 10 months. You are currently at the end of month 4. According to your tracking, you have spent $220,000 and completed work that was budgeted at $180,000. What is the cost performance of your project at this point?
November 2, 2026
You are managing a construction project to build a new office building. During the planning phase, your team has identified all project activities and estimated their durations. You now need to determine when each activity should start and finish, considering their dependencies and resource constraints. What tool or technique should you use to create a visual timeline showing the project schedule?
November 2, 2026
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
September 24, 2026
Your manufacturing project has a budget of $500,000 and is scheduled to last 10 months. You are currently at the end of month 4. According to the project management plan, you should have spent $200,000 by now, but you have actually spent $180,000. The value of the work completed is $190,000. What is the Cost Variance (CV) for this project?
September 24, 2026
You are managing a government infrastructure project with strict documentation requirements. During a planning meeting, a stakeholder questions why you need to document lessons learned throughout the project rather than just at the end. The stakeholder is concerned about the additional administrative burden. What is the primary benefit of documenting lessons learned throughout the project lifecycle?
September 24, 2026
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
September 24, 2026
You are managing a construction project to build a new office facility. During project planning, you identify that concrete foundation work cannot begin until the excavation is complete and inspected. The concrete must cure for 7 days before framing can start. You need to document these relationships in your project schedule. What type of dependency exists between excavation and foundation work?
September 24, 2026
