PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

105 questions found · page 4 of 5

76
PeoplePredictiveMedium

You are managing a large infrastructure project with a team of 45 members across multiple departments. During the weekly status meeting, two senior engineers from different functional areas have a heated disagreement about the technical approach for a critical deliverable. The conflict is affecting team morale, and other team members are beginning to take sides. The project is currently on schedule, but this issue could impact the next milestone in three weeks. What should you do first as the project manager?

June 17, 2026

77
PeoplePredictiveMedium

You are managing a construction project that is entering the execution phase. During resource planning, you identified that three specialized technicians are needed for a critical phase starting in six weeks. Your functional manager has just informed you that due to competing organizational priorities, only two of the three requested technicians will be available. The project baseline assumed all three resources would be available, and this shortage will likely extend the project schedule by two weeks. What should you do next?

June 17, 2026

78
PeoplePredictiveMedium

You are managing a multi-phase engineering project that is currently in month 8 of a 16-month schedule. During performance reviews, you notice that four team members who joined the project three months ago are not integrating well with the existing team. They frequently work in isolation, miss key communications, and their deliverables require significant rework. The original team members have mentioned feeling frustrated with the additional coordination effort. These four members were added to accelerate the project schedule, but productivity has not improved as expected. What is the best approach to address this situation?

June 17, 2026

79
PeoplePredictiveMedium

You are managing a product development project for a manufacturing company. A team member from the quality assurance department approaches you privately and expresses concern that another team member from engineering has been taking shortcuts in the testing protocols to meet schedule deadlines. The QA team member has evidence of incomplete test documentation but is reluctant to raise the issue directly because the engineering team member is senior and well-connected in the organization. The project is currently showing green status, but you know that quality issues could have serious compliance implications. How should you address this situation?

June 17, 2026

80
PeoplePredictiveMedium

You are leading a predictive software development project for a financial institution. A key developer who is responsible for the security module has been consistently missing deadlines over the past three weeks. This developer was previously a high performer. During a one-on-one conversation, you learn that they are dealing with a personal family situation that requires significant attention. The security module is on the critical path, and any further delays will impact the project delivery date committed to the sponsor. What is the most appropriate course of action?

June 17, 2026

81
PeopleHybridMedium

You are managing a hybrid project with a distributed team across three time zones. The agile components use Scrum with daily standups at 9 AM EST, while the waterfall components have weekly status meetings at 10 AM EST. Team members in the Pacific time zone (6 AM and 7 AM their local time) have complained these meeting times are difficult. One team member has started skipping standups, and another has requested to send written updates instead. Productivity metrics show the Pacific team's velocity declining. How should you address this situation?

June 9, 2026

82
PeopleHybridMedium

Your organization is transitioning to hybrid project delivery. You are managing a project where the design phase is planned using predictive methods with detailed requirements, while development will use iterative sprints. During design phase completion, your most experienced business analyst accepts a position at another company and will leave in two weeks. The development team is scheduled to start sprints immediately after the design phase ends. What should be your primary focus to ensure team continuity?

June 9, 2026

83
PeopleHybridMedium

You are leading a hybrid project where feature development follows Scrum, but infrastructure deployment requires formal change control and approval gates. A senior developer who has extensive experience with agile approaches has been openly criticizing the change control process in team channels, calling it 'bureaucratic waste' and discouraging newer team members from following it. This is creating tension with the operations team who manages the approval gates. What is the most appropriate way to address this situation?

June 9, 2026

84
PeopleHybridMedium

Your hybrid project team consists of eight developers working in sprints and four business analysts following a stage-gate process. You notice that the developers rarely interact with the business analysts, leading to misaligned requirements. The project sponsor has emphasized the importance of knowledge sharing across the team. One developer mentions they prefer written documentation over meetings. How should you best facilitate knowledge transfer between these groups?

June 9, 2026

85
PeopleHybridMedium

You are managing a hybrid project where the development team works in two-week sprints while the regulatory compliance team follows a traditional waterfall approach. During a retrospective, several development team members express frustration that compliance reviews are causing delays at the end of each sprint. The compliance team lead explains they need at least five business days to review deliverables but are only notified when the sprint ends. What should you do first to address this conflict?

June 9, 2026

86
PeopleAgileMedium

A Scrum Master notices that during the past four sprints, team members have been working significant overtime to complete their sprint commitments. While they are meeting their sprint goals, team morale surveys indicate increasing stress and work-life balance concerns. Three team members have recently mentioned feeling burned out. The Product Owner is pleased with the team's output and wants to maintain the current pace. When the Scrum Master raises concerns, the Product Owner argues that the team voluntarily commits to the work during sprint planning. How should the Scrum Master address this situation?

June 6, 2026

87
PeopleAgileMedium

A cross-functional agile team is preparing for their next sprint. During sprint planning, the QA specialist expresses concern that the team has been committing to user stories without adequately considering testing effort. She feels that her input is often sought too late in the process, after developers have already estimated and committed to stories. This has resulted in quality issues and testing becoming a bottleneck in the last two sprints. The team wants to improve but is unsure how to better integrate QA perspective earlier. What should the team do?

June 6, 2026

88
PeopleAgileMedium

During a sprint retrospective, a senior developer consistently dominates the conversation, speaking for 80% of the meeting time. Several junior team members have stopped participating and appear disengaged. The Scrum Master notices this pattern has occurred in the last three retrospectives. The team's velocity has been declining, and post-retrospective surveys show decreased satisfaction among junior members. What should the Scrum Master do to address this situation?

June 6, 2026

89
PeopleAgileMedium

An agile team of eight members has been working together for three months. The Product Owner notices that two developers, who are both highly skilled but have different technical philosophies, frequently disagree during daily standups and refinement sessions. These disagreements sometimes delay decisions and create tension. Other team members have started avoiding technical discussions when both developers are present. Yesterday, a refinement session ended early because the disagreement escalated into a heated argument. What is the most appropriate action for addressing this conflict?

June 6, 2026

90
PeopleAgileMedium

An agile team has two new members who joined three weeks ago. The existing team members have been working together for over a year and have well-established working relationships and informal communication patterns. The new members are competent but seem hesitant to speak up in team meetings. During the last sprint review, neither new member presented any of their completed work, even though they contributed significantly to the increment. One existing team member mentioned that the new developers 'just need more time to adjust.' What should the team lead do to better integrate the new members?

June 6, 2026

91
PeopleAgileMedium

During a sprint retrospective, your agile team identifies that knowledge silos have formed around specific technical components. Only one person understands the payment integration module, and only another person understands the reporting engine. This has caused delays when those individuals are unavailable and has created bottlenecks during code reviews. The team agrees this is a problem but is unsure how to address it given their current sprint commitments and competing priorities. What should you recommend as the most effective solution?

June 5, 2026

92
PeopleAgileMedium

Your distributed agile team spans three time zones across North America, Europe, and Asia. Team members have complained that the current sprint ceremonies (planning, review, retrospective, and daily stand-ups) don't work well for everyone. Some team members attend meetings very early in their morning or late at night, leading to reduced participation and energy. The team has delivered successfully for two sprints, but engagement is declining. What approach would best support the team's continued collaboration and performance?

June 5, 2026

93
PeopleAgileMedium

You are coaching a product owner who is new to agile approaches. She has been attending all daily stand-ups and frequently interrupts team members to ask detailed questions about their work, provide suggestions, and redirect their efforts based on new information she receives from stakeholders. Team members have started arriving late to stand-ups, and the meetings now regularly run 30 minutes instead of the intended 15 minutes. The development team has privately expressed frustration to you about the product owner's behavior. What is the best way to address this situation?

June 5, 2026

94
PeopleAgileMedium

Your agile team has been working together for three months and has established a good rhythm. During sprint planning, two developers disagree about the technical approach for a critical user story. The disagreement becomes heated, with each developer defending their position strongly. The rest of the team appears uncomfortable, and the planning session has stalled for 20 minutes. Both proposed approaches are technically viable but represent different trade-offs between speed and maintainability. How should you facilitate resolution?

June 5, 2026

95
PeopleAgileMedium

You are leading an agile project with a newly formed team. During the first two sprints, you notice that one team member, Sarah, consistently remains quiet during daily stand-ups and retrospectives. When she does speak, her contributions are valuable, but she appears uncomfortable in group settings. Other team members have started making decisions without her input. The team's velocity is acceptable, but you sense Sarah's potential is not being fully utilized. What should you do first to address this situation?

June 5, 2026

96
PeopleHybridMedium

You're leading a hybrid project in a matrix organization where team members report to functional managers while working on your project. A high-performing business analyst has been contributing to agile ceremonies and producing excellent work. Her functional manager now wants to reassign her to another priority project, which would significantly impact your project's analysis capability during a critical phase. When you discuss this with the business analyst, she mentions feeling burned out from working long hours to satisfy both your expectations and her functional manager's demands. How should you address this situation?

June 1, 2026

97
PeopleHybridMedium

Your hybrid project team consists of five co-located members following agile practices and three remote members managing waterfall-based procurement and vendor contracts. The remote members rarely participate in daily standups, citing time zone differences and claiming the meetings aren't relevant to their work. Co-located team members complain they're unaware of vendor delays until major issues arise. The remote members feel excluded from project celebrations and recognition. What strategy would best build cohesion across this distributed hybrid team?

June 1, 2026

98
PeopleHybridMedium

You are managing a hybrid software project where features are developed using Scrum, but regulatory compliance reviews follow a stage-gate process. A critical sprint deliverable has been completed and tested, but it cannot be released until passing a compliance review scheduled in three weeks. The product owner wants to continue building dependent features in the next sprint. Team members are concerned this creates risk if compliance findings require rework. The compliance team cannot accelerate their review schedule. What approach best balances team empowerment with risk management?

June 1, 2026

99
PeopleHybridMedium

Your organization is transitioning to hybrid project delivery. You're leading a project where experienced waterfall team members are now required to work alongside a newly formed agile team. During the first iteration planning meeting, you notice the waterfall-experienced members remain silent while agile team members dominate the conversation. After the meeting, two senior waterfall practitioners privately tell you they don't understand the agile terminology and feel their expertise is being dismissed. How should you best support these team members?

June 1, 2026

100
PeopleHybridMedium

You are managing a hybrid project where the development team follows Scrum while the infrastructure team uses a waterfall approach. During a retrospective, several developers express frustration that infrastructure delays are blocking their sprint goals. The infrastructure lead explains their team must follow a strict change control process that takes 2-3 weeks for approvals. Team morale is declining as developers feel their efforts are wasted. What should you do first to address this conflict?

June 1, 2026