Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
60 questions found · page 1 of 3
You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?
November 11, 2026
During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?
November 11, 2026
You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?
November 11, 2026
Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?
November 11, 2026
You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?
November 11, 2026
You are managing a product development project with multiple external vendors. One vendor has submitted an invoice for $85,000 for completed work. Your procurement specialist reviews the invoice against the contract and identifies that the deliverables match the contract requirements, but notices the vendor applied a 5% price increase that was not in the original fixed-price contract. The vendor claims the increase was discussed verbally with a team member due to scope changes. Your team member confirms a conversation occurred but no formal change was processed. What should you do?
October 25, 2026
Your project team is developing a detailed project schedule for a 16-month infrastructure project. During schedule network analysis, you identify that the critical path has 18 months of duration, exceeding the required completion date by 2 months. You have identified a sequence of activities on the critical path where design and procurement activities could be overlapped to save time. However, overlapping these activities will increase project risk and may require additional design resources. What technique are you considering, and what is the most important factor to evaluate before implementing it?
October 25, 2026
You are managing a manufacturing facility expansion project. During a quality audit, the auditor identifies that three deliverables were completed without the required inspections documented in the quality management plan, though the deliverables appear to meet specifications. The project is currently on schedule and within budget. The construction manager argues that the inspections are bureaucratic and the work quality is evident. What should you do first?
October 25, 2026
During the planning phase of a software development project, your team has identified 47 risks. You've completed qualitative risk analysis and are now preparing for quantitative risk analysis. The project sponsor questions why you need to spend additional time and budget on quantitative analysis when risks have already been prioritized. The project has a firm deadline for regulatory compliance and a contingency reserve of 10% has been allocated. What is the strongest justification for conducting quantitative risk analysis?
October 25, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. After 6 months, the project has spent $1.1 million and completed work valued at $900,000 according to the baseline. The planned value at this point was $1 million. Senior management is concerned about project performance and asks for your assessment. What is the most critical performance issue you should address first?
October 25, 2026
You are managing a product development project that is currently in the testing phase. During a quality audit, the quality assurance team identifies that three deliverables do not meet the quality standards defined in the quality management plan, though they meet the customer's acceptance criteria as stated in the scope statement. The rework required to meet the quality standards would cost an additional $35,000 and delay the project by two weeks. The customer has not complained and seems satisfied with the current deliverables. What should you do?
October 12, 2026
Your project team has completed the WBS decomposition for a 14-month infrastructure project. During the Define Activities process, a senior team member suggests that some work packages are still too large and should be broken down further into activities. Another team member argues that the current work packages are appropriate and further decomposition would create unnecessary detail. The work packages in question represent 3-4 weeks of work each. As the project manager, how should you handle this situation?
October 12, 2026
You are managing a software implementation project for a government agency using a waterfall approach. The requirements documentation has been approved and baselined. During the design phase, the compliance officer identifies a new regulatory requirement that was published last month and will be effective in three months. Implementing this requirement would require changes to 15% of the approved requirements and add approximately $75,000 to the $500,000 budget. The project is currently on schedule and within budget. What should you do FIRST?
October 12, 2026
During the execution phase of a manufacturing facility upgrade project, a key supplier informs you that a critical component will be delayed by three weeks due to supply chain disruptions. This component is on the critical path and is needed for installation activities scheduled to begin in four weeks. You have a contingency reserve allocated in the budget, and the schedule baseline includes buffer time but not specifically for this activity. The delay will impact subsequent critical path activities. What is the BEST course of action?
October 12, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 12-month timeline. After six months, the project has completed 40% of the planned work and spent $1.3 million. The project sponsor is concerned about cost performance and asks you to provide an analysis. Based on earned value metrics, you calculate that CPI is 0.77 and SPI is 0.80. The sponsor wants to know if the project can be completed within the original budget if current performance continues. What should you recommend?
October 12, 2026
You are managing a pharmaceutical research project following a stage-gate process. Your project has just completed the Phase 2 clinical trials deliverable. According to the project management plan, a phase gate review is scheduled before proceeding to Phase 3 trials, which will require significant investment. During your preparation for the gate review, you discover that while the trials met their primary endpoint, two secondary endpoints showed concerning trends. The data is not conclusive but suggests potential issues. The project is currently on schedule and under budget. What should you do?
October 7, 2026
Your project team has completed the project scope statement and is now developing the work breakdown structure (WBS). One of your team members suggests creating work packages at different levels of decomposition across the WBS—some at a very detailed level that can be completed in days, and others at a higher level representing several weeks of work. The team member argues this will save time in the planning process. What is the best approach?
October 7, 2026
You are managing a software development project using a waterfall methodology. During the design phase, your technical lead identifies that implementing a requested feature will require a third-party library that introduces significant security vulnerabilities. The feature was explicitly defined in the approved scope baseline and is important to the customer. After analysis, your team proposes an alternative technical approach that provides similar functionality without the security risk but will add $15,000 to the project cost. What should you do?
October 7, 2026
Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?
October 7, 2026
You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?
October 7, 2026
You are managing a pharmaceutical research project following a stage-gate predictive methodology. Your project has just completed the design phase, and you are preparing for the gate review before entering the development phase. During preparation, you discover that one of the key assumptions documented in the project charter—that a specific research facility would be available—is no longer valid due to facility renovations. The next available equivalent facility is in a different location and would increase project costs by 8%. What should you do BEFORE the gate review?
September 29, 2026
You are managing a large infrastructure project with multiple subcontractors. One of your key vendors has completed their deliverable, and you are conducting procurement closure activities. While reviewing the final deliverable, you notice it meets all technical specifications in the contract, but the vendor failed to submit three required progress reports during execution as stipulated in the contract terms. The vendor is requesting final payment and contract closure. What is the MOST appropriate action?
September 29, 2026
You are managing a software implementation project for a financial institution using a waterfall approach. During quality testing, the QA team discovers that 12% of test cases are failing, primarily related to security authentication features. The quality management plan specified that no more than 5% of test cases should fail at this stage. The development team believes they can fix the issues within one week, but this will delay the scheduled user acceptance testing. What should you do?
September 29, 2026
Your manufacturing project is in the planning phase, and you are developing the cost baseline. You have completed bottom-up estimating for all work packages and have aggregated these costs. The finance department requires a 10% management reserve for organizational risks, and historical data shows similar projects typically experience 15% cost variance. Your project sponsor asks what the final project budget should include. What is the MOST appropriate approach?
September 29, 2026
You are managing a construction project using a predictive approach. During the execution phase, a key supplier informs you that critical materials will be delayed by three weeks due to manufacturing issues. The delay will impact the critical path and push the project completion date beyond the contractually agreed deadline. Several team members suggest crashing the schedule by adding overtime resources, while the sponsor wants to explore fast-tracking options. What should you do FIRST?
September 29, 2026
