Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
60 questions found · page 3 of 3
You are managing a complex aerospace engineering project with a 36-month timeline using earned value management (EVM) for performance tracking. Your project has a CPI of 0.89 and SPI of 0.92 at the 12-month mark. The executive steering committee is considering canceling the project due to poor performance. Your analysis reveals that performance issues are concentrated in one engineering team led by a manager who has been with the company for 18 years and has strong relationships with senior executives. This manager is resistant to your process improvement suggestions and has stated that 'engineering excellence cannot be rushed.' Other team leads have privately expressed frustration with this manager's team missing dependencies. The manager's functional director is defensive of their employee and suggests the schedule was unrealistic from the start. What should be your PRIMARY focus to address this situation?
June 1, 2026
You are managing a multinational IT implementation project with team members across five countries spanning four time zones. The project follows a traditional waterfall approach with phase gates. Your project management office (PMO) requires weekly status meetings with all core team members present. After three months, you notice declining participation, with team members frequently joining late, multitasking during meetings, or sending delegates. Survey feedback reveals that team members find the meetings unproductive and poorly timed for their time zones. However, the PMO director insists the meeting format is a governance requirement and cannot be changed. Your sponsor is concerned about team engagement scores dropping from 85% to 62%. What is the BEST way to address this situation?
June 1, 2026
You are managing a government construction project with a fixed-price contract and a defined scope. Six months into the 18-month project, a new government regulation is enacted that requires additional safety measures, impacting 30% of the completed work and all remaining work. Your project team is demoralized because they believe they will need to redo work that was compliant at the time of completion. The compliance officer insists all work must meet the new standards before final acceptance. The sponsor indicates no additional budget is available and expects you to absorb the changes. During a team meeting, several senior team members openly criticize the sponsor's position and question the project's viability. How should you address this situation?
June 1, 2026
You are leading a pharmaceutical product development project following a waterfall methodology with strict regulatory requirements. Your quality manager reports that three team members from the testing department have been consistently missing defect documentation deadlines, causing delays in the validation phase. Upon investigation, you discover these team members are also assigned to two other critical projects and are working 60-70 hours per week. The functional manager states they cannot provide additional resources due to budget constraints. The testing phase must be completed in four weeks to meet the regulatory submission deadline. What is the MOST effective approach to address this situation?
June 1, 2026
You are managing a large infrastructure project with a 24-month timeline using a predictive approach. During the execution phase, your technical lead, who has been with the project since initiation and possesses critical knowledge about legacy system integrations, submits their resignation with a two-week notice. The project is currently 40% complete, and the integration work is scheduled to begin in six weeks. Your sponsor is concerned about the impact on the project schedule and is pressuring you to immediately hire a replacement at a higher salary to retain institutional knowledge. What should be your FIRST action as the project manager?
June 1, 2026
You are managing a large infrastructure project using a waterfall approach. During the execution phase, you notice that two senior engineers from different departments are having ongoing disagreements about technical specifications, causing delays in critical path activities. Both engineers are subject matter experts and report to different functional managers, not to you. The disagreements are escalating and beginning to affect team morale. What should you do first?
May 29, 2026
You are managing a construction project using a traditional waterfall approach. The project is in the execution phase, and you have a geographically distributed team with members across three different time zones. You notice that team members in the remote locations seem less engaged during virtual meetings and are often unaware of important decisions made by the core team at headquarters. Productivity metrics show that deliverables from remote team members are occasionally misaligned with project requirements. How should you address this situation?
May 29, 2026
You are managing a multi-year government infrastructure project using a predictive approach. Six months into execution, a key technical lead who has been with the project since initiation submits their resignation, citing a better opportunity elsewhere. This individual possesses critical knowledge about design decisions and has established relationships with several government stakeholders. Their departure is scheduled for three weeks from now. The project is currently on track, but several complex deliverables are planned for the next quarter. What is your best course of action?
May 29, 2026
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
May 29, 2026
You are managing a software implementation project using a waterfall methodology for a financial services client. During the design phase, you discover that one of your key business analysts, who is responsible for defining critical system requirements, lacks experience with the specific regulatory compliance requirements of the financial industry. This knowledge gap was not apparent during resource assignment. The design phase is scheduled to complete in six weeks, and this analyst is already assigned full-time to your project. What should you do?
May 29, 2026
