Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
485 questions found · page 2 of 20
A project manager is executing a government contract project using a predictive approach. The project has strict compliance requirements and formal change control processes. A new technology solution becomes available that could reduce project costs by 15% and improve the final product's performance. However, implementing this technology would require significant design changes and extend the schedule by two months. The contract includes performance incentives for early completion. What should the project manager evaluate first when considering this opportunity?
November 11, 2026
A project manager is leading a manufacturing facility expansion project. Six months into the 18-month project, the company announces a merger with a competitor. The merger brings uncertainty about future facility requirements, as the combined organization may need different capacity than originally planned. The project baseline called for doubling production capacity, but the merger may change this requirement significantly. Senior leadership has not yet decided whether to continue, pause, or cancel the project. What should the project manager do?
November 11, 2026
A project manager is leading an infrastructure upgrade project for a financial services company. During execution, a major economic downturn occurs, and the organization announces a 20% budget cut across all projects. The CFO has requested all project managers to identify cost reduction options. The project is currently on schedule and within budget, with 30% of the work completed. Several vendors have already been contracted for upcoming phases. What should the project manager prioritize when developing cost reduction recommendations?
November 11, 2026
A pharmaceutical project manager is overseeing a new drug development project using a predictive approach. During the planning phase, the project team identifies that a key competitor has announced a similar product launch scheduled six months before their planned release date. The executive leadership is pressuring the project manager to accelerate the timeline to maintain competitive advantage. However, the project includes mandatory regulatory approval phases that cannot be compressed. What is the best course of action?
November 11, 2026
A project manager is leading a predictive construction project when new environmental regulations are announced that will affect the project's compliance requirements. The project is 40% complete, and the regulations will take effect in three months, midway through the project timeline. The regulatory changes will require additional environmental impact assessments and potentially design modifications. Stakeholders are concerned about project costs and schedule. What should the project manager do first?
November 11, 2026
An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?
November 11, 2026
Your agile team is developing a financial reporting system for a highly regulated industry. During the sprint, a new compliance regulation is announced that affects functionality planned for the next three sprints. The product owner wants to immediately pivot to address the compliance requirement, which would mean abandoning partially completed work from the current sprint. The team is five days into a two-week sprint and has completed about 60% of their committed work. What should the Scrum Master recommend?
November 11, 2026
A software development team is working on a cloud migration project using Scrum. During the sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though it meets all the acceptance criteria defined in the user stories. The product owner approved these acceptance criteria during backlog refinement two weeks ago. Several stakeholders express disappointment and suggest the team wasted the sprint. What is the most appropriate action for the team to take?
November 11, 2026
An agile project team is building a customer portal for an insurance company. During sprint planning, the development team estimates that the highest-priority user story will take 13 story points to complete, but the team's average velocity is only 35 points per two-week sprint and they have already committed to 28 points of other work. The product owner insists this story must be included because a major client has requested this feature for a demo in three weeks. The team is concerned about over-committing. How should the team proceed?
November 11, 2026
Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?
November 11, 2026
You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?
November 11, 2026
During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?
November 11, 2026
You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?
November 11, 2026
Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?
November 11, 2026
You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?
November 11, 2026
You are managing a product development project using a waterfall methodology. During the planning phase, you identify that the project requires expertise in a specialized technology that none of your current team members possess. You have budget to either train two existing team members (12 weeks training time, $15,000 cost) or hire an external contractor with immediate availability ($45,000 for project duration). The project schedule is tight, and this expertise is needed within 4 weeks. Your organization values employee development and has a strategic initiative to build internal capabilities. What should you do?
November 5, 2026
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?
November 5, 2026
You are managing an infrastructure upgrade project with a clearly defined scope, schedule, and budget. During a performance review meeting, you notice that one team member consistently delivers high-quality work but often misses deadlines by 2-3 days, causing minor delays in dependent activities. When you discuss this with the team member, they explain that they are perfecting every detail because they take pride in their work and want to avoid any defects. The project baseline schedule has limited float, and these delays are beginning to consume schedule reserves. How should you address this situation?
November 5, 2026
You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
November 5, 2026
You are managing a predictive software development project with a team of 12 members. During the executing phase, you notice that two senior developers frequently disagree during technical design meetings, causing delays in decision-making. The disagreements are becoming personal, and other team members are starting to take sides. The project schedule shows that critical design decisions must be finalized within two weeks to avoid impacting downstream activities. What should you do FIRST to address this situation?
November 5, 2026
Your hybrid project team includes both co-located and remote members across three time zones. The agile portion of the team has daily stand-ups at 9 AM in the main office timezone, which is 6 AM for some remote team members. The predictive portion has weekly status meetings at 4 PM, which is 7 PM for others. You've noticed participation declining and several remote team members seem less engaged. In a one-on-one, a remote developer mentions feeling like a 'second-class team member.' How should you address this to promote an inclusive team environment?
November 4, 2026
You are managing a hybrid project where the development team uses Scrum for product features while the compliance team follows a waterfall approach for regulatory documentation. During a retrospective, several developers express frustration that compliance delays are blocking their sprint reviews because required documentation isn't ready. The compliance lead argues their sequential process cannot be rushed due to legal requirements. Team morale is declining, and integration points are becoming contentious. What should you do first to address this situation?
November 4, 2026
You are leading a hybrid infrastructure project where the software development follows Scrum while hardware procurement and installation follows a predictive approach. During a sprint planning meeting, the development team commits to features that require hardware components currently scheduled for delivery in two months according to the predictive plan. The developers argue they can work on integration points now, but the hardware team warns this will create rework. Tensions are rising between the teams. What should you do to resolve this?
November 4, 2026
You're managing a hybrid project delivering a new customer portal. The UX design team works in two-week sprints with daily stand-ups, while the security team follows a phase-gate approach with formal reviews. A critical security vulnerability was discovered during a sprint review, requiring immediate redesign of a feature the UX team just completed. The UX team wants to address it in their current sprint, but the security team insists on a formal impact assessment that will take three weeks. The product owner is pressuring for a quick resolution. What is your best course of action?
November 4, 2026
Your organization is transitioning to hybrid project management. You're leading a project with a team of 12 members, where 5 are experienced in agile practices and 7 have only worked in traditional environments. During the first planning session, you notice the agile-experienced members dominating discussions about iteration planning, while the traditional team members appear confused and disengaged. One traditional team member privately tells you they feel their experience is being dismissed. How should you address this to build an effective hybrid team?
November 4, 2026
