PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

265 questions found · page 2 of 11

26
ProcessHybridMedium

You are managing a hybrid project to implement an enterprise resource planning (ERP) system. The system configuration follows a predictive approach with detailed requirements and formal testing phases, while the change management and user adoption activities use an adaptive approach with iterative training sessions and feedback loops. Your project is currently in the user acceptance testing (UAT) phase for the predictive stream. Users participating in UAT are providing feedback that should inform the next iteration of training materials in the adaptive stream, but the training team says they have already locked their next iteration plan and starting new work would disrupt their sprint commitment. How should you proceed?

August 16, 2026

27
ProcessHybridMedium

Your hybrid project is developing a medical device with hardware components managed predictively due to manufacturing lead times and regulatory submissions, while the embedded software uses iterative development with monthly releases. You have just completed the third software iteration when the hardware team discovers a component obsolescence issue that will delay hardware delivery by two months. The software team has three more iterations of features planned that depend on the specific hardware configuration. What should you do?

August 16, 2026

28
ProcessHybridMedium

You are leading a hybrid software development project where infrastructure deployment follows a predictive methodology with formal change control, while application features are developed using Kanban. During a retrospective, the development team expresses frustration that infrastructure changes take 3-4 weeks to implement through the change advisory board (CAB), creating bottlenecks for feature delivery. The infrastructure team is concerned that bypassing the CAB process could create security and stability risks. Several features are now blocked waiting for infrastructure changes. What is the best approach to address this issue?

August 16, 2026

29
ProcessHybridMedium

Your organization is implementing a hybrid project to modernize its payment processing system. The core payment engine follows a waterfall approach with strict regulatory requirements and formal testing gates, while the mobile app interface is developed using Scrum with two-week sprints. You are currently planning the integration testing phase. The payment engine team requests a four-week notice before any integration point, while the Scrum team wants to integrate continuously as features are completed. How should you handle this conflict in integration approaches?

August 16, 2026

30
ProcessHybridMedium

You are managing a hybrid project implementing a new customer relationship management (CRM) system. The infrastructure and data migration components follow a predictive approach with fixed deliverables, while the user interface customization uses iterative sprints. During the third sprint review, stakeholders request significant changes to the reporting dashboard that would require substantial rework to the data warehouse already built in the predictive phase. The data warehouse is 80% complete and on schedule. What should you do first?

August 16, 2026

31
PeopleAgileMedium

Your agile team has been consistently meeting sprint commitments, but during a recent retrospective, team members admitted they have been padding estimates significantly to ensure they never miss a commitment. The team's capacity allows them to complete stories early, but they wait until late in the sprint to pull in additional work to avoid looking like they overcommitted. The product owner is frustrated because the team could be delivering more value. What should you do to address this behavior?

August 13, 2026

32
PeopleAgileMedium

During a sprint review, your product owner presents a new feature idea that excites stakeholders, and they immediately begin discussing implementation details. Three team members become animated and start volunteering to work on it, while two others remain silent and look uncomfortable. After the meeting, one of the quiet team members tells you privately that they feel their opinions are never heard because the more vocal members always dominate discussions. How should you address this to promote inclusive team participation?

August 13, 2026

33
PeopleAgileMedium

Your agile team consists of members distributed across three time zones with only a two-hour overlap in working hours. Team members have reported feeling disconnected and unaware of what others are working on. The daily standup has become a status report where people simply read updates without meaningful interaction. Sprint planning meetings are running long because decisions take time with limited real-time collaboration. What is the most effective approach to improve team collaboration?

August 13, 2026

34
PeopleAgileMedium

You are leading an agile team that has been working together for three sprints. During the last retrospective, two team members had a heated disagreement about the definition of done for user stories. The conflict escalated, and other team members became uncomfortable. One developer now refuses to pair program with the other. The team's velocity has dropped by 30% since the conflict began. What should you do first to address this situation?

August 13, 2026

35
PeopleAgileMedium

You are coaching a new scrum master who is struggling with their role. During sprint planning, you observe them directing the team on which tasks each member should work on and how long each should take. In the daily standup, they spend time problem-solving individual blockers rather than facilitating team self-organization. When you provide feedback, they explain that they are trying to be helpful because they have the most technical experience and want to ensure the team succeeds. What coaching approach would best help this scrum master develop?

August 13, 2026

36
ProcessHybridMedium

Your hybrid project delivers software features iteratively while following a predictive schedule for regulatory compliance milestones. You're three months into the six-month project when a new competitor launches a product with features your stakeholders now want to prioritize. The product owner wants to immediately reprioritize the backlog to include these competitive features, but doing so would likely cause the team to miss a regulatory filing deadline scheduled for next month. The regulatory work cannot be delayed without significant business consequences. What should be your next step?

August 11, 2026

37
ProcessHybridMedium

You're managing a marketing campaign project using a hybrid approach where creative development is agile and media buying follows predictive contracts. During a retrospective, the creative team expresses frustration that their iterative work is often wasted because media placements are locked in months ahead based on initial concepts. The media team counters that they need creative specifications early to negotiate the best rates and placements. This tension is affecting team morale and collaboration. What is the most effective way to address this underlying conflict?

August 11, 2026

38
ProcessHybridMedium

You are leading a construction project with a hybrid approach where design work follows agile iterations while procurement and construction follow predictive methods due to regulatory requirements. Your team has just completed an iteration that resulted in significant design changes based on user feedback. However, these changes conflict with materials already procured based on earlier design decisions. The procurement lead insists on using the existing materials to avoid waste and delays, while the design team believes the new approach better serves the end users. How should you proceed?

August 11, 2026

39
ProcessHybridMedium

Your product development project uses a hybrid approach with quarterly predictive planning cycles and two-week agile sprints for execution. During sprint planning for sprint 5, the development team identifies technical debt accumulated over the past four sprints that is slowing their velocity by approximately 30%. The team wants to dedicate the next two sprints entirely to addressing technical debt, but this would impact committed deliverables for the quarterly milestone. The business stakeholders are expecting specific features at the end of the quarter. What is the best approach to address this situation?

August 11, 2026

40
ProcessHybridMedium

You are managing a digital transformation project using a hybrid approach where infrastructure components follow a predictive lifecycle while software features are developed iteratively. The infrastructure team has completed their foundation work ahead of schedule, and some team members are now idle. The software team is struggling with their current sprint and could use additional resources. Your project sponsor suggests moving infrastructure team members to help the software team immediately. What should you do first?

August 11, 2026

41
PeopleAgileMedium

Your distributed agile team spans three time zones across North America, Europe, and Asia. Team members have been complaining that the daily stand-up time (9 AM EST) requires the Asia-based developers to join at midnight their time, and they often appear disengaged. Sprint productivity has been declining, and the Asia-based team members recently missed several critical integration issues that could have been caught earlier. The European team members have also expressed concerns about work-life balance. What is the best way to address this challenge?

August 11, 2026

42
PeopleAgileMedium

Your agile team has consistently met sprint commitments for the past four iterations, and team morale appears high. However, during a one-on-one conversation, a junior developer confides that they feel overwhelmed and have been working 50-60 hours per week to complete their tasks. They haven't mentioned this in retrospectives because they don't want to let the team down. When you review the sprint metrics, you notice this developer's velocity is significantly higher than other team members. What should you do?

August 11, 2026

43
PeopleAgileMedium

During sprint planning, two senior developers on your agile team have a significant disagreement about the technical approach for a critical user story. One advocates for refactoring existing code to improve long-term maintainability, while the other insists on building a new module to meet the immediate sprint goal. The discussion is becoming heated, and other team members are growing uncomfortable. Both approaches are technically valid but require different levels of effort. What is the most appropriate action for you as the project manager?

August 11, 2026

44
PeopleAgileMedium

Your agile team has recently added three new developers who are experienced in traditional waterfall methodologies but new to agile practices. During the first sprint, you notice they are hesitant to speak up in daily stand-ups, wait for explicit task assignments rather than self-organizing, and ask for detailed upfront requirements documents. The existing team members are becoming frustrated with the slower pace. How should you best support the new team members' transition?

August 11, 2026

45
PeopleAgileMedium

You are leading an agile project team that has been working together for three sprints. During the latest retrospective, several team members express frustration that decisions are taking too long because the product owner is often unavailable for clarification. The team has been waiting 2-3 days for answers to blocking questions, which is impacting sprint goals. The product owner works remotely and supports multiple projects. What should you do first to address this situation?

August 11, 2026

46
Business EnvironmentPredictiveMedium

A project manager is leading a predictive product development project in a highly regulated medical device industry. Six months into the twelve-month project, a major competitor fails a regulatory audit, causing the regulatory agency to increase scrutiny across the entire industry. The agency announces more frequent inspections and stricter documentation requirements. The project's quality management plan was based on previous regulatory standards. The project is currently on schedule and within budget. What is the most appropriate action?

August 11, 2026

47
Business EnvironmentPredictiveMedium

A project manager is executing a predictive ERP implementation project for a manufacturing company. During a steering committee meeting, the CFO announces that the company is acquiring a smaller competitor, which will add 200 employees and two manufacturing facilities within four months. The acquisition was not anticipated in the project planning. The current project scope covers only the existing organization structure. Several stakeholders immediately suggest expanding the project scope to include the acquired company. What should the project manager do next?

August 11, 2026

48
Business EnvironmentPredictiveMedium

A pharmaceutical project manager is leading a predictive approach drug development project. The organization's strategic focus has shifted toward personalized medicine, while the current project focuses on a traditional mass-market drug. The project is 40% complete and on track to meet all success criteria. During a portfolio review meeting, executives question whether resources should be reallocated to projects better aligned with the new strategy. The project has strong clinical trial results and a clear path to regulatory approval. What should the project manager do?

August 11, 2026

49
Business EnvironmentPredictiveMedium

A construction project manager is overseeing a three-year infrastructure project using a predictive approach. After the first year, a competitor announces a new building technology that could reduce costs by 15% and improve energy efficiency. Several team members suggest switching to this new technology. The project baseline was approved six months ago, and 30% of the work is complete. The sponsor is known to be cost-conscious and values innovation. What is the best course of action?

August 11, 2026

50
Business EnvironmentPredictiveMedium

A project manager is leading a predictive software implementation project for a regional bank. During the planning phase, the legal department notifies the project manager that a new financial regulation will take effect in six months, requiring additional data encryption features. The regulation was not included in the original business case or project charter. The project is currently on schedule with detailed requirements already baselined. What should the project manager do first?

August 11, 2026