Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
340 questions found · page 2 of 14
You have just been assigned as the project manager for a bridge construction project that will take 18 months. The project charter has been signed by the sponsor, and you are beginning the planning phase. You need to identify all individuals, groups, and organizations that could impact or be impacted by the project. What process are you performing?
November 2, 2026
Your manufacturing project has been running for three months. During a quality inspection, you discover that 15% of the produced components do not meet the specifications defined in the quality management plan. Production is continuing, but you are concerned about the trend. What should be your immediate course of action?
November 2, 2026
You are managing a software implementation project for a healthcare client. During a requirements gathering session, the client's Chief Medical Officer requests a new feature that was not included in the original project scope statement or WBS. The feature would add significant value but also increase costs and timeline. What should you do first?
November 2, 2026
Your project to develop a new financial reporting system has a budget of $500,000 and is scheduled to take 10 months. You are currently at the end of month 4. According to your tracking, you have spent $220,000 and completed work that was budgeted at $180,000. What is the cost performance of your project at this point?
November 2, 2026
You are managing a construction project to build a new office building. During the planning phase, your team has identified all project activities and estimated their durations. You now need to determine when each activity should start and finish, considering their dependencies and resource constraints. What tool or technique should you use to create a visual timeline showing the project schedule?
November 2, 2026
Your product has been in production for 18 months using continuous deployment with automated testing. The development team releases small increments to production multiple times per week. Recently, the operations team escalated concerns that production incidents have increased 40% over the past two months, with several customer-impacting outages. The VP of Engineering questions whether the continuous deployment approach is too risky and suggests returning to monthly release cycles with more comprehensive manual testing. Your analysis shows that while incident count increased, 85% of incidents are caught and auto-rolled back within 2 minutes before customers are affected. The remaining 15% that impact customers are primarily due to third-party API changes and infrastructure issues, not code defects. The team's automated test coverage is 87% and their mean time to recovery is 8 minutes. What should you recommend?
November 2, 2026
Your organization is scaling agile across five teams working on a complex financial services platform. Each team has been working independently using Scrum for eight months with their own Product Owner from different business units (Trading, Risk Management, Compliance, Customer Service, and Reporting). The architecture team reports increasing integration problems, with teams making conflicting technical decisions that require expensive rework. Dependencies between teams are causing 20% of stories to be blocked each sprint. The CTO wants better alignment but doesn't want to lose team autonomy or slow down delivery. Teams currently sync through a weekly Scrum of Scrums meeting. What structural change would most effectively address the integration and dependency issues?
November 2, 2026
Your product team has been using two-week sprints with good success. After four months, you notice a troubling pattern in the metrics: sprint burndowns show the team typically completes only 40% of story points in the first week, then rushes to finish the remaining 60% in the second week. Defect rates in the second week are 3x higher than the first week. The team's Definition of Done includes unit testing, code review, and integration testing. During retrospectives, team members mention they often wait for clarification from the Product Owner, who is only available for detailed questions during the sprint review on day 10. Sprint velocity remains consistent at about 50 points per sprint, and stakeholders are satisfied with deliveries. What underlying process issue should you address?
November 2, 2026
During a release planning session, your distributed agile team is estimating features for the next quarter. The team has historical data showing their velocity averages 60 story points per two-week sprint. Marketing has committed to customers that Features A, B, and C (totaling 380 story points) will be delivered in the next six sprints. The Development Team estimates there's a 30% risk that Feature B's technical complexity is underestimated and could require 40% more effort. The Product Owner asks you how to plan the release with confidence. Feature A is worth $500K in revenue, Feature B is worth $300K, and Feature C is worth $150K. What is the most appropriate recommendation?
November 2, 2026
Your agile team has been delivering increments successfully for six sprints, maintaining a stable velocity of 45 story points. In sprint 7, the Product Owner requests adding a critical regulatory compliance feature that requires immediate attention due to an unexpected government mandate. The feature is estimated at 55 story points and cannot be decomposed further without losing its compliance value. The Product Owner wants to add it to the current sprint backlog which already contains 45 story points of committed work. Team members express concern about overcommitment, but the Product Owner insists this is a business-critical emergency. What should the Scrum Master do first?
November 2, 2026
You are managing a digital transformation project using a hybrid approach. The enterprise architecture team works in a predictive manner with quarterly milestones, while multiple product teams use Scrum. During PI (Program Increment) planning, you discover that two product teams have dependencies on an architectural component that the enterprise team planned to deliver in Q3, but the product teams need it in Q2 to meet their commitments. The enterprise architect states that accelerating this component would require deferring other architectural work that supports different initiatives. How should you proceed?
November 2, 2026
Your hybrid project combines predictive planning for hardware procurement and facilities setup with agile development for the software components. You're three months into the project, and the predictive track is on schedule, but the agile teams have consistently delivered only 60% of their planned story points each sprint. The cumulative flow is trending behind, and stakeholders are concerned about meeting the fixed launch date in six months. The teams report that integration testing with hardware prototypes takes longer than expected. What is the most appropriate action?
November 2, 2026
You are leading a product development project using a hybrid approach where research and regulatory approval follow a waterfall process, while feature development uses Kanban. The regulatory team has just received approval for the product specifications, which is a major milestone. However, during the regulatory review process, the development team continued building features based on the submitted specifications and has now completed 60% of the planned features. The approved specifications include three changes from what was originally submitted. What should you do next?
November 2, 2026
Your organization is implementing a new customer portal using a hybrid approach. The compliance and security requirements are being managed predictively with detailed documentation and stage-gate approvals, while the user interface features are developed iteratively using two-week sprints. During a sprint review, stakeholders request significant changes to the authentication flow that would require modifications to the security architecture currently in the design phase. The security architect says these changes would delay the security deliverables by one month. What is the best way to handle this situation?
November 2, 2026
You are managing a hybrid project where the infrastructure team uses predictive methods while the software development team uses Scrum. During sprint planning, the infrastructure lead informs you that a critical server installation scheduled for next week has been delayed by two weeks due to vendor issues. This delay will impact the development team's ability to deploy features in the next three sprints. The development team has already committed to their sprint goals. What should you do first?
November 2, 2026
Your organization is implementing a new ERP system using a hybrid approach: core system configuration follows predictive methodology while custom integrations use Scrum. During the third sprint review, stakeholders request a demonstration of the complete system including both core and custom components. However, the predictive track won't have testable deliverables for another two months. Stakeholders express frustration about not seeing the 'whole picture.' How should you address this?
October 29, 2026
Your hybrid project uses iterative development for product features while marketing and compliance activities follow a predictive timeline. The compliance team has just informed you that a regulatory requirement will change in three months, affecting features currently in the product backlog. The change is mandatory but the detailed requirements won't be available for six weeks. How should you respond?
October 29, 2026
You're managing a construction project with a hybrid approach: building construction uses predictive methods while the smart building technology implementation uses agile sprints. The construction is running two weeks behind schedule due to weather delays, which will impact the technology team's access to spaces where they planned to work next sprint. The technology team wants to reprioritize their backlog to work on components they can complete off-site. What should you evaluate first before approving this change?
October 29, 2026
You're leading a hybrid project where design work follows a waterfall approach while development uses two-week sprints. The design team has completed 70% of their deliverables, but recent customer feedback suggests significant changes are needed. The development team has already built features based on the completed designs. The project sponsor wants to incorporate the feedback but is concerned about budget overruns. What is your best course of action?
October 29, 2026
You are managing a hybrid project where the software development team uses Scrum while the infrastructure team follows a predictive approach. During sprint planning, the development team commits to features that require infrastructure components not yet scheduled in the infrastructure team's plan. This misalignment has caused delays in the past two sprints. What should you do to address this recurring issue?
October 29, 2026
You are managing a product development project with multiple external vendors. One vendor has submitted an invoice for $85,000 for completed work. Your procurement specialist reviews the invoice against the contract and identifies that the deliverables match the contract requirements, but notices the vendor applied a 5% price increase that was not in the original fixed-price contract. The vendor claims the increase was discussed verbally with a team member due to scope changes. Your team member confirms a conversation occurred but no formal change was processed. What should you do?
October 25, 2026
Your project team is developing a detailed project schedule for a 16-month infrastructure project. During schedule network analysis, you identify that the critical path has 18 months of duration, exceeding the required completion date by 2 months. You have identified a sequence of activities on the critical path where design and procurement activities could be overlapped to save time. However, overlapping these activities will increase project risk and may require additional design resources. What technique are you considering, and what is the most important factor to evaluate before implementing it?
October 25, 2026
You are managing a manufacturing facility expansion project. During a quality audit, the auditor identifies that three deliverables were completed without the required inspections documented in the quality management plan, though the deliverables appear to meet specifications. The project is currently on schedule and within budget. The construction manager argues that the inspections are bureaucratic and the work quality is evident. What should you do first?
October 25, 2026
During the planning phase of a software development project, your team has identified 47 risks. You've completed qualitative risk analysis and are now preparing for quantitative risk analysis. The project sponsor questions why you need to spend additional time and budget on quantitative analysis when risks have already been prioritized. The project has a firm deadline for regulatory compliance and a contingency reserve of 10% has been allocated. What is the strongest justification for conducting quantitative risk analysis?
October 25, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. After 6 months, the project has spent $1.1 million and completed work valued at $900,000 according to the baseline. The planned value at this point was $1 million. Senior management is concerned about project performance and asks for your assessment. What is the most critical performance issue you should address first?
October 25, 2026
