Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
50 questions found · page 1 of 2
You are managing a defense contractor project with 30 team members working on classified deliverables. Three months into the project, a key architect who designed the overall solution structure has received a more lucrative offer from a competitor and will leave in two weeks. This architect's knowledge is essential for the next phase, and direct replacement is complicated by security clearance requirements that take 4-6 months. You have identified an internal candidate with relevant experience but who lacks the specific domain expertise. The project baseline includes detailed technical specifications, but much of the architect's design rationale exists only in email threads and meeting notes. Your sponsor is pressing you to maintain the current schedule. What is your best course of action?
August 20, 2026
You are managing a large construction project that has entered the execution phase. During a routine performance review, you discover that one of your site supervisors has been consistently inflating progress reports for the past three weeks, showing 85% completion when actual completion is closer to 65%. This supervisor is well-liked by the team, has 15 years of experience, and this is the first time you've encountered integrity issues with this individual. The misinformation has affected your earned value calculations and led you to reassign resources that were actually still needed. The project is visible to executive leadership, and you have a steering committee meeting in two days. What is the most appropriate course of action?
August 20, 2026
You are leading a pharmaceutical project to develop validation documentation for a new manufacturing process. The project team includes quality assurance specialists, process engineers, and regulatory affairs experts. During a critical review meeting, you observe that the QA specialists consistently dismiss input from the process engineers, citing regulatory concerns, while the engineers feel the QA team doesn't understand operational realities. This dynamic has resulted in rework cycles and is threatening the project's ability to meet regulatory submission deadlines. The organizational matrix structure gives you limited authority over these functional resources. How should you address this situation?
August 20, 2026
You are managing a government contract project following a predictive approach with strict scope, schedule, and budget constraints. During month 4 of the 12-month project, a key team member who holds critical institutional knowledge about legacy systems unexpectedly resigns. This team member was responsible for integrating the new system with three legacy platforms, and replacement hiring could take 6-8 weeks due to security clearance requirements. The integration work is scheduled to begin in 3 weeks. Your team suggests aggressively cross-training other members, but this would require pulling resources from their current critical path activities. What should you prioritize first?
August 20, 2026
You are managing a complex infrastructure project with a team of 45 members across three geographical locations. During the executing phase, you notice that two senior technical leads from different locations are consistently disagreeing on technical approaches during virtual meetings, causing delays in decision-making. The disagreements have begun to affect team morale, and other team members are starting to take sides. Both leads are highly skilled and their expertise is critical to project success. The project is currently on schedule but at risk of delays if this conflict continues. What is the most appropriate action to take?
August 20, 2026
A global technology company is executing a predictive project to standardize enterprise resource planning (ERP) systems across 47 subsidiaries in 23 countries, with a 42-month timeline and $310M budget. During month 28, while implementing in the European region, the company's board approves a significant corporate restructuring that will consolidate the 47 subsidiaries into 12 global business units organized by product line rather than geography. This restructuring will change reporting structures, business processes, financial consolidation requirements, and potentially the entire ERP architecture. The project has successfully implemented the system in 18 subsidiaries, with 12 more in various implementation stages. The CIO asks the project manager to assess the impact and recommend how to proceed. What should the project manager do first?
August 16, 2026
A manufacturing company is executing a predictive project to build a $220M production facility for automotive components in an emerging market. The project is month 21 of a 36-month timeline, with building construction complete and equipment installation beginning. Economic conditions in the target market have deteriorated significantly—currency devaluation of 35%, increased import tariffs on raw materials, and two major automotive customers have delayed their regional expansion plans by 2-3 years. The original business case projected ROI of 18% over 8 years based on specific production volumes and pricing. The CFO has requested an updated financial analysis and is considering project termination or conversion to a smaller-scale facility. Equipment purchases worth $78M are committed but not yet delivered. What should the project manager do?
August 16, 2026
A financial services company is executing a core banking system replacement project using a predictive methodology with a 30-month timeline and $95M budget. The project has completed detailed requirements, design, and procurement phases. During the development phase (month 16), the company acquires a smaller competitor that uses a different technology platform. The merger integration team proposes consolidating onto a single platform, which would either require abandoning the current project (wasting $42M invested) or forcing the acquired bank to migrate twice—first to their interim platform, then to the new system within 18 months. The PMO director asks the project manager to evaluate strategic options. Regulatory requirements mandate system consolidation within 24 months of acquisition closing. What analysis should the project manager prioritize?
August 16, 2026
A government infrastructure project worth $420M is in its execution phase using a predictive approach with a 5-year timeline. The project is building a regional transportation hub with multiple contractors. Three years into execution, a new administration takes office with different policy priorities and appoints a new agency director who questions the project's strategic alignment. The director requests a comprehensive benefits realization review before authorizing the next $150M funding tranche. Current earned value metrics show: SPI = 0.92, CPI = 0.88, with 58% of work completed. The project business case was approved under different economic assumptions, and inflation has increased costs by 14%. How should the project manager approach this situation?
August 16, 2026
A multinational pharmaceutical company is executing a predictive drug development project with a 4-year timeline and $180M budget. During year 2, a competitor receives FDA fast-track designation for a similar drug, potentially reducing the market window by 18 months. The project sponsor pressures the project manager to compress the schedule by overlapping clinical trial phases, which would violate regulatory protocols and risk patient safety. The governance board is split—some members prioritize speed-to-market while others emphasize compliance. Financial analysts project a $250M revenue loss if the competitor launches first. What should the project manager do first?
August 16, 2026
You are managing a predictive infrastructure project for a public utility company with a detailed WBS, approved baseline, and 24-month timeline. At month 16, a new CEO joins the organization and introduces a strategic initiative to adopt renewable energy sources. She directs that your project must now incorporate solar panel installations and battery storage systems, representing a 40% scope increase. The CEO expects the same completion date, stating 'we need to show renewable commitment to our board and regulators.' Your project sponsor privately tells you to 'make it work' to avoid conflict with the new executive. The additional scope has not gone through formal change control, and preliminary analysis suggests the original budget is insufficient. What is your best course of action?
July 29, 2026
Your organization has been awarded a predictive project to implement a financial system for a client in a country with strict data sovereignty laws. The project plan, developed six months ago, specified using your company's standard cloud infrastructure hosted in your home country. Two months into the eight-month project, the client's government issues new guidance clarifying that all financial data must be processed and stored within national borders with no exceptions. Your cloud provider has no data centers in the client's country and establishing one would take 14 months. The client will not grant an extension beyond 60 days. Senior management is considering proceeding with the original plan and addressing compliance 'later.' What should you do?
July 29, 2026
You are managing a predictive pharmaceutical research project that requires approval from multiple regulatory bodies across different countries. The project is structured with sequential phase gates, and investment in each subsequent phase depends on passing regulatory reviews. During Phase 2 clinical trials, preliminary data suggests the drug is effective but the European Medicines Agency (EMA) requests additional long-term safety data that was not originally planned, while the FDA is satisfied with current protocols. This additional study will cost $3.2 million and delay market entry by 18 months. Your CFO argues the company should focus only on FDA approval and enter the European market later. What should you recommend?
July 29, 2026
Your organization is executing a three-year government defense project using a predictive approach with strict earned value management (EVM) reporting requirements. At the 15-month progress review, the Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.82. The customer is threatening contract termination due to poor performance. Your executive sponsor suggests re-baselining the project to show improved metrics for the next reporting period. The original baseline was approved by all stakeholders including the government oversight committee. What is the most appropriate action?
July 29, 2026
You are managing a predictive construction project with a fixed-price contract worth $8 million. Six months into the 18-month project, a new environmental regulation is enacted that requires additional soil remediation work not included in the original scope. The customer insists this should be absorbed within the existing contract price, citing the fixed-price nature of the agreement. Your legal team confirms the regulation was not foreseeable at contract signing. The additional work is estimated at $450,000 and will add two months to the schedule. What should be your primary course of action?
July 29, 2026
Your pharmaceutical project team of 30 specialists is executing a predictive plan to develop regulatory submission documentation. You have one team member, a senior regulatory expert with 20 years of experience, who possesses unique knowledge critical to project success but consistently demonstrates poor mentoring skills, dismisses junior team members' questions as 'basic,' and has caused two junior regulatory writers to request transfers. The junior members are necessary for document production volume, but the senior expert's specialized knowledge of FDA interactions cannot be easily replaced. Your HR business partner has documented complaints but states the expert has not violated any policies. The project is at the midpoint and approaching critical regulatory milestones. What is your best approach?
July 27, 2026
You are leading a construction project that is 60% complete. During a routine team performance assessment, you discover that your site supervisor has been consistently inflating progress reports to make their team appear more productive. Upon investigation, you learn the supervisor was responding to intense pressure from the construction manager to meet aggressive milestones, and feared their team would be viewed negatively. The actual progress indicates the project is approximately 3 weeks behind schedule. The construction manager is unaware of the misreported data and is making decisions based on the inflated reports. What should you do?
July 27, 2026
You are managing a government defense project with strict security clearance requirements and a hierarchical organizational structure. A high-performing team member has been consistently delivering excellent technical work but has begun circumventing the established approval chain by directly contacting the client's technical lead to expedite decisions. While this has accelerated some approvals, your project sponsor has received a formal complaint from the client's program manager about protocol violations. The team member argues their actions have saved the project two weeks of schedule delays. How should you address this situation?
July 27, 2026
Your predictive project is entering month 8 of a 14-month schedule. Three team members who were critical resources for the design phase have been reassigned to other organizational priorities by their functional managers, despite your resource management plan identifying them as needed through month 10. The remaining team has the technical skills but lacks the institutional knowledge these members possessed. The project sponsor is pressuring you to maintain the original schedule. Performance reviews show current team morale is declining. What is your best course of action?
July 27, 2026
You are managing a large infrastructure project with a team of 45 members across engineering, procurement, and construction disciplines. During the execution phase, you notice that two senior engineers who must collaborate on critical path activities have fundamentally different working styles—one prefers detailed documentation and formal approvals, while the other favors quick decisions and minimal paperwork. Their conflict is causing delays in design reviews that are impacting the project schedule. The procurement lead suggests reassigning one engineer to a different work package. What should you do first?
July 27, 2026
You are managing a critical infrastructure project for a utility company with a 36-month timeline and a highly structured governance framework. Six months into execution, your most senior electrical engineer, who serves as a technical authority and mentors three junior engineers, begins showing signs of stress and reduced engagement. Their deliverable quality remains acceptable, but they are increasingly absent from team meetings, less responsive to questions, and have stopped participating in design reviews. Two junior engineers have privately expressed concern. When you meet with the engineer, they acknowledge feeling overwhelmed but are reluctant to discuss specifics, saying 'it's personal' and they'll work it out. Your next major design milestone requiring their expertise is in five weeks. The project has no schedule buffer. What is the MOST appropriate course of action?
July 13, 2026
You are managing a complex manufacturing facility upgrade project for an automotive supplier. The project has a fixed-price contract with milestone-based payments. Your project team includes 12 full-time employees and 18 contractors from three different vendors. At the 60% complete point, you learn that two contractors from Vendor A have been socializing with your client's procurement director outside of work and have mentioned they could deliver certain components 'more efficiently' if contracted directly by the client, bypassing your organization. Your contracts manager confirms this would violate the exclusivity clause in your vendor agreement. The contractors are performing well technically, and replacing them now would delay the project by 4-6 weeks, risking a $200,000 milestone payment. What should you do?
July 13, 2026
You are managing a defense contract project with 35 team members across four locations. The contract includes specific earned value management (EVM) reporting requirements. At the month 9 performance review, you notice that one remote team of eight developers consistently reports 100% completion of planned tasks on time, yet integration testing repeatedly uncovers significant defects requiring rework. The team lead is well-liked and has been with the company for 15 years. Other teams have expressed frustration about the rework burden. Your SPI is 1.02 but CPI is 0.87, partly due to these rework costs. When you discuss this with the team lead privately, they explain their team is working hard and meeting their commitments as they understand them. What is the MOST effective way to address this performance issue?
July 13, 2026
You are leading a pharmaceutical product development project following a waterfall approach. During the detailed design phase, your quality assurance lead raises concerns that the technical lead is making design decisions without consulting the regulatory compliance specialist, potentially creating future audit risks. When you investigate, you discover the technical lead believes the compliance specialist is being overly cautious and slowing down progress. The technical lead has 20 years of experience and has successfully delivered similar projects. The compliance specialist is newer to the company but has deep regulatory expertise. Your project has strict regulatory submission deadlines with significant financial penalties for delays. How should you address this situation?
July 13, 2026
You are managing a large government infrastructure project with a baseline budget of $45 million and a 24-month timeline. At month 16, a critical team member who holds specialized knowledge about legacy system integration submits their resignation, citing personal reasons. This team member has been instrumental in interfacing with three key stakeholders and possesses undocumented institutional knowledge. The project is currently on schedule but slightly over budget (CPI 0.92). Your sponsor is concerned about the impact on the upcoming integration phase scheduled to begin in three weeks. What should be your FIRST action to address this situation?
July 13, 2026
