Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
95 questions found · page 1 of 4
A project manager is leading a government defense project using a predictive methodology with strict earned value management requirements. At the 60% completion milestone review, the project shows CPI of 0.92 and SPI of 0.88. During the review, a government auditor identifies that several procurement processes did not fully comply with new federal acquisition regulations that took effect 4 months ago, though the contracts themselves are valid. The non-compliance issues are administrative rather than substantive, but could trigger a formal audit and potential penalties. The project sponsor suggests quietly correcting the processes going forward without reporting the past issues to avoid audit delays. The project manager knows that government contracts require disclosure of compliance issues. What is the MOST appropriate course of action?
November 18, 2026
A project manager is overseeing a large construction project using a predictive approach when the organization announces a major merger with a competitor. The merger brings significant organizational changes including new executives, revised strategic priorities, and potential consolidation of project portfolios. The project is 55% complete and on track to deliver within baseline constraints. However, three weeks after the merger announcement, the project manager learns informally that a similar project exists in the acquired company and both projects may be evaluated for continuation. The formal portfolio review is scheduled for 8 weeks away. The project team is concerned about job security, and two key resources have started interviewing elsewhere. What should the project manager do?
November 18, 2026
A pharmaceutical company is executing a predictive project to build a new manufacturing facility. The project is 40% complete when a competitor announces a breakthrough technology that could make the planned facility's production method obsolete within 3-5 years instead of the projected 15-year lifecycle. The project has already spent $45M of a $120M budget. Market analysts predict the competitive landscape will shift significantly, but there is uncertainty about regulatory approval timelines for the new technology. The project sponsor wants to continue as planned, citing sunk costs and the need for near-term production capacity. Senior executives are divided. What is the MOST appropriate action for the project manager?
November 18, 2026
A project manager is leading a multinational software implementation project using a predictive waterfall methodology across five countries. During the design phase, the project team discovers that the technology architecture approved in the planning phase conflicts with data sovereignty laws recently clarified by regulators in two of the target countries, representing 35% of the user base. The legal department confirms the architecture cannot be used as designed. The project is already 3 months into an 18-month timeline, and the architecture was a key dependency for vendor selection. The governance board meets quarterly, with the next meeting in 6 weeks. How should the project manager proceed?
November 18, 2026
A large government infrastructure project is in its execution phase when new environmental regulations are enacted that significantly impact the project's deliverables. The project uses a predictive approach with detailed baseline requirements established 18 months ago. The regulatory change requires substantial modifications to the technical specifications, potentially adding 8 months and $4.2M to the project. Senior management pressures the project manager to absorb these changes within the existing schedule and budget constraints to avoid negative stakeholder perception. The contract with the primary vendor has a fixed-price component for 60% of the work. What should the project manager do FIRST to address this situation?
November 18, 2026
Your construction firm is executing a predictive $50M hospital expansion project. You've identified that specialized medical imaging equipment with 14-month lead times represents a critical path constraint. During procurement planning, your lead structural engineer discovers that the selected equipment manufacturer is involved in ongoing patent litigation that could result in an injunction preventing equipment sales in your country. The litigation outcome is expected in 8-10 months, and your procurement must be initiated within 60 days to meet the project schedule. An alternative manufacturer exists but their equipment requires significant design modifications, adding $2.8M and 4 months to the project. Your company's legal counsel assesses a 40% probability of an adverse litigation outcome. What approach BEST manages this business environment risk?
October 29, 2026
You are managing a three-year predictive ERP implementation for a publicly-traded retail corporation. Eighteen months into execution, a private equity firm launches a hostile takeover bid. During the uncertainty, three key functional executives who are critical project stakeholders resign, the CEO announces a hiring freeze affecting 12 planned project positions, and the board initiates a strategic review of all capital expenditures over $5M. Your project has spent $18M of a $35M budget and is on track for the planned go-live in 15 months. The interim CFO has requested a briefing on project status and options. The sponsor suggests continuing as planned to avoid disruption. What recommendation should you provide to the CFO?
October 29, 2026
Your pharmaceutical company is executing a predictive project to build a new manufacturing facility in an emerging market country. The project is 60% complete when the country's currency depreciates by 35% against the dollar over six weeks due to political instability. While your major equipment contracts were negotiated in USD, local labor, materials, and services—representing 45% of your remaining budget—are contracted in local currency. Your Cost Performance Index is currently 1.05, and you're two weeks ahead of schedule. The country's central bank has imposed capital controls limiting foreign currency transactions. Senior leadership is concerned about the project's viability. What should be your FIRST action?
October 29, 2026
You are managing a predictive government defense project under a firm-fixed-price contract. Six months into the 18-month effort, a new federal regulation is published that requires significant changes to data encryption standards for all systems handling classified information. Your project was 95% compliant with the old standards, but the new regulation requires hardware replacements and software re-engineering affecting 40% of completed work. The contracting officer has confirmed this constitutes a changes in law provision under the contract. Your executive sponsor is pressuring you to absorb the changes within the existing budget to preserve the company's reputation with this client. What is the MOST appropriate course of action?
October 29, 2026
Your organization is undergoing a strategic shift from product-based revenue to a subscription-based SaaS model. The PMO director has assigned you to lead a critical infrastructure migration project with a 14-month timeline and $4.2M budget. During the project charter development, the CFO insists on including strict cost baseline controls and stage-gate approvals, while the CTO wants flexibility to adopt emerging cloud technologies that may become available during execution. The CEO has made it clear that missing the go-live date will result in significant competitive disadvantage as two competitors are launching similar offerings. What should be your PRIMARY consideration when finalizing the project management approach?
October 29, 2026
Your organization is executing a predictive software development project for a government client under a firm-fixed-price contract. During the requirements validation phase, you discover that two key requirements conflict with recently updated data privacy laws that were enacted after contract signing but before development began. Legal compliance requires modifying these requirements, which will reduce some functionality the client specifically requested. The contract does not include a clause addressing regulatory changes. Your legal team confirms that non-compliance could expose both organizations to significant penalties. The client's program manager insists you must deliver all original requirements as specified in the contract and suggests finding 'creative technical solutions' to satisfy both the requirements and the laws. Your organization's compliance officer has flagged this as a high-risk issue requiring resolution. What is the most appropriate response?
October 16, 2026
You are leading a predictive ERP implementation project for a global retail organization. During the planning phase, you identified the need for extensive organizational change management, including training 5,000 employees across 12 countries. Management approved a $800K change management budget as part of the $12M project. Nine months into execution, a new CFO conducts a portfolio review and reallocates your change management budget to a revenue-generating digital marketing initiative, stating that 'training is overhead, not a project deliverable.' Your project team warns that without proper change management, user adoption will fail, likely resulting in the ERP system being underutilized. Historical data from similar projects shows 60% failure rate without change management versus 15% with it. What should be your primary concern?
October 16, 2026
Your construction project is building a manufacturing facility in an emerging market. Six months into the 24-month schedule, the host country implements new environmental regulations requiring additional emissions control systems not included in your original scope. Compliance will add $3.5M to the $28M budget and extend the schedule by four months. However, your contracts with the client contain a clause stating that regulatory changes are the client's responsibility. The client's legal team argues that these regulations were proposed (but not enacted) before contract signing, so you should have anticipated them. The client refuses to approve a change request and demands you absorb the costs. Senior management wants to maintain the client relationship for future opportunities worth an estimated $200M. What should you do?
October 16, 2026
You are managing a predictive regulatory compliance project for a pharmaceutical client. During the execution phase, a competitor announces they have received expedited approval for a similar drug using a new regulatory pathway that was not available when your project was initiated. Your client's legal team believes pursuing this new pathway could reduce the compliance timeline from 18 months to 10 months, but it would require re-validating 30% of completed work and restructuring your project baseline. The project steering committee is meeting in two days to decide whether to continue with the original approach or adopt the new pathway. Your analysis shows the new pathway has a 70% probability of success but lacks established precedent. What is your best course of action?
October 16, 2026
Your organization has recently merged with a competitor, creating significant shifts in strategic priorities. The PMO director has asked you to reassess your ongoing predictive infrastructure project, which is 40% complete and on schedule. The merged entity's new strategic plan emphasizes cloud-based solutions, while your project is implementing on-premise data centers. Senior leadership is divided—some want to continue as planned to avoid sunk costs, while others advocate for immediate termination. The project has already consumed $2.4M of a $6M budget and has binding contracts with hardware vendors totaling $1.8M. What should you do first?
October 16, 2026
You are managing a 30-month construction project with a team of 60 people including engineers, architects, contractors, and site workers. The project is performing on schedule and budget. Your HR business partner informs you that a formal complaint has been filed by a junior female engineer alleging gender-based harassment by a senior male site supervisor. The supervisor is a 15-year company veteran with strong technical skills who manages 12 site workers critical to the current phase. Initial HR investigation suggests the complaint has merit. The supervisor denies the allegations and has strong support from his direct reports. The situation is creating tension within the team, with some members supporting each person. What is your primary responsibility as project manager in this situation?
October 15, 2026
You are managing a critical 20-month regulatory compliance project for a financial services organization. The project team includes 8 full-time employees and 12 contract resources. Six months into the project, your organization announces a major restructuring that will affect 30% of the workforce. Rumors are widespread, team morale has dropped significantly, and productivity has declined by 15% over the past three weeks. Two key team members have confidentially told you they are interviewing elsewhere. Your sponsor has confirmed that no project team members are targeted for layoffs, but this information is confidential and cannot be shared broadly for another four weeks. What should you do to maintain team performance during this period?
October 15, 2026
You are managing a 18-month enterprise software implementation project using a predictive approach. During the execution phase, you notice that two senior developers, who previously worked well together, are now in constant conflict affecting team morale. The conflict centers on technical design decisions, with each developer believing their approach is superior. Both are high performers, and their disagreement has created factions within the 12-person development team. Three other developers have approached you privately expressing frustration about the hostile environment. The conflict is not yet impacting deliverables but is affecting team collaboration and knowledge sharing. What is the most effective approach to resolve this conflict?
October 15, 2026
You are leading a 36-month manufacturing project with a geographically distributed team across four countries. A highly skilled subject matter expert (SME) based in Germany, who is critical to the design phase, has been underperforming for six weeks. Her work quality has declined, she misses virtual meetings, and other team members report communication difficulties. You learn through informal channels that she is dealing with a serious family health crisis but has not disclosed this officially. Your project is entering a critical phase where her expertise is essential, and replacing her would cause a 4-6 week delay. How should you handle this situation?
October 15, 2026
You are managing a 24-month government infrastructure project with a team of 45 resources across five functional departments. During month 8, performance metrics show that three senior technical leads from different departments are consistently missing deliverable deadlines, causing schedule variance. When you investigate, you discover that all three leads are being pulled into other departmental priorities by their functional managers, despite the resource agreements established during project planning. The functional managers claim their departmental work takes precedence. What should you do first to address this situation?
October 15, 2026
You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?
October 9, 2026
You are managing a defense contractor project using a firm-fixed-price contract worth $28M. During planning, you identified 47 risks and developed response plans with allocated contingency reserves totaling $2.1M. At the 60% completion point, you have consumed $1.85M of contingency reserves, primarily due to three risks that materialized with greater impact than anticipated. You identify a new high-probability, high-impact risk related to a critical supplier's financial instability that could halt production of a custom component with no alternative sources. The risk response would require $450K for a mitigation strategy (qualifying a second supplier). Your remaining contingency reserve is $250K, and management reserves are $800K controlled by the sponsor. What should you do?
October 9, 2026
Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?
October 9, 2026
You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. The design phase deliverables were approved three months ago, and construction is 40% complete. A new regulatory requirement has been published that mandates additional safety features in the HVAC system, requiring significant design changes. The change will cost $2.8M (8% of the total budget) and add 6 weeks to the critical path. The regulatory compliance officer insists this is a mandatory change and not subject to change control. Your project charter states that regulatory compliance changes require automatic approval. What should you do FIRST?
October 9, 2026
You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?
October 9, 2026
