PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

310 questions found · page 4 of 13

76
PeoplePredictiveHard

You are managing a predictive construction project to build a new hospital wing with a 36-month timeline and $45M budget. Your team of 40 members includes architects, engineers, contractors, and hospital operational staff. At the 18-month mark, during earned value analysis, you identify that CPI is 0.92 and SPI is 0.88. In reviewing team performance data, you notice that the top 20% of your team members are producing 60% of the project value, while several team members are consistently underperforming against their assigned tasks. The human resource management plan includes a performance measurement approach, but you have not conducted formal performance reviews due to project pressures. Several stakeholders have commented on specific individuals not meeting expectations. Union agreements require 90-day notice for any personnel changes. What should you prioritize?

September 29, 2026

→
77
PeoplePredictiveHard

You are managing a predictive pharmaceutical project developing a new drug delivery system with a fixed 18-month regulatory submission deadline. Your team includes research scientists, regulatory specialists, and manufacturing engineers. Six months into the project, you notice that the scientists are creating highly detailed technical documentation that far exceeds regulatory requirements, while the regulatory team complains this slows down their review process. The scientists argue that thorough documentation is part of their professional standards. Meanwhile, manufacturing engineers are waiting for finalized specifications to begin their work, and this path is now on the critical path with only two weeks of float remaining. The quality management plan specifies documentation standards that the scientists are exceeding. How should you address this situation?

September 29, 2026

→
78
PeoplePredictiveHard

You are managing a multi-year predictive ERP implementation project for a global manufacturing company. The project organizational chart shows a matrixed structure where team members report both to you and their functional managers. Three months into execution, you discover that five critical team members are consistently being pulled back to operations by their functional managers to address production issues, causing them to miss 40% of their planned project hours. This has resulted in two successive missed milestones. You have raised this issue in the last two steering committee meetings, but functional managers argue that production takes priority. The project charter clearly states resource commitment levels, and the sponsor supported the project publicly but has not intervened. What should be your next step?

September 29, 2026

→
79
PeoplePredictiveHard

You are leading a predictive aerospace project with strict quality gates and regulatory requirements. Your project team of 25 members has been working together for nine months. During a critical design review, you notice that two senior engineers from different functional departments consistently undermine each other's technical approaches in meetings, creating tension that is now affecting team morale. Other team members have started taking sides, and collaboration has noticeably decreased. The project sponsor mentions that both engineers are highly regarded in the organization and have worked together on previous projects without issues. You have a major milestone deliverable due in four weeks that requires their joint contribution. What is the most effective approach?

September 29, 2026

→
80
PeoplePredictiveHard

You are managing a large government infrastructure project using a predictive approach with a 24-month timeline. During month 8, your technical lead submits his resignation, citing personal reasons. This individual has deep knowledge of legacy systems that interface with your new solution, and no documentation exists for these integrations. The resource manager offers you two options: promote a junior team member who has been shadowing the technical lead for three months, or bring in an external consultant with general expertise but no project-specific knowledge. Your project is currently on schedule, but the next phase involves critical integration work starting in six weeks. What should you do first?

September 29, 2026

→
81
PeopleAgileMedium

You are coaching a newly formed agile team that includes three junior developers and two senior developers. During the first two sprints, you notice the senior developers are completing most of the complex stories while junior developers are assigned only simple tasks. The senior developers say they are trying to help the team meet commitments, but the junior developers express frustration in private that they are not learning new skills. Sprint goals are being met, but you are concerned about long-term team capability and sustainability. What is the best approach?

September 29, 2026

→
82
PeopleAgileMedium

Your agile team has two developers who consistently clash during daily standups and sprint planning. One developer prefers thoroughly discussing technical approaches before committing to work, while the other prefers to start coding quickly and iterate. Their disagreements are starting to affect team dynamics, with other team members avoiding engaging in technical discussions. Both developers are highly skilled and their work quality is excellent. Yesterday, their disagreement during refinement caused the session to run 30 minutes over time. What should you do?

September 29, 2026

→
83
PeopleAgileMedium

During a sprint review, a key stakeholder becomes visibly upset when seeing the increment, stating that the features demonstrated are not what they expected, even though the stories were approved during sprint planning. The product owner defends the work, saying the team delivered exactly what was written in the user stories. The stakeholder insists the team must redo the work. Team morale drops immediately as they feel their hard work is being dismissed. How should you address this conflict?

September 29, 2026

→
84
PeopleAgileMedium

Your agile development team includes members from four different countries across three time zones. During sprint planning, you notice that team members in the Asia-Pacific region rarely speak up, while team members in North America dominate the conversation. The sprint retrospectives show similar patterns. The team's velocity has been declining over the past two sprints, and some stories are being carried over because requirements were misunderstood. What is the most effective action to improve team collaboration?

September 29, 2026

→
85
PeopleAgileMedium

You are leading an agile project team that has been working together for three sprints. During the latest retrospective, several team members express frustration that decisions are often delayed because they feel they need to wait for your approval on minor implementation details. The team has strong technical skills and has consistently met their sprint commitments. Team velocity is stable, but you notice team members seem hesitant to self-organize. What should you do to address this situation?

September 29, 2026

→
86
PeopleHybridHard

You are leading a regulatory compliance project using a hybrid approach where legal reviews follow predictive gates and process implementation uses iterative delivery. A new compliance regulation is announced mid-project that significantly impacts scope. The legal team insists on a complete requirements freeze and full impact analysis before proceeding (6-8 weeks), following their standard risk management protocol. The implementation team wants to continue iterating on unaffected areas and adapt as legal analysis progresses. The compliance deadline is regulatory-mandated and cannot move. Both teams believe their approach protects the organization, and tension is escalating. Several implementation team members have complained that legal is 'blocking progress,' while legal counsel has expressed concerns about 'reckless iteration' on compliance matters. What is your BEST course of action?

September 29, 2026

→
87
PeopleHybridHard

Your hybrid project includes an offshore agile development team and an onshore predictive implementation team. The agile team's Scrum Master has been highly effective, and team members openly share impediments and collaborate well. However, you've noticed in the predictive workstream that team members rarely speak up in status meetings, several risks weren't reported until they became issues, and there's high reliance on formal change control processes even for minor decisions. The predictive team lead is experienced but tends to make decisions unilaterally. Cultural assessments show the offshore team comes from a high power-distance culture while the predictive team reflects the corporate risk-averse culture. What should you do to create greater psychological safety across both workstreams?

September 29, 2026

→
88
PeopleHybridHard

You are managing a product development initiative using a hybrid approach where hardware follows a stage-gate predictive model and software uses Scrum. During integration testing, a critical hardware defect is discovered that requires three months to redesign and remanufacture—extending beyond the current software release schedule. The software team has already completed features dependent on the hardware specifications and wants to continue with new features. The hardware team is demoralized by the setback and feeling blamed. Senior management is pressuring you to maintain the original launch date. How should you lead the teams through this challenge?

September 29, 2026

→
89
PeopleHybridHard

Your organization is piloting agile practices within traditionally predictive portfolios. You're leading a hybrid project with a co-located agile team and distributed predictive workstreams across three continents. After four months, you notice the agile team has strong cohesion and high performance, but the distributed predictive teams report feeling disconnected and undervalued. Several key resources from the predictive workstreams have requested transfers, citing lack of engagement. Executive stakeholders are questioning whether the hybrid approach is sustainable. What is the MOST effective way to address this disparity?

September 29, 2026

→
90
PeopleHybridHard

You are managing a hybrid project where the development team uses Scrum while the compliance and regulatory workstreams follow a predictive approach. During sprint planning, a senior compliance officer insists on attending all Scrum ceremonies and has been providing detailed instructions to developers, effectively bypassing the Product Owner. Team velocity has dropped 30% over two sprints, and developers privately express frustration about conflicting priorities. The compliance officer believes their involvement is necessary due to regulatory risks. How should you address this situation?

September 29, 2026

→
91
PeopleHybridHard

Your hybrid project team includes contractors who are deeply familiar with the legacy system (managed predictively) and permanent employees who are newer but working on the agile modernization effort. During planning, you notice the contractors dominate technical discussions and the permanent employees defer to them, even though the employees will maintain the new system long-term. The contractors are scheduled to roll off in three months. Knowledge transfer was included in the project plan but hasn't been prioritized due to schedule pressure. What should you do?

September 11, 2026

→
92
PeopleHybridHard

You're managing a product development project using a hybrid approach where UX research follows Kanban while engineering uses Scrum. Two team members—a UX researcher and a software engineer—have had escalating disagreements about research timing and findings. The researcher believes the engineer dismisses user insights, while the engineer feels research is delivered too late to influence sprint planning. Both are technically excellent but their conflict is creating tension in cross-functional planning sessions. Other team members are starting to take sides. What is the most effective way to address this conflict?

September 11, 2026

→
93
PeopleHybridHard

Your hybrid project combines agile development sprints with stage-gated regulatory approvals. A high-performing senior developer has become increasingly disengaged after being denied a promotion due to budget constraints. She has begun missing daily standups and her code review quality has declined. Other team members have noticed and morale is affected. The predictive workstream manager suggests documenting performance issues formally. You have a 1-on-1 scheduled with her tomorrow. What is your best approach?

September 11, 2026

→
94
PeopleHybridHard

You're leading a hybrid transformation project where 40% of team members are co-located and 60% are distributed across three time zones. During retrospectives, the remote team members have been unusually quiet, and anonymous feedback reveals they feel their opinions are less valued than those of co-located staff. The co-located team leads tend to have side conversations that exclude remote participants. Despite this, sprint commitments are being met. A key stakeholder suggests this isn't a priority since delivery metrics are satisfactory. How should you respond?

September 11, 2026

→
95
PeopleHybridHard

You are managing a hybrid project where the development team uses Scrum while the infrastructure team follows a predictive approach. Recently, several infrastructure team members have expressed frustration that they are being excluded from sprint reviews and feel disconnected from the product vision. The development team argues that including infrastructure in reviews slows down their feedback cycles. Team velocity has started declining, and integration issues are increasing. What should you do first to address this situation?

September 11, 2026

→
96
PeoplePredictiveMedium

You are managing a manufacturing equipment installation project with team members from multiple countries and cultures. During status meetings, you notice that team members from some cultures rarely speak up or challenge ideas, even when asked directly for input. Meanwhile, team members from other cultures dominate discussions. You need full team participation to identify risks and issues early, as the project follows a sequential phase-gate approach. What should you do to improve team participation?

September 10, 2026

→
97
PeoplePredictiveMedium

You are managing a pharmaceutical project in the execution phase with a fixed timeline due to regulatory requirements. A critical team member who holds specialized knowledge about regulatory compliance has requested a two-week leave for personal reasons during a crucial project phase. No other team member has equivalent expertise. The team member has been highly dedicated and this is their first leave request. According to your resource management plan, coverage for key roles should be identified. What is the best course of action?

September 10, 2026

→
98
PeoplePredictiveMedium

Your construction project has a detailed resource management plan and established team ground rules. A new senior engineer has joined the team and immediately begins suggesting process changes and questioning established procedures during team meetings. While some suggestions have merit, the constant challenges are creating tension among team members who have been following the agreed-upon processes. Several team members have privately expressed frustration to you. What should you do?

September 10, 2026

→
99
PeoplePredictiveMedium

You are leading a software development project using a waterfall methodology. One of your key developers, who has been with the project since initiation, has been consistently high-performing. Recently, you notice their work quality declining and they seem disengaged during team meetings. The project is currently in the detailed design phase with tight deadlines. When you ask about their performance, they mention feeling unchallenged by repetitive tasks. What is the best approach to address this situation?

September 10, 2026

→
100
PeoplePredictiveMedium

You are managing a large infrastructure project using a predictive approach. During the execution phase, you notice that two senior engineers from different functional departments are having frequent disagreements about technical specifications, which is causing delays in deliverables. Both engineers report to different functional managers, not to you. The project schedule shows that their collaboration is critical for the next three months. What should you do first?

September 10, 2026

→