PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

15 questions found

1
ProcessPredictiveEasy

You are leading a pharmaceutical research project to develop a new drug formulation. During risk identification workshops, your team identifies a risk that a key regulatory approval might be delayed by up to 6 months due to recent policy changes. The probability is assessed at 40% and the impact on project completion would be significant. What should you do with this information?

July 13, 2026

2
ProcessPredictiveEasy

You are managing a product development project with a fixed budget of $500,000. At the end of month 3, your earned value analysis shows: Planned Value (PV) = $150,000, Earned Value (EV) = $120,000, and Actual Cost (AC) = $130,000. The project sponsor asks for a status update. What should you report about the project performance?

July 13, 2026

3
ProcessPredictiveEasy

Your team is developing a project schedule for a manufacturing facility upgrade. You have identified all activities, sequenced them, and estimated their durations. Several team members have been assigned to multiple concurrent activities. What should you do next to complete the schedule development process?

July 13, 2026

4
ProcessPredictiveEasy

You are managing a software implementation project using a waterfall approach. The testing phase has just begun, and the QA team reports that 15% of test cases are failing due to missing requirements that were not included in the requirements specification document approved three months ago. The client insists these requirements are essential. What is the best course of action?

July 13, 2026

5
ProcessPredictiveEasy

You are managing a construction project to build a new office building. During the planning phase, you identify that specialized steel beams must be ordered from an overseas supplier with a 12-week lead time. The beams are needed in week 20 of the project schedule. Your team is currently in week 2 of the project. What should you do first?

July 13, 2026

6
ProcessPredictiveEasy

You are managing a product development project using a predictive approach. The project management plan has been approved and execution has begun. During a team meeting, you realize that several team members are unclear about their specific responsibilities and who has decision-making authority for various project activities. This confusion is beginning to cause delays. What document should you reference or update to clarify these roles and responsibilities?

July 2, 2026

7
ProcessPredictiveEasy

You are leading a predictive infrastructure project that is currently in the executing phase. A stakeholder who was not involved in initial planning requests a significant change to the project scope that would add new deliverables. The stakeholder insists the change is critical and wants it implemented immediately. What is the most appropriate action to take?

July 2, 2026

8
ProcessPredictiveEasy

You are managing a manufacturing project to develop a new product line. During the execution phase, one of your team members discovers that a delivered component does not meet the specifications documented in the project requirements. The supplier claims the component meets industry standards, but it clearly does not match what was agreed upon in the procurement contract. What should be your first step?

July 2, 2026

9
ProcessPredictiveEasy

You are planning a software implementation project for a financial services company. The project sponsor has approved a budget of $500,000. During cost planning, you need to establish a performance measurement baseline that will be used to monitor and control project costs throughout execution. The baseline should integrate scope, schedule, and cost to enable earned value management. What should you create?

July 2, 2026

10
ProcessPredictiveEasy

You are managing a construction project to build a new office building. During the planning phase, you need to determine the total project duration by analyzing the sequence of activities and their dependencies. You have identified all activities, estimated their durations, and mapped out their logical relationships. What technique should you use to calculate the longest path through the project and identify the minimum project duration?

July 2, 2026

11
ProcessPredictiveEasy

You have just been assigned as project manager for a new manufacturing project. During your first review of the project documentation, you find the project charter, stakeholder register, and several technical specifications. However, you cannot locate a document that clearly defines what is included and excluded from the project, along with the acceptance criteria for deliverables. Which document are you missing?

May 31, 2026

12
ProcessPredictiveEasy

You are managing a pharmaceutical research project with a strict regulatory timeline. During a weekly team meeting, one of your scientists mentions that a required laboratory test is taking longer than expected due to equipment calibration issues. This task is on the critical path and any delay will impact the project completion date. What should you do first?

May 31, 2026

13
ProcessPredictiveEasy

Your team has identified a risk that a key supplier might not deliver critical components on time, which would delay your project by two weeks. After analyzing the risk, you decide to order the components from a backup supplier who can guarantee delivery within your required timeframe, even though this will cost 15% more. What risk response strategy are you implementing?

May 31, 2026

14
ProcessPredictiveEasy

You are leading a software development project using a predictive approach. The project has been ongoing for three months, and you need to report the current status to stakeholders. You calculate that the project has completed $150,000 worth of work, but you have actually spent $175,000. The planned value at this point was $160,000. What is the cost variance (CV) for this project?

May 31, 2026

15
ProcessPredictiveEasy

You are managing a construction project to build a new office building. During the planning phase, you need to create a detailed breakdown of all the deliverables and work required to complete the project. Your sponsor has asked you to organize this information in a hierarchical structure that will serve as the foundation for planning, scheduling, and cost estimation. What should you create?

May 31, 2026