PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

70 questions found · page 1 of 3

1
ProcessHybridEasy

You are managing a hybrid project for a marketing campaign. The creative design work is being managed using Scrum with two-week sprints, while the media buying and placement follows a predictive approach with fixed deadlines. At the end of sprint 2, the creative team has completed designs that need approval before media placement can proceed. The media buying schedule shows placement must begin in one week. What should you do to ensure both components stay coordinated?

November 14, 2026

→
2
ProcessHybridEasy

Your hybrid project includes a hardware component managed predictively and a software component managed using Kanban. The hardware team reports they are on schedule, but the software team's Kanban board shows several items stuck in the 'In Progress' column for over two weeks. The team's work-in-progress (WIP) limit is being exceeded. As the project manager, what should you do?

November 14, 2026

→
3
ProcessHybridEasy

You are leading a hybrid project where regulatory compliance activities follow a predictive approach with formal gate reviews, while user interface development follows an agile approach with two-week sprints. The compliance team has identified a new regulatory requirement that will impact the user interface. The development team is currently in the middle of sprint 3. What is the best way to handle this new requirement?

November 14, 2026

→
4
ProcessHybridEasy

Your organization is implementing a new product using a hybrid approach. The infrastructure setup follows a waterfall methodology, while feature development uses Scrum. You are creating the overall project schedule. The infrastructure team needs four months to complete their work before any development can begin. The product owner wants to see working features as soon as possible. How should you structure the project timeline?

November 14, 2026

→
5
ProcessHybridEasy

You are managing a hybrid project where the design phase follows a predictive approach and the development phase uses iterative sprints. The design team has completed their work and handed off specifications to the development team. However, the development team reports that several requirements are unclear and need clarification. The design team has already moved on to another project. What should you do first?

November 14, 2026

→
6
ProcessPredictiveEasy

You have just been assigned as the project manager for a bridge construction project that will take 18 months. The project charter has been signed by the sponsor, and you are beginning the planning phase. You need to identify all individuals, groups, and organizations that could impact or be impacted by the project. What process are you performing?

November 2, 2026

→
7
ProcessPredictiveEasy

Your manufacturing project has been running for three months. During a quality inspection, you discover that 15% of the produced components do not meet the specifications defined in the quality management plan. Production is continuing, but you are concerned about the trend. What should be your immediate course of action?

November 2, 2026

→
8
ProcessPredictiveEasy

You are managing a software implementation project for a healthcare client. During a requirements gathering session, the client's Chief Medical Officer requests a new feature that was not included in the original project scope statement or WBS. The feature would add significant value but also increase costs and timeline. What should you do first?

November 2, 2026

→
9
ProcessPredictiveEasy

Your project to develop a new financial reporting system has a budget of $500,000 and is scheduled to take 10 months. You are currently at the end of month 4. According to your tracking, you have spent $220,000 and completed work that was budgeted at $180,000. What is the cost performance of your project at this point?

November 2, 2026

→
10
ProcessPredictiveEasy

You are managing a construction project to build a new office building. During the planning phase, your team has identified all project activities and estimated their durations. You now need to determine when each activity should start and finish, considering their dependencies and resource constraints. What tool or technique should you use to create a visual timeline showing the project schedule?

November 2, 2026

→
11
ProcessPredictiveEasy

You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?

September 24, 2026

→
12
ProcessPredictiveEasy

Your manufacturing project has a budget of $500,000 and is scheduled to last 10 months. You are currently at the end of month 4. According to the project management plan, you should have spent $200,000 by now, but you have actually spent $180,000. The value of the work completed is $190,000. What is the Cost Variance (CV) for this project?

September 24, 2026

→
13
ProcessPredictiveEasy

You are managing a government infrastructure project with strict documentation requirements. During a planning meeting, a stakeholder questions why you need to document lessons learned throughout the project rather than just at the end. The stakeholder is concerned about the additional administrative burden. What is the primary benefit of documenting lessons learned throughout the project lifecycle?

September 24, 2026

→
14
ProcessPredictiveEasy

You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?

September 24, 2026

→
15
ProcessPredictiveEasy

You are managing a construction project to build a new office facility. During project planning, you identify that concrete foundation work cannot begin until the excavation is complete and inspected. The concrete must cure for 7 days before framing can start. You need to document these relationships in your project schedule. What type of dependency exists between excavation and foundation work?

September 24, 2026

→
16
ProcessHybridEasy

A project team is using a hybrid approach where high-level milestones and deliverables were defined upfront, but the team uses two-week sprints to deliver increments. At the end of each sprint, the team holds a review session with stakeholders. A key stakeholder has missed the last three sprint reviews and is now complaining that the project is not meeting their expectations. What should the project manager do?

September 18, 2026

→
17
ProcessHybridEasy

A hybrid project has a fixed budget approved by the steering committee, but features are being delivered iteratively based on business value. After completing 40% of the planned iterations, the project has spent 50% of the budget due to higher than expected infrastructure costs. The remaining features in the backlog are all considered high priority by stakeholders. What should the project manager do next?

September 18, 2026

→
18
ProcessHybridEasy

A project manager is leading a hybrid project where the design phase was completed using a predictive approach, and now the team is moving into iterative development sprints. Several team members who were not involved in the design phase are confused about the project requirements. Velocity has been lower than expected in the first sprint. What should the project manager do?

September 18, 2026

→
19
ProcessHybridEasy

A project team is using a hybrid approach where requirements are gathered upfront but development is executed in two-week sprints. The product owner has just requested a new feature that was not in the original project scope. The team has completed three sprints and has five more planned. What should the project manager do first?

September 18, 2026

→
20
ProcessHybridEasy

A software development project is using a hybrid approach with a defined budget and timeline, but iterative delivery of features. During the third iteration, the team discovers that a core architectural component needs to be redesigned, which will impact the overall project schedule. The project sponsor is concerned about meeting the fixed deadline. What is the best way for the project manager to address this situation?

September 18, 2026

→
21
ProcessAgileEasy

Your agile team has completed a two-week sprint and is preparing for the sprint retrospective. This is the team's first retrospective, and some team members are unclear about the purpose of the meeting. One developer asks why they need to have a retrospective when they already completed a sprint review with stakeholders. How should you explain the PRIMARY purpose of the sprint retrospective?

August 28, 2026

→
22
ProcessAgileEasy

Your team is working on an e-commerce platform using Kanban. The team has a board with columns: To Do, In Progress, Code Review, Testing, and Done. The team notices that work items are piling up in the Code Review column, and the flow of work has slowed significantly. What is the BEST action the team should take to address this bottleneck?

August 28, 2026

→
23
ProcessAgileEasy

You are facilitating a daily standup for your agile development team. One team member begins explaining in detail the technical solution they are implementing and starts discussing code architecture with another developer. The conversation extends beyond 15 minutes, and other team members appear disengaged. As the Scrum Master, what should you do?

August 28, 2026

→
24
ProcessAgileEasy

Your agile team has just completed their third sprint of a mobile app development project. During the sprint review, stakeholders provide feedback and request several changes to features that were demonstrated. The product owner wants to incorporate this feedback. What should the product owner do NEXT with the feedback received during the sprint review?

August 28, 2026

→
25
ProcessAgileEasy

You are managing a software development project using Scrum. During the sprint planning meeting, the development team is estimating user stories for the upcoming sprint. One team member suggests using story points to estimate the relative effort required for each user story. Another team member asks why the team doesn't just estimate in hours instead. What is the PRIMARY benefit of using story points over hours for estimation in an agile project?

August 28, 2026

→