PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

140 questions found · page 2 of 6

26
PeoplePredictiveMedium

You are managing a predictive IT infrastructure project. During a scheduled performance review, one of your team members expresses frustration about not having opportunities for professional growth and mentions feeling underutilized despite having advanced certifications. This team member has been consistently meeting expectations but hasn't been challenged. The project has several complex upcoming tasks that could benefit from this person's advanced skills. How should you respond?

August 11, 2026

27
PeoplePredictiveMedium

You are managing a predictive engineering project with team members from three different countries across multiple time zones. During the first month of execution, you notice that team members in the Asia-Pacific region are not participating actively in status meetings held at 9 AM Eastern Time, and their updates are often brief or submitted via email. The project communication management plan specifies weekly synchronous team meetings. Project deliverables from the Asia-Pacific team are on schedule but there are increasing integration issues with other regional teams. What should you do?

August 11, 2026

28
PeoplePredictiveMedium

You are managing a predictive software development project with a team of 12 members. During the executing phase, you notice that two senior developers frequently disagree on technical approaches during team meetings, causing delays in decision-making. The disagreements are becoming more personal, and other team members are starting to take sides. The project schedule shows that critical path activities are beginning to slip. What should you do first to address this situation?

August 11, 2026

29
PeoplePredictiveMedium

You are leading a construction project using a predictive approach. The project management plan includes a resource management plan with clearly defined roles and responsibilities. A key team member, who is responsible for quality inspections on the critical path, has requested a two-week leave during a crucial phase of the project. This absence was not anticipated in the resource plan. The team member has unique expertise that is difficult to replace. What is the best course of action?

August 11, 2026

30
PeoplePredictiveMedium

You are managing a manufacturing project following a predictive lifecycle. During the planning phase, you identified that the project requires specialized skills in industrial automation that your current team lacks. You have submitted a resource request to functional managers three weeks ago, but they have not yet assigned the required specialist. The project is scheduled to begin the execution phase in two weeks, and this resource is needed for activities on the critical path. What should you do?

August 11, 2026

31
PeoplePredictiveMedium

You are leading a construction project using a predictive approach. One of your senior engineers has been consistently completing tasks ahead of schedule with high quality. However, during a recent team meeting, you noticed other team members seem reluctant to collaborate with this engineer and engagement has decreased. A junior team member privately mentions that the senior engineer is dismissive of others' ideas and takes credit for team contributions. What is the best course of action?

August 3, 2026

32
PeoplePredictiveMedium

You are three months into a twelve-month predictive project developing a new financial system. Your project team includes members from four different countries across three time zones. You've noticed that team members in the Asia-Pacific region rarely speak up during the weekly status meetings held at 9:00 AM EST, though they submit thorough written reports. Decisions made in meetings sometimes need to be revisited because important input was missing. What is the best way to improve team engagement and decision quality?

August 3, 2026

33
PeoplePredictiveMedium

You are managing an infrastructure project using a waterfall approach. During the execution phase, you receive feedback from the functional manager that one of the team members you requested has performance issues in their home department. However, this team member has been performing well on your project tasks and meeting all commitments. The functional manager suggests replacing this person. What is the most appropriate response?

August 3, 2026

34
PeoplePredictiveMedium

Your manufacturing project team of 15 members has been working together for four months following a detailed project plan. You notice that decision-making has become slower, with team members frequently seeking your approval even for minor issues within their assigned responsibilities. Team members appear capable but hesitant to act independently. The project is on schedule, but you are concerned about sustainability. What should you do to improve this situation?

August 3, 2026

35
PeoplePredictiveMedium

You are managing a predictive software implementation project with a planned duration of 18 months. During the planning phase, you identify that three critical team members with specialized technical skills will be needed for months 6-12, but they are currently assigned to other projects. The resource manager indicates these team members might not be available when needed. What should you do first to address this constraint?

August 3, 2026

36
PeoplePredictiveMedium

Your construction project team has been working for four months following a detailed WBS and schedule baseline. You notice during status meetings that one of your experienced engineers consistently provides optimistic progress reports, but when you review actual deliverables, the work is 2-3 weeks behind what was reported. Other team members have begun making comments about this engineer's reliability. The engineer is technically competent and has delivered quality work in the past. What is the most appropriate action?

August 3, 2026

37
PeoplePredictiveMedium

You are managing a product development project using a predictive lifecycle. During the execution phase, you notice that one of your team members, who is typically highly productive, has shown a significant decline in performance over the past three weeks. Deliverables are late, quality has decreased, and the team member seems disengaged during meetings. This is affecting dependent tasks on the critical path. You have a positive working relationship with this individual. What is your best course of action?

August 3, 2026

38
PeoplePredictiveMedium

Your infrastructure project is following a detailed project management plan with strict phase gates. During the design phase, you discover that two team members from different functional departments have incompatible work styles: one prefers detailed documentation and formal reviews before proceeding, while the other favors quick iterations with minimal documentation. Both approaches have merit, but their conflict is delaying deliverables by two weeks. The work requires their collaboration. What should you do?

August 3, 2026

39
PeoplePredictiveMedium

You are leading a manufacturing project with a clearly defined scope and a 12-month timeline. Three months into execution, a senior team member who has been with the company for 15 years frequently challenges your decisions in team meetings, often referencing 'how we've always done things.' This behavior is starting to influence other team members and slow down decision-making. The team member's technical expertise is valuable, but the resistance is affecting team cohesion. How should you address this situation?

August 3, 2026

40
PeoplePredictiveMedium

You are managing a predictive software development project with a fixed timeline of 18 months. During the planning phase, you identify that two critical team members with specialized database expertise will be needed for months 8-12, but they are currently assigned to another project. The resource manager indicates they might become available, but cannot guarantee it. Your project schedule shows these resources on the critical path. What should you do first?

August 3, 2026

41
Business EnvironmentPredictiveHard

You are managing a predictive infrastructure project for a public utility company with a detailed WBS, approved baseline, and 24-month timeline. At month 16, a new CEO joins the organization and introduces a strategic initiative to adopt renewable energy sources. She directs that your project must now incorporate solar panel installations and battery storage systems, representing a 40% scope increase. The CEO expects the same completion date, stating 'we need to show renewable commitment to our board and regulators.' Your project sponsor privately tells you to 'make it work' to avoid conflict with the new executive. The additional scope has not gone through formal change control, and preliminary analysis suggests the original budget is insufficient. What is your best course of action?

July 29, 2026

42
Business EnvironmentPredictiveHard

Your organization has been awarded a predictive project to implement a financial system for a client in a country with strict data sovereignty laws. The project plan, developed six months ago, specified using your company's standard cloud infrastructure hosted in your home country. Two months into the eight-month project, the client's government issues new guidance clarifying that all financial data must be processed and stored within national borders with no exceptions. Your cloud provider has no data centers in the client's country and establishing one would take 14 months. The client will not grant an extension beyond 60 days. Senior management is considering proceeding with the original plan and addressing compliance 'later.' What should you do?

July 29, 2026

43
Business EnvironmentPredictiveHard

You are managing a predictive pharmaceutical research project that requires approval from multiple regulatory bodies across different countries. The project is structured with sequential phase gates, and investment in each subsequent phase depends on passing regulatory reviews. During Phase 2 clinical trials, preliminary data suggests the drug is effective but the European Medicines Agency (EMA) requests additional long-term safety data that was not originally planned, while the FDA is satisfied with current protocols. This additional study will cost $3.2 million and delay market entry by 18 months. Your CFO argues the company should focus only on FDA approval and enter the European market later. What should you recommend?

July 29, 2026

44
Business EnvironmentPredictiveHard

Your organization is executing a three-year government defense project using a predictive approach with strict earned value management (EVM) reporting requirements. At the 15-month progress review, the Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.82. The customer is threatening contract termination due to poor performance. Your executive sponsor suggests re-baselining the project to show improved metrics for the next reporting period. The original baseline was approved by all stakeholders including the government oversight committee. What is the most appropriate action?

July 29, 2026

45
Business EnvironmentPredictiveHard

You are managing a predictive construction project with a fixed-price contract worth $8 million. Six months into the 18-month project, a new environmental regulation is enacted that requires additional soil remediation work not included in the original scope. The customer insists this should be absorbed within the existing contract price, citing the fixed-price nature of the agreement. Your legal team confirms the regulation was not foreseeable at contract signing. The additional work is estimated at $450,000 and will add two months to the schedule. What should be your primary course of action?

July 29, 2026

46
PeoplePredictiveHard

Your pharmaceutical project team of 30 specialists is executing a predictive plan to develop regulatory submission documentation. You have one team member, a senior regulatory expert with 20 years of experience, who possesses unique knowledge critical to project success but consistently demonstrates poor mentoring skills, dismisses junior team members' questions as 'basic,' and has caused two junior regulatory writers to request transfers. The junior members are necessary for document production volume, but the senior expert's specialized knowledge of FDA interactions cannot be easily replaced. Your HR business partner has documented complaints but states the expert has not violated any policies. The project is at the midpoint and approaching critical regulatory milestones. What is your best approach?

July 27, 2026

47
PeoplePredictiveHard

You are leading a construction project that is 60% complete. During a routine team performance assessment, you discover that your site supervisor has been consistently inflating progress reports to make their team appear more productive. Upon investigation, you learn the supervisor was responding to intense pressure from the construction manager to meet aggressive milestones, and feared their team would be viewed negatively. The actual progress indicates the project is approximately 3 weeks behind schedule. The construction manager is unaware of the misreported data and is making decisions based on the inflated reports. What should you do?

July 27, 2026

48
PeoplePredictiveHard

You are managing a government defense project with strict security clearance requirements and a hierarchical organizational structure. A high-performing team member has been consistently delivering excellent technical work but has begun circumventing the established approval chain by directly contacting the client's technical lead to expedite decisions. While this has accelerated some approvals, your project sponsor has received a formal complaint from the client's program manager about protocol violations. The team member argues their actions have saved the project two weeks of schedule delays. How should you address this situation?

July 27, 2026

49
PeoplePredictiveHard

Your predictive project is entering month 8 of a 14-month schedule. Three team members who were critical resources for the design phase have been reassigned to other organizational priorities by their functional managers, despite your resource management plan identifying them as needed through month 10. The remaining team has the technical skills but lacks the institutional knowledge these members possessed. The project sponsor is pressuring you to maintain the original schedule. Performance reviews show current team morale is declining. What is your best course of action?

July 27, 2026

50
PeoplePredictiveHard

You are managing a large infrastructure project with a team of 45 members across engineering, procurement, and construction disciplines. During the execution phase, you notice that two senior engineers who must collaborate on critical path activities have fundamentally different working styles—one prefers detailed documentation and formal approvals, while the other favors quick decisions and minimal paperwork. Their conflict is causing delays in design reviews that are impacting the project schedule. The procurement lead suggests reassigning one engineer to a different work package. What should you do first?

July 27, 2026