PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

75 questions found · page 3 of 3

51
ProcessPredictiveHard

You are managing a complex engineering project with 47 identified risks in your risk register. During a risk audit, your PMO director challenges your risk response strategy for Risk #23, which has a probability of 35% and an impact of $180,000 if it occurs. You have allocated $45,000 from the contingency reserve to implement a mitigation strategy that will reduce the probability to 15% and the impact to $120,000. The mitigation work will take 3 weeks and consume resources from the critical path. The PMO director argues that this mitigation strategy is not cost-effective. What is the most valid justification for your mitigation approach?

June 12, 2026

52
ProcessPredictiveHard

You are managing a software implementation project for a financial services client using a predictive approach with a detailed WBS and network diagram. During the planning phase, you identified a critical dependency: the data migration activity (Activity M, 15 days duration) cannot start until both the database configuration (Activity D, 10 days) and the data cleansing validation (Activity V, 12 days) are complete. Activities D and V can occur in parallel and both start after user requirements approval (Activity R, 8 days). Activity M is followed by user acceptance testing (Activity T, 20 days). If Activity R starts on Day 1, what is the earliest day that user acceptance testing can be completed, and what type of dependency exists between Activities D and V relative to Activity M?

June 12, 2026

53
ProcessPredictiveHard

You are managing a government defense project operating under a Cost Plus Fixed Fee (CPFF) contract with a target cost of $8 million and a fixed fee of $800,000. At the 60% completion point, you discover that a subcontractor has been misclassifying certain labor costs as direct project costs when they should have been indirect overhead costs. The misclassification has inflated your actual costs by $400,000. The client's auditor has identified this issue and is demanding corrective action. The contract includes a clause limiting reimbursable costs to 115% of target cost. What is your most appropriate immediate action as project manager?

June 12, 2026

54
ProcessPredictiveHard

During the execution phase of a pharmaceutical manufacturing facility construction project, a critical piece of specialized equipment arrives on-site three weeks late due to supply chain issues. The equipment installation is on the critical path and has zero float. Your project team has identified four potential corrective actions, each with different implications. The original schedule shows the equipment installation taking 4 weeks with 2 weeks of successor activities before the facility handover. What corrective action should you implement first to minimize overall project impact?

June 12, 2026

55
ProcessPredictiveHard

You are managing a large infrastructure project with a 24-month timeline and a fixed budget of $15 million. At the end of month 12, you conduct an earned value analysis and find: PV = $7.5M, EV = $6.8M, AC = $7.9M. The sponsor is concerned about cost overruns and asks whether the project can be completed within the original budget. Your team estimates that current performance trends will continue. What is the most accurate estimate at completion (EAC) you should report to the sponsor?

June 12, 2026

56
PeoplePredictiveHard

You are managing a complex aerospace engineering project with a 36-month timeline using earned value management (EVM) for performance tracking. Your project has a CPI of 0.89 and SPI of 0.92 at the 12-month mark. The executive steering committee is considering canceling the project due to poor performance. Your analysis reveals that performance issues are concentrated in one engineering team led by a manager who has been with the company for 18 years and has strong relationships with senior executives. This manager is resistant to your process improvement suggestions and has stated that 'engineering excellence cannot be rushed.' Other team leads have privately expressed frustration with this manager's team missing dependencies. The manager's functional director is defensive of their employee and suggests the schedule was unrealistic from the start. What should be your PRIMARY focus to address this situation?

June 1, 2026

57
PeoplePredictiveHard

You are managing a multinational IT implementation project with team members across five countries spanning four time zones. The project follows a traditional waterfall approach with phase gates. Your project management office (PMO) requires weekly status meetings with all core team members present. After three months, you notice declining participation, with team members frequently joining late, multitasking during meetings, or sending delegates. Survey feedback reveals that team members find the meetings unproductive and poorly timed for their time zones. However, the PMO director insists the meeting format is a governance requirement and cannot be changed. Your sponsor is concerned about team engagement scores dropping from 85% to 62%. What is the BEST way to address this situation?

June 1, 2026

58
PeoplePredictiveHard

You are managing a government construction project with a fixed-price contract and a defined scope. Six months into the 18-month project, a new government regulation is enacted that requires additional safety measures, impacting 30% of the completed work and all remaining work. Your project team is demoralized because they believe they will need to redo work that was compliant at the time of completion. The compliance officer insists all work must meet the new standards before final acceptance. The sponsor indicates no additional budget is available and expects you to absorb the changes. During a team meeting, several senior team members openly criticize the sponsor's position and question the project's viability. How should you address this situation?

June 1, 2026

59
PeoplePredictiveHard

You are leading a pharmaceutical product development project following a waterfall methodology with strict regulatory requirements. Your quality manager reports that three team members from the testing department have been consistently missing defect documentation deadlines, causing delays in the validation phase. Upon investigation, you discover these team members are also assigned to two other critical projects and are working 60-70 hours per week. The functional manager states they cannot provide additional resources due to budget constraints. The testing phase must be completed in four weeks to meet the regulatory submission deadline. What is the MOST effective approach to address this situation?

June 1, 2026

60
PeoplePredictiveHard

You are managing a large infrastructure project with a 24-month timeline using a predictive approach. During the execution phase, your technical lead, who has been with the project since initiation and possesses critical knowledge about legacy system integrations, submits their resignation with a two-week notice. The project is currently 40% complete, and the integration work is scheduled to begin in six weeks. Your sponsor is concerned about the impact on the project schedule and is pressuring you to immediately hire a replacement at a higher salary to retain institutional knowledge. What should be your FIRST action as the project manager?

June 1, 2026

61
ProcessPredictiveEasy

You have just been assigned as project manager for a new manufacturing project. During your first review of the project documentation, you find the project charter, stakeholder register, and several technical specifications. However, you cannot locate a document that clearly defines what is included and excluded from the project, along with the acceptance criteria for deliverables. Which document are you missing?

May 31, 2026

62
ProcessPredictiveEasy

You are managing a pharmaceutical research project with a strict regulatory timeline. During a weekly team meeting, one of your scientists mentions that a required laboratory test is taking longer than expected due to equipment calibration issues. This task is on the critical path and any delay will impact the project completion date. What should you do first?

May 31, 2026

63
ProcessPredictiveEasy

Your team has identified a risk that a key supplier might not deliver critical components on time, which would delay your project by two weeks. After analyzing the risk, you decide to order the components from a backup supplier who can guarantee delivery within your required timeframe, even though this will cost 15% more. What risk response strategy are you implementing?

May 31, 2026

64
ProcessPredictiveEasy

You are leading a software development project using a predictive approach. The project has been ongoing for three months, and you need to report the current status to stakeholders. You calculate that the project has completed $150,000 worth of work, but you have actually spent $175,000. The planned value at this point was $160,000. What is the cost variance (CV) for this project?

May 31, 2026

65
ProcessPredictiveEasy

You are managing a construction project to build a new office building. During the planning phase, you need to create a detailed breakdown of all the deliverables and work required to complete the project. Your sponsor has asked you to organize this information in a hierarchical structure that will serve as the foundation for planning, scheduling, and cost estimation. What should you create?

May 31, 2026

66
PeoplePredictiveMedium

You are managing a large infrastructure project using a waterfall approach. During the execution phase, you notice that two senior engineers from different departments are having ongoing disagreements about technical specifications, causing delays in critical path activities. Both engineers are subject matter experts and report to different functional managers, not to you. The disagreements are escalating and beginning to affect team morale. What should you do first?

May 29, 2026

67
PeoplePredictiveMedium

You are managing a construction project using a traditional waterfall approach. The project is in the execution phase, and you have a geographically distributed team with members across three different time zones. You notice that team members in the remote locations seem less engaged during virtual meetings and are often unaware of important decisions made by the core team at headquarters. Productivity metrics show that deliverables from remote team members are occasionally misaligned with project requirements. How should you address this situation?

May 29, 2026

68
PeoplePredictiveMedium

You are managing a multi-year government infrastructure project using a predictive approach. Six months into execution, a key technical lead who has been with the project since initiation submits their resignation, citing a better opportunity elsewhere. This individual possesses critical knowledge about design decisions and has established relationships with several government stakeholders. Their departure is scheduled for three weeks from now. The project is currently on track, but several complex deliverables are planned for the next quarter. What is your best course of action?

May 29, 2026

69
PeoplePredictiveMedium

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

May 29, 2026

70
PeoplePredictiveMedium

You are managing a software implementation project using a waterfall methodology for a financial services client. During the design phase, you discover that one of your key business analysts, who is responsible for defining critical system requirements, lacks experience with the specific regulatory compliance requirements of the financial industry. This knowledge gap was not apparent during resource assignment. The design phase is scheduled to complete in six weeks, and this analyst is already assigned full-time to your project. What should you do?

May 29, 2026

71
ProcessPredictiveMedium

You are managing a government IT project following predictive methodologies. During a phase gate review at the end of the design phase, the project governance board expresses concern that several technical risks identified in the risk register have not been actively managed, though none have materialized yet. The board notes that risk response plans were documented during planning but asks for evidence of ongoing risk monitoring activities. Your risk register has not been updated in six weeks. How should you address this situation moving forward?

May 28, 2026

72
ProcessPredictiveMedium

You are managing a 12-month infrastructure project using a predictive approach. At the end of month 4, you review the project dashboard and notice that planned value (PV) is $400,000, earned value (EV) is $350,000, and actual cost (AC) is $380,000. Several team members report that they have been working on activities that were not originally scheduled for this period because they had available time. What is the PRIMARY issue this situation reveals about project management processes?

May 28, 2026

73
ProcessPredictiveMedium

You are leading a pharmaceutical software implementation project following a predictive approach. The project has completed the planning phase, and you have a detailed WBS, activity list, and resource assignments. During the first month of execution, three team members inform you they will be pulled away for two weeks to support an urgent regulatory audit. This was not anticipated during planning and affects activities on the critical path. What should be your FIRST action as the project manager?

May 28, 2026

74
ProcessPredictiveMedium

Your manufacturing equipment upgrade project is in the executing phase. A key vendor has submitted deliverables for the third milestone, but during the inspection process, your quality assurance team identifies that 15% of the components do not meet the specifications outlined in the procurement contract. The vendor claims the specifications were ambiguous and requests additional payment to remake the components. This is causing a potential two-week delay. What is the BEST course of action?

May 28, 2026

75
ProcessPredictiveMedium

You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?

May 28, 2026