Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
320 questions found · page 3 of 13
You are managing a product development project with multiple external vendors. One vendor has submitted an invoice for $85,000 for completed work. Your procurement specialist reviews the invoice against the contract and identifies that the deliverables match the contract requirements, but notices the vendor applied a 5% price increase that was not in the original fixed-price contract. The vendor claims the increase was discussed verbally with a team member due to scope changes. Your team member confirms a conversation occurred but no formal change was processed. What should you do?
October 25, 2026
Your project team is developing a detailed project schedule for a 16-month infrastructure project. During schedule network analysis, you identify that the critical path has 18 months of duration, exceeding the required completion date by 2 months. You have identified a sequence of activities on the critical path where design and procurement activities could be overlapped to save time. However, overlapping these activities will increase project risk and may require additional design resources. What technique are you considering, and what is the most important factor to evaluate before implementing it?
October 25, 2026
You are managing a manufacturing facility expansion project. During a quality audit, the auditor identifies that three deliverables were completed without the required inspections documented in the quality management plan, though the deliverables appear to meet specifications. The project is currently on schedule and within budget. The construction manager argues that the inspections are bureaucratic and the work quality is evident. What should you do first?
October 25, 2026
During the planning phase of a software development project, your team has identified 47 risks. You've completed qualitative risk analysis and are now preparing for quantitative risk analysis. The project sponsor questions why you need to spend additional time and budget on quantitative analysis when risks have already been prioritized. The project has a firm deadline for regulatory compliance and a contingency reserve of 10% has been allocated. What is the strongest justification for conducting quantitative risk analysis?
October 25, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. After 6 months, the project has spent $1.1 million and completed work valued at $900,000 according to the baseline. The planned value at this point was $1 million. Senior management is concerned about project performance and asks for your assessment. What is the most critical performance issue you should address first?
October 25, 2026
Your organization is executing a predictive software development project for a government client under a firm-fixed-price contract. During the requirements validation phase, you discover that two key requirements conflict with recently updated data privacy laws that were enacted after contract signing but before development began. Legal compliance requires modifying these requirements, which will reduce some functionality the client specifically requested. The contract does not include a clause addressing regulatory changes. Your legal team confirms that non-compliance could expose both organizations to significant penalties. The client's program manager insists you must deliver all original requirements as specified in the contract and suggests finding 'creative technical solutions' to satisfy both the requirements and the laws. Your organization's compliance officer has flagged this as a high-risk issue requiring resolution. What is the most appropriate response?
October 16, 2026
You are leading a predictive ERP implementation project for a global retail organization. During the planning phase, you identified the need for extensive organizational change management, including training 5,000 employees across 12 countries. Management approved a $800K change management budget as part of the $12M project. Nine months into execution, a new CFO conducts a portfolio review and reallocates your change management budget to a revenue-generating digital marketing initiative, stating that 'training is overhead, not a project deliverable.' Your project team warns that without proper change management, user adoption will fail, likely resulting in the ERP system being underutilized. Historical data from similar projects shows 60% failure rate without change management versus 15% with it. What should be your primary concern?
October 16, 2026
Your construction project is building a manufacturing facility in an emerging market. Six months into the 24-month schedule, the host country implements new environmental regulations requiring additional emissions control systems not included in your original scope. Compliance will add $3.5M to the $28M budget and extend the schedule by four months. However, your contracts with the client contain a clause stating that regulatory changes are the client's responsibility. The client's legal team argues that these regulations were proposed (but not enacted) before contract signing, so you should have anticipated them. The client refuses to approve a change request and demands you absorb the costs. Senior management wants to maintain the client relationship for future opportunities worth an estimated $200M. What should you do?
October 16, 2026
You are managing a predictive regulatory compliance project for a pharmaceutical client. During the execution phase, a competitor announces they have received expedited approval for a similar drug using a new regulatory pathway that was not available when your project was initiated. Your client's legal team believes pursuing this new pathway could reduce the compliance timeline from 18 months to 10 months, but it would require re-validating 30% of completed work and restructuring your project baseline. The project steering committee is meeting in two days to decide whether to continue with the original approach or adopt the new pathway. Your analysis shows the new pathway has a 70% probability of success but lacks established precedent. What is your best course of action?
October 16, 2026
Your organization has recently merged with a competitor, creating significant shifts in strategic priorities. The PMO director has asked you to reassess your ongoing predictive infrastructure project, which is 40% complete and on schedule. The merged entity's new strategic plan emphasizes cloud-based solutions, while your project is implementing on-premise data centers. Senior leadership is divided—some want to continue as planned to avoid sunk costs, while others advocate for immediate termination. The project has already consumed $2.4M of a $6M budget and has binding contracts with hardware vendors totaling $1.8M. What should you do first?
October 16, 2026
You are managing a 30-month construction project with a team of 60 people including engineers, architects, contractors, and site workers. The project is performing on schedule and budget. Your HR business partner informs you that a formal complaint has been filed by a junior female engineer alleging gender-based harassment by a senior male site supervisor. The supervisor is a 15-year company veteran with strong technical skills who manages 12 site workers critical to the current phase. Initial HR investigation suggests the complaint has merit. The supervisor denies the allegations and has strong support from his direct reports. The situation is creating tension within the team, with some members supporting each person. What is your primary responsibility as project manager in this situation?
October 15, 2026
You are managing a critical 20-month regulatory compliance project for a financial services organization. The project team includes 8 full-time employees and 12 contract resources. Six months into the project, your organization announces a major restructuring that will affect 30% of the workforce. Rumors are widespread, team morale has dropped significantly, and productivity has declined by 15% over the past three weeks. Two key team members have confidentially told you they are interviewing elsewhere. Your sponsor has confirmed that no project team members are targeted for layoffs, but this information is confidential and cannot be shared broadly for another four weeks. What should you do to maintain team performance during this period?
October 15, 2026
You are managing a 18-month enterprise software implementation project using a predictive approach. During the execution phase, you notice that two senior developers, who previously worked well together, are now in constant conflict affecting team morale. The conflict centers on technical design decisions, with each developer believing their approach is superior. Both are high performers, and their disagreement has created factions within the 12-person development team. Three other developers have approached you privately expressing frustration about the hostile environment. The conflict is not yet impacting deliverables but is affecting team collaboration and knowledge sharing. What is the most effective approach to resolve this conflict?
October 15, 2026
You are leading a 36-month manufacturing project with a geographically distributed team across four countries. A highly skilled subject matter expert (SME) based in Germany, who is critical to the design phase, has been underperforming for six weeks. Her work quality has declined, she misses virtual meetings, and other team members report communication difficulties. You learn through informal channels that she is dealing with a serious family health crisis but has not disclosed this officially. Your project is entering a critical phase where her expertise is essential, and replacing her would cause a 4-6 week delay. How should you handle this situation?
October 15, 2026
You are managing a 24-month government infrastructure project with a team of 45 resources across five functional departments. During month 8, performance metrics show that three senior technical leads from different departments are consistently missing deliverable deadlines, causing schedule variance. When you investigate, you discover that all three leads are being pulled into other departmental priorities by their functional managers, despite the resource agreements established during project planning. The functional managers claim their departmental work takes precedence. What should you do first to address this situation?
October 15, 2026
You are managing a product development project that is currently in the testing phase. During a quality audit, the quality assurance team identifies that three deliverables do not meet the quality standards defined in the quality management plan, though they meet the customer's acceptance criteria as stated in the scope statement. The rework required to meet the quality standards would cost an additional $35,000 and delay the project by two weeks. The customer has not complained and seems satisfied with the current deliverables. What should you do?
October 12, 2026
Your project team has completed the WBS decomposition for a 14-month infrastructure project. During the Define Activities process, a senior team member suggests that some work packages are still too large and should be broken down further into activities. Another team member argues that the current work packages are appropriate and further decomposition would create unnecessary detail. The work packages in question represent 3-4 weeks of work each. As the project manager, how should you handle this situation?
October 12, 2026
You are managing a software implementation project for a government agency using a waterfall approach. The requirements documentation has been approved and baselined. During the design phase, the compliance officer identifies a new regulatory requirement that was published last month and will be effective in three months. Implementing this requirement would require changes to 15% of the approved requirements and add approximately $75,000 to the $500,000 budget. The project is currently on schedule and within budget. What should you do FIRST?
October 12, 2026
During the execution phase of a manufacturing facility upgrade project, a key supplier informs you that a critical component will be delayed by three weeks due to supply chain disruptions. This component is on the critical path and is needed for installation activities scheduled to begin in four weeks. You have a contingency reserve allocated in the budget, and the schedule baseline includes buffer time but not specifically for this activity. The delay will impact subsequent critical path activities. What is the BEST course of action?
October 12, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 12-month timeline. After six months, the project has completed 40% of the planned work and spent $1.3 million. The project sponsor is concerned about cost performance and asks you to provide an analysis. Based on earned value metrics, you calculate that CPI is 0.77 and SPI is 0.80. The sponsor wants to know if the project can be completed within the original budget if current performance continues. What should you recommend?
October 12, 2026
You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?
October 9, 2026
You are managing a defense contractor project using a firm-fixed-price contract worth $28M. During planning, you identified 47 risks and developed response plans with allocated contingency reserves totaling $2.1M. At the 60% completion point, you have consumed $1.85M of contingency reserves, primarily due to three risks that materialized with greater impact than anticipated. You identify a new high-probability, high-impact risk related to a critical supplier's financial instability that could halt production of a custom component with no alternative sources. The risk response would require $450K for a mitigation strategy (qualifying a second supplier). Your remaining contingency reserve is $250K, and management reserves are $800K controlled by the sponsor. What should you do?
October 9, 2026
Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?
October 9, 2026
You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. The design phase deliverables were approved three months ago, and construction is 40% complete. A new regulatory requirement has been published that mandates additional safety features in the HVAC system, requiring significant design changes. The change will cost $2.8M (8% of the total budget) and add 6 weeks to the critical path. The regulatory compliance officer insists this is a mandatory change and not subject to change control. Your project charter states that regulatory compliance changes require automatic approval. What should you do FIRST?
October 9, 2026
You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?
October 9, 2026
