Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
140 questions found · page 1 of 6
You are managing a telecommunications infrastructure project using a predictive approach. The project team includes specialists from engineering, procurement, and installation departments. During project planning, you identified that the engineering team needs to complete detailed designs before procurement can begin vendor selection, and installation cannot start until equipment arrives. You've created a detailed schedule with these dependencies. However, the engineering manager informs you that his team is being pulled to support an emergency on another project and will be unavailable for three weeks, which will impact your critical path. What is the best way to handle this situation?
October 5, 2026
You are managing a manufacturing project following a predictive life cycle. During a milestone review, you discover that one of your team leads has consistently overstated the completion percentage of their work packages in status reports. Upon investigation, you find the actual progress is about 20% behind what was reported, though the work quality is acceptable. This team lead has been with the company for 15 years and is generally reliable. The project is now showing as on-track when it is actually behind schedule. What should be your first course of action?
October 5, 2026
You are leading a construction project with a detailed work breakdown structure and baseline schedule. A team member who is relatively new to the organization approaches you privately and mentions that they feel intimidated by the project's senior architect, who frequently dismisses their input during technical meetings. The team member is responsible for quality inspections and their observations are important for project success. The senior architect is known for being direct but has excellent technical expertise. How should you address this situation?
October 5, 2026
You are managing a software development project using a waterfall methodology. During the development phase, your lead developer informs you that she has received a job offer from another company and will be leaving in three weeks. She is the only team member with deep knowledge of the legacy system integration, which is critical for the next phase. The project is currently on schedule, and this phase is expected to complete in two months. What is the most effective action to take?
October 5, 2026
You are managing a large infrastructure project using a predictive approach with a team of 45 members across three locations. During the executing phase, you notice that two senior engineers from different locations are in constant disagreement about technical specifications, causing delays in deliverables. The project schedule shows this work is on the critical path. Both engineers are highly skilled and have worked on similar projects before. What should you do first to address this situation?
October 5, 2026
You are managing a product development project using a hybrid approach. The UX design work follows a phase-gate process to ensure brand consistency, while development uses Scrum. During Sprint 5, a major competitor launches a similar product with a feature your team planned for Sprint 8. The product owner wants to reprioritize immediately and skip the UX design review to accelerate delivery. The UX lead insists that bypassing the design process will create technical debt and brand inconsistency. Both are escalating to you. What is your best course of action?
October 4, 2026
Your organization is piloting a hybrid approach on a strategic initiative. The predictive-focused PMO requires detailed monthly status reports with earned value metrics, while your agile team tracks progress through burndown charts and sprint reviews. Team members are spending six hours per month translating their agile metrics into PMO templates, and they're frustrated by what they perceive as duplicative reporting. The PMO director insists on standardized reporting for portfolio visibility. How should you address this situation?
October 4, 2026
You are leading a hybrid project where regulatory compliance work follows a waterfall approach due to audit requirements, while new feature development uses Kanban. A senior developer who excels at iterative development has been assigned to document compliance procedures, a predictive task requiring detailed upfront planning. The developer is frustrated, producing low-quality documentation, and has privately expressed feeling underutilized. Meanwhile, a compliance specialist is struggling with the ambiguity of Kanban flow. What should you do?
October 4, 2026
Your hybrid project team includes five co-located developers working in two-week sprints and three distributed subject matter experts who contribute according to a predictive schedule with monthly milestones. The SMEs have missed two consecutive touchpoints, causing the development team to make assumptions that later required rework. The SMEs claim they were unaware of the specific timing of developer needs. You need to improve team cohesion and reduce waste. What is the most effective approach?
October 4, 2026
You are managing a hybrid project where the development team uses Scrum for product features while the infrastructure team follows a waterfall approach. During sprint planning, the development team commits to delivering a new customer portal feature. However, the infrastructure team later reports they cannot provision the required cloud servers until their phase-gate approval is completed in three weeks, which will cause the sprint goal to fail. Team morale is declining as developers feel blocked. What should you do first?
October 4, 2026
You are coaching a newly formed agile team that includes three junior developers and two senior developers. During the first two sprints, you notice the senior developers are completing most of the complex stories while junior developers are assigned only simple tasks. The senior developers say they are trying to help the team meet commitments, but the junior developers express frustration in private that they are not learning new skills. Sprint goals are being met, but you are concerned about long-term team capability and sustainability. What is the best approach?
September 29, 2026
Your agile team has two developers who consistently clash during daily standups and sprint planning. One developer prefers thoroughly discussing technical approaches before committing to work, while the other prefers to start coding quickly and iterate. Their disagreements are starting to affect team dynamics, with other team members avoiding engaging in technical discussions. Both developers are highly skilled and their work quality is excellent. Yesterday, their disagreement during refinement caused the session to run 30 minutes over time. What should you do?
September 29, 2026
During a sprint review, a key stakeholder becomes visibly upset when seeing the increment, stating that the features demonstrated are not what they expected, even though the stories were approved during sprint planning. The product owner defends the work, saying the team delivered exactly what was written in the user stories. The stakeholder insists the team must redo the work. Team morale drops immediately as they feel their hard work is being dismissed. How should you address this conflict?
September 29, 2026
Your agile development team includes members from four different countries across three time zones. During sprint planning, you notice that team members in the Asia-Pacific region rarely speak up, while team members in North America dominate the conversation. The sprint retrospectives show similar patterns. The team's velocity has been declining over the past two sprints, and some stories are being carried over because requirements were misunderstood. What is the most effective action to improve team collaboration?
September 29, 2026
You are leading an agile project team that has been working together for three sprints. During the latest retrospective, several team members express frustration that decisions are often delayed because they feel they need to wait for your approval on minor implementation details. The team has strong technical skills and has consistently met their sprint commitments. Team velocity is stable, but you notice team members seem hesitant to self-organize. What should you do to address this situation?
September 29, 2026
You are managing a manufacturing equipment installation project with team members from multiple countries and cultures. During status meetings, you notice that team members from some cultures rarely speak up or challenge ideas, even when asked directly for input. Meanwhile, team members from other cultures dominate discussions. You need full team participation to identify risks and issues early, as the project follows a sequential phase-gate approach. What should you do to improve team participation?
September 10, 2026
You are managing a pharmaceutical project in the execution phase with a fixed timeline due to regulatory requirements. A critical team member who holds specialized knowledge about regulatory compliance has requested a two-week leave for personal reasons during a crucial project phase. No other team member has equivalent expertise. The team member has been highly dedicated and this is their first leave request. According to your resource management plan, coverage for key roles should be identified. What is the best course of action?
September 10, 2026
Your construction project has a detailed resource management plan and established team ground rules. A new senior engineer has joined the team and immediately begins suggesting process changes and questioning established procedures during team meetings. While some suggestions have merit, the constant challenges are creating tension among team members who have been following the agreed-upon processes. Several team members have privately expressed frustration to you. What should you do?
September 10, 2026
You are leading a software development project using a waterfall methodology. One of your key developers, who has been with the project since initiation, has been consistently high-performing. Recently, you notice their work quality declining and they seem disengaged during team meetings. The project is currently in the detailed design phase with tight deadlines. When you ask about their performance, they mention feeling unchallenged by repetitive tasks. What is the best approach to address this situation?
September 10, 2026
You are managing a large infrastructure project using a predictive approach. During the execution phase, you notice that two senior engineers from different functional departments are having frequent disagreements about technical specifications, which is causing delays in deliverables. Both engineers report to different functional managers, not to you. The project schedule shows that their collaboration is critical for the next three months. What should you do first?
September 10, 2026
You are managing a predictive pharmaceutical project with strict regulatory deliverables. A team member consistently produces high-quality work but submits deliverables 2-3 days after agreed-upon deadlines, causing delays in the dependent review processes. When you discussed this previously, the team member explained they need extra time to ensure quality and compliance. Other team members are becoming frustrated with the repeated delays. How should you address this situation?
August 31, 2026
You are three months into a 12-month predictive project when your most experienced business analyst announces she will be leaving the company in four weeks. She is the only team member who fully understands the complex regulatory requirements that drive 40% of project deliverables. The project baseline schedule shows her involvement is critical for the next six months. What is your best course of action?
August 31, 2026
You are managing a predictive software implementation project with a team of 15 members. During a weekly status meeting, two senior developers publicly disagree about the technical approach for a critical module, and the discussion becomes heated. Other team members are visibly uncomfortable, and the meeting agenda is derailed. You need to restore team collaboration while ensuring the technical issue gets resolved. What should you do first?
August 31, 2026
You are managing a predictive infrastructure project with a detailed resource management plan. Your functional manager informs you that one of your key team members will need to support a critical production issue for the next two weeks, reducing their availability to your project from 100% to 25%. This team member is scheduled to complete design activities that are on the critical path. What is the most appropriate action?
August 31, 2026
Your predictive construction project team includes contractors from three different companies. You notice that team members primarily communicate within their own company groups and rarely collaborate across organizational boundaries. This siloed behavior is causing information gaps and coordination delays. Performance reports show the project is currently on schedule, but you're concerned about upcoming integration activities. What should you do?
August 31, 2026
