PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

45 questions found · page 1 of 2

1
PeoplePredictiveMedium

You are managing a predictive project to implement a new financial reporting system. Midway through the project, your lead business analyst, who has been with the company for 15 years and knows the legacy systems intimately, announces she will retire in six weeks. Her knowledge is crucial for the remaining requirements validation and user acceptance testing phases scheduled over the next three months. She is willing to help with transition activities before leaving. What is your best course of action?

July 8, 2026

2
PeoplePredictiveMedium

You are leading a predictive infrastructure project with team members from three different departments. During the third monthly project review meeting, you notice that members from the operations department consistently remain silent when asked for input, even on topics directly affecting their work. Later, one operations team member privately tells you they feel their opinions don't matter because engineering always dominates the discussions. The project requires integrated input from all departments to succeed. How should you address this situation?

July 8, 2026

3
PeoplePredictiveMedium

Your predictive manufacturing project is entering the execution phase with a baseline schedule approved by all stakeholders. You discover that a key subject matter expert, who was promised to your project at 50% allocation, is now only available 20% due to competing organizational priorities. This resource was critical for your planned knowledge transfer sessions with the implementation team. The functional manager apologizes but says they cannot change the allocation. What should you do?

July 8, 2026

4
PeoplePredictiveMedium

You are managing a construction project using a predictive approach with a detailed WBS and Gantt chart. Three months into the six-month project, you notice that one of your team leads has been consistently missing status meeting deadlines and providing incomplete progress reports. However, their team's deliverables are being completed on time and meeting quality standards. Other team leads have started complaining about the inconsistent reporting. What is the most appropriate action?

July 8, 2026

5
PeoplePredictiveMedium

You are managing a predictive software development project with a team of 12 members. During the planning phase, you notice that two senior developers, who must work closely on the database architecture, have a history of conflict from a previous project. The project schedule is tight, and their collaboration is critical for meeting the milestone dates. Team morale appears positive otherwise, but you're concerned this unresolved tension could impact performance. What should you do first?

July 8, 2026

6
PeopleHybridMedium

You are leading a product development project using a hybrid approach where design and development follow Scrum, but manufacturing and supply chain operate in predictive phases. A key team member from manufacturing, who has 20 years of experience, consistently questions agile practices in cross-functional meetings, stating 'this would never work in the real world' and 'we tried this before and it failed.' This is creating doubt among other team members and reducing engagement in collaborative planning sessions. The manufacturing manager confirms this person's technical expertise is critical to project success. What is the most appropriate way to address this?

July 7, 2026

7
PeopleHybridMedium

Your hybrid project team includes employees and contractors from a vendor organization. The vendor's contract specifies fixed deliverables and milestones, while your internal team operates using agile sprints with flexible scope. During a sprint review, stakeholders request significant changes that would benefit the product but would require substantial rework from the vendor team. The vendor project manager states they cannot accommodate changes without a contract modification and additional payment. Your internal team is frustrated by the vendor's 'inflexibility.' What should you do?

July 7, 2026

8
PeopleHybridMedium

You are managing a hybrid transformation project where half the team is experienced with agile practices and half has only worked in traditional environments. During the first iteration planning session, the traditional team members remain silent while the agile-experienced members dominate the discussion. Later, a traditionally-trained business analyst tells you privately that they feel their expertise in requirements documentation is no longer valued. The project requires both detailed requirements for regulatory purposes and iterative development. How should you address this situation?

July 7, 2026

9
PeopleHybridMedium

Your hybrid project has a distributed team across three time zones. The agile software development team conducts daily standups, while the regulatory compliance team works in traditional phases with monthly reviews. You notice that collaboration between these groups is minimal, causing delays when compliance requirements impact sprint deliverables. The compliance lead insists their work cannot be broken into smaller increments, while the development team lead complains about last-minute compliance changes. What is the best approach to improve collaboration?

July 7, 2026

10
PeopleHybridMedium

You are leading a hybrid project where the development team works in two-week sprints while the infrastructure team follows a waterfall approach with phase gates. During sprint planning, a senior developer publicly criticizes a junior team member's previous work, causing visible discomfort. The junior member becomes withdrawn for the remainder of the meeting. Several team members later approach you expressing concern about the negative team dynamics. What should you do first to address this situation?

July 7, 2026

11
PeopleAgileMedium

During sprint planning, your agile team commits to 30 story points based on their historical velocity. Midway through the sprint, a critical production bug requires immediate attention, consuming 40% of the team's capacity. The product owner insists that all originally planned stories must still be completed and suggests the team work overtime. Several team members express concern about burnout. What is the most appropriate action?

June 29, 2026

12
PeopleAgileMedium

Your distributed agile team spans three time zones across North America, Europe, and Asia. Team members have complained that the daily standup time rotates to accommodate everyone, but this means each region experiences inconvenient times regularly. Additionally, team bonding has suffered because members rarely interact outside of formal ceremonies. Sprint retrospectives reveal low team morale despite delivering features successfully. What should you prioritize to improve team cohesion?

June 29, 2026

13
PeopleAgileMedium

A new team member joined your agile team two weeks ago. She has strong technical skills but comes from a traditional waterfall background. During the daily standup, she provides detailed status reports to you rather than discussing impediments with the team. She also waits for task assignments instead of pulling work from the board. Other team members are becoming frustrated with her approach. How should you handle this situation?

June 29, 2026

14
PeopleAgileMedium

Your agile development team is struggling to complete stories within sprints. During planning, developers frequently say they cannot estimate stories because requirements are unclear. The product owner insists the stories are sufficiently detailed and becomes defensive when the team asks questions. This pattern has repeated for four sprints, causing incomplete work and team frustration. As the project manager, what is your best course of action?

June 29, 2026

15
PeopleAgileMedium

You are leading an agile team that has been working together for three sprints. During the latest retrospective, you notice that two team members consistently dominate the conversation while three others remain silent. The silent members later confide in you that they feel their ideas are not valued. Team velocity has been declining, and you suspect the lack of diverse input is affecting quality. What should you do first to address this situation?

June 29, 2026

16
PeoplePredictiveMedium

You are managing a large infrastructure project with a team of 45 members across multiple departments. During the weekly status meeting, two senior engineers from different functional areas have a heated disagreement about the technical approach for a critical deliverable. The conflict is affecting team morale, and other team members are beginning to take sides. The project is currently on schedule, but this issue could impact the next milestone in three weeks. What should you do first as the project manager?

June 17, 2026

17
PeoplePredictiveMedium

You are managing a construction project that is entering the execution phase. During resource planning, you identified that three specialized technicians are needed for a critical phase starting in six weeks. Your functional manager has just informed you that due to competing organizational priorities, only two of the three requested technicians will be available. The project baseline assumed all three resources would be available, and this shortage will likely extend the project schedule by two weeks. What should you do next?

June 17, 2026

18
PeoplePredictiveMedium

You are managing a multi-phase engineering project that is currently in month 8 of a 16-month schedule. During performance reviews, you notice that four team members who joined the project three months ago are not integrating well with the existing team. They frequently work in isolation, miss key communications, and their deliverables require significant rework. The original team members have mentioned feeling frustrated with the additional coordination effort. These four members were added to accelerate the project schedule, but productivity has not improved as expected. What is the best approach to address this situation?

June 17, 2026

19
PeoplePredictiveMedium

You are managing a product development project for a manufacturing company. A team member from the quality assurance department approaches you privately and expresses concern that another team member from engineering has been taking shortcuts in the testing protocols to meet schedule deadlines. The QA team member has evidence of incomplete test documentation but is reluctant to raise the issue directly because the engineering team member is senior and well-connected in the organization. The project is currently showing green status, but you know that quality issues could have serious compliance implications. How should you address this situation?

June 17, 2026

20
PeoplePredictiveMedium

You are leading a predictive software development project for a financial institution. A key developer who is responsible for the security module has been consistently missing deadlines over the past three weeks. This developer was previously a high performer. During a one-on-one conversation, you learn that they are dealing with a personal family situation that requires significant attention. The security module is on the critical path, and any further delays will impact the project delivery date committed to the sponsor. What is the most appropriate course of action?

June 17, 2026

21
PeopleHybridMedium

You are managing a hybrid project with a distributed team across three time zones. The agile components use Scrum with daily standups at 9 AM EST, while the waterfall components have weekly status meetings at 10 AM EST. Team members in the Pacific time zone (6 AM and 7 AM their local time) have complained these meeting times are difficult. One team member has started skipping standups, and another has requested to send written updates instead. Productivity metrics show the Pacific team's velocity declining. How should you address this situation?

June 9, 2026

22
PeopleHybridMedium

Your organization is transitioning to hybrid project delivery. You are managing a project where the design phase is planned using predictive methods with detailed requirements, while development will use iterative sprints. During design phase completion, your most experienced business analyst accepts a position at another company and will leave in two weeks. The development team is scheduled to start sprints immediately after the design phase ends. What should be your primary focus to ensure team continuity?

June 9, 2026

23
PeopleHybridMedium

You are leading a hybrid project where feature development follows Scrum, but infrastructure deployment requires formal change control and approval gates. A senior developer who has extensive experience with agile approaches has been openly criticizing the change control process in team channels, calling it 'bureaucratic waste' and discouraging newer team members from following it. This is creating tension with the operations team who manages the approval gates. What is the most appropriate way to address this situation?

June 9, 2026

24
PeopleHybridMedium

Your hybrid project team consists of eight developers working in sprints and four business analysts following a stage-gate process. You notice that the developers rarely interact with the business analysts, leading to misaligned requirements. The project sponsor has emphasized the importance of knowledge sharing across the team. One developer mentions they prefer written documentation over meetings. How should you best facilitate knowledge transfer between these groups?

June 9, 2026

25
PeopleHybridMedium

You are managing a hybrid project where the development team works in two-week sprints while the regulatory compliance team follows a traditional waterfall approach. During a retrospective, several development team members express frustration that compliance reviews are causing delays at the end of each sprint. The compliance team lead explains they need at least five business days to review deliverables but are only notified when the sprint ends. What should you do first to address this conflict?

June 9, 2026