Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
250 questions found · page 4 of 10
You are managing a pharmaceutical product development project following a predictive lifecycle with strict regulatory requirements. During the testing phase, a critical test reveals unexpected results that require investigation before proceeding. This was not anticipated in the risk register. The project schedule has no float, and any delay will impact the launch date that has been publicly announced to investors. The quality manager insists on a thorough investigation that will take three weeks, while the sponsor pressures you to proceed with limited investigation to maintain the schedule. What should you do?
September 9, 2026
You are managing a manufacturing project using a predictive approach. During a quality inspection, you discover that 15% of the completed components do not meet the quality specifications defined in the quality management plan. The components are already installed, and removing them would require significant rework, causing a two-week delay and 20% cost increase. The defects are minor and do not affect functionality, but they do not meet documented specifications. Your team suggests accepting the components as-is. What should you do?
September 9, 2026
Your software development project is following a predictive lifecycle with detailed upfront planning. You are currently in the execution phase, and the project is on schedule and within budget. A key stakeholder who was minimally involved during planning now requests a significant feature addition that would provide substantial business value but was not included in the original scope. The stakeholder insists this feature is critical and should be added immediately without formal approval processes. What is the most appropriate action?
September 9, 2026
You are managing a construction project using a predictive approach. During the execution phase, a major supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. The project schedule shows this material is on the critical path, and the delay will impact the project completion date. You review the risk register and find this supplier delay was identified as a potential risk with a mitigation strategy documented. What should you do first?
September 9, 2026
You are managing a telecommunications infrastructure project using a predictive methodology. The project is 60% complete when you conduct an earned value analysis. The results show: PV = $800,000, EV = $720,000, AC = $780,000, BAC = $1,200,000. Based on these metrics, the project team is concerned about performance. The sponsor asks you to forecast the total cost at completion and explain the project's current performance status. What is the most accurate assessment?
September 9, 2026
Your organization is executing a portfolio of projects, and you are managing a critical ERP implementation with a 18-month timeline. At month 10, the portfolio review board redirects your two most experienced technical resources to a new executive priority project for the next 90 days. These resources are currently assigned to critical path activities for database migration and integration testing. Your resource manager can provide three junior resources as replacements, but they lack ERP experience. The portfolio manager states this is non-negotiable due to business priorities. Your analysis shows that using junior resources will likely cause 6-8 weeks of schedule delay and increase risk of integration defects. What should be your PRIMARY response?
September 9, 2026
You are managing a government defense project with a fixed-price contract and strict security protocols. At the 40% completion point, a new regulation is published requiring additional cybersecurity controls that were not in the original scope. Implementing these controls will add $1.2M to project costs and 4 months to the schedule. Your contracts team confirms this qualifies as a changes in law provision under the contract. However, the government client's project office indicates their fiscal year budget cannot accommodate the increase and suggests descoping other requirements to offset costs. Your technical lead warns that descoping any current requirements will likely fail the final security certification. What is the MOST appropriate next step?
September 9, 2026
You are managing a large infrastructure project with a 24-month timeline and a $15M budget. During month 14, your Cost Performance Index (CPI) is 0.89 and Schedule Performance Index (SPI) is 0.92. The project has consumed $9.2M of the budget. Your sponsor is concerned about cost overruns and demands that you reduce spending immediately. The critical path activities for the next three months include foundation work that requires specialized equipment already procured and scheduled. What should be your PRIMARY response to the sponsor's demand?
September 9, 2026
You are leading a construction project that is 65% complete when a key subcontractor declares bankruptcy. This subcontractor was responsible for all electrical work, representing 20% of remaining project activities. Three alternative subcontractors have been identified: Vendor A can start immediately but costs 35% more; Vendor B matches the original cost but needs 45 days mobilization; Vendor C costs 15% more and needs 20 days mobilization. The electrical work is on the critical path, and contract penalties of $50,000 per week apply after the baseline completion date, which is 90 days away. Your analysis shows current electrical work would take 70 days. What is the BEST course of action?
September 9, 2026
Your pharmaceutical project is developing a new drug formulation with strict FDA validation requirements. The project is using a stage-gate approach with formal quality reviews at each phase. During the Phase 2 gate review, quality auditors identify that 12 of 47 deliverables from Phase 1 do not fully meet the documented acceptance criteria, though they passed initial reviews. Reworking these deliverables will cost $340,000 and delay the project by 6 weeks. The Phase 1 project manager, who has since left the company, approved these deliverables based on verbal agreements with stakeholders that differ from the documented requirements. What should you do FIRST?
September 9, 2026
A project manager is leading a predictive construction project for a manufacturing facility. During the planning phase, the sponsor requests that the project incorporate sustainable building practices to align with the organization's new environmental strategy announced last quarter. The project baseline has been approved, and construction is scheduled to begin in two weeks. The sponsor emphasizes that this alignment is critical for the company's public commitments. What should the project manager do first?
August 31, 2026
A project manager is overseeing a predictive ERP implementation project for a multinational corporation. During execution, the organization announces a merger with another company that uses a different ERP system. Senior leadership has not yet decided which ERP system will be used for the combined organization, but the decision is expected within three months. The current project is 40% complete and scheduled to finish in eight months. What should the project manager do?
August 31, 2026
A project manager is leading a government infrastructure project using a predictive approach. A new regulation is passed requiring all public infrastructure projects to conduct additional environmental impact assessments that were not part of the original compliance requirements. The regulation becomes effective immediately and applies to all ongoing projects. The project team has already completed the design phase, and procurement activities are underway. What is the most appropriate action?
August 31, 2026
A pharmaceutical project manager is overseeing the development of a new drug delivery system using a waterfall approach. Midway through the execution phase, a competitor releases a similar product with superior features that is gaining significant market share. The executive team is concerned about the project's business value and market viability. The project is currently on schedule and within budget, with 60% of deliverables completed. What should the project manager recommend?
August 31, 2026
A project manager is leading a predictive software development project for a financial services client. The project team has identified an opportunity to implement a new technology that would significantly reduce operational costs for the client after project completion. However, adopting this technology would require additional development time and increase the project budget by 15%. The current project is meeting all baseline requirements, and the client has not requested this enhancement. What should the project manager do?
August 31, 2026
You are managing a predictive pharmaceutical project with strict regulatory deliverables. A team member consistently produces high-quality work but submits deliverables 2-3 days after agreed-upon deadlines, causing delays in the dependent review processes. When you discussed this previously, the team member explained they need extra time to ensure quality and compliance. Other team members are becoming frustrated with the repeated delays. How should you address this situation?
August 31, 2026
You are three months into a 12-month predictive project when your most experienced business analyst announces she will be leaving the company in four weeks. She is the only team member who fully understands the complex regulatory requirements that drive 40% of project deliverables. The project baseline schedule shows her involvement is critical for the next six months. What is your best course of action?
August 31, 2026
You are managing a predictive software implementation project with a team of 15 members. During a weekly status meeting, two senior developers publicly disagree about the technical approach for a critical module, and the discussion becomes heated. Other team members are visibly uncomfortable, and the meeting agenda is derailed. You need to restore team collaboration while ensuring the technical issue gets resolved. What should you do first?
August 31, 2026
You are managing a predictive infrastructure project with a detailed resource management plan. Your functional manager informs you that one of your key team members will need to support a critical production issue for the next two weeks, reducing their availability to your project from 100% to 25%. This team member is scheduled to complete design activities that are on the critical path. What is the most appropriate action?
August 31, 2026
Your predictive construction project team includes contractors from three different companies. You notice that team members primarily communicate within their own company groups and rarely collaborate across organizational boundaries. This siloed behavior is causing information gaps and coordination delays. Performance reports show the project is currently on schedule, but you're concerned about upcoming integration activities. What should you do?
August 31, 2026
You are managing a manufacturing facility construction project with a detailed WBS and baseline schedule. During month 4 of the 18-month project, you receive the performance reviews for your project team members from their functional managers. You notice that one of your key electrical engineers received a below-average rating, citing lack of contribution to departmental initiatives. However, this engineer has been fully dedicated to your project, meeting all assigned deadlines and producing high-quality work. The functional manager suggests reducing this person's allocation to your project. What should you do?
August 31, 2026
You are leading a government software development project using a waterfall approach. Three months into the project, you notice that two senior developers who were highly collaborative during planning have become increasingly adversarial, disagreeing on technical approaches during design reviews and making critical comments about each other's work. Their conflict is starting to affect team morale, and other team members are beginning to take sides. The design phase is scheduled to complete in two weeks. What is your best course of action?
August 31, 2026
You are managing a complex infrastructure project with a 24-month timeline. During the planning phase, you identify that your team will need specialized database architects for months 8-12, but your functional manager can only commit these resources for months 10-14 due to competing organizational priorities. The project schedule shows critical database design activities starting in month 8, and any delay would impact the critical path. What should you do first?
August 31, 2026
You are managing a bridge construction project with a 36-month timeline and a team of 45 people including engineers, construction workers, and safety officers. The project is performing well against the baseline, with CPI at 1.02 and SPI at 0.98. During month 12, your construction superintendent, who has 20 years of experience and has been instrumental in maintaining quality and safety standards, submits a resignation letter citing a better opportunity. The construction superintendent is not easily replaceable due to specialized knowledge of the bridge design and local regulations. What is your most important immediate action?
August 31, 2026
You are managing a product development project for a new medical device. The project is in the execution phase, and you have a cross-functional team including engineers, regulatory specialists, and quality assurance professionals. During a weekly team meeting, you notice that the regulatory specialists consistently remain silent when technical decisions are being discussed, even though these decisions have significant regulatory implications. When you ask them directly for input, they provide valuable insights. The team is approaching a critical design decision milestone next week. How should you address this situation?
August 31, 2026
