Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
340 questions found · page 5 of 14
Your agile project team has been using two-week sprints successfully for six months. A new regulatory requirement has been introduced that mandates monthly compliance reports with detailed documentation of all work completed. The compliance officer suggests moving to four-week sprints to align with the reporting cycle, arguing it will reduce administrative overhead. The team is concerned this will reduce their ability to adapt quickly to changing market conditions. How should you address this situation?
September 21, 2026
During a sprint, your development team discovers that implementing a user story as currently defined would require significant technical debt due to integration with a legacy system. The story is high priority for the product owner and represents 8 story points of the 40-point sprint commitment. Refactoring to avoid technical debt would increase the effort to 13 story points. The team is currently on day 3 of a 10-day sprint. What should happen next?
September 21, 2026
Your agile team is developing a customer portal and has received feedback from the product owner that the last three increments did not meet customer expectations, despite meeting acceptance criteria. The team followed all documented requirements and the product owner approved each user story before development. Customers are frustrated that features don't solve their actual problems. What should the team do to prevent this in future sprints?
September 21, 2026
You are managing an agile software development project with a distributed team across three time zones. During sprint planning, the team commits to 45 story points, which is significantly higher than their historical average of 32 story points per sprint. When you question this, the team explains they want to impress the new executive sponsor who will attend the sprint review. The product owner supports the ambitious commitment. What is the BEST action to take?
September 21, 2026
Your agile team has completed three sprints on a mobile application project. During the sprint retrospective, several team members mention that the Definition of Done (DoD) has become unclear, as some user stories are being marked complete without proper testing documentation. The product owner suggests loosening the DoD to improve velocity metrics. Team members are divided on this approach. What should you do as the Scrum Master?
September 21, 2026
You are managing a 14-month product development project currently in month 8. The project has a documented communications management plan that specifies monthly status reports to stakeholders. A key stakeholder who rarely attended review meetings or responded to status reports suddenly expresses strong dissatisfaction with the project direction during a chance meeting with your sponsor. The sponsor is now questioning your stakeholder management approach. Upon investigation, you discover this stakeholder's engagement level has dropped from 'supportive' to 'resistant' without your awareness. What should you have done differently?
September 18, 2026
You are managing a software development project using a predictive approach. During a quality audit, the quality assurance team identifies that 15% of the deliverables from the development phase contain defects that meet the defined acceptance criteria but fall short of industry best practices for security standards. The project quality management plan specifies conformance to acceptance criteria as the measure of quality. Fixing these issues would require additional time and budget not currently allocated. What should you do?
September 18, 2026
Your manufacturing project is in the execution phase. A critical supplier informs you that a key component will be delayed by three weeks due to material shortages. This component is on the critical path and was scheduled to be delivered in two weeks. You review your risk register and find that supplier delays were identified as a risk, with a mitigation strategy to identify alternate suppliers. However, no alternate suppliers were pre-qualified. What should you do first?
September 18, 2026
You are managing a construction project with a 12-month timeline and a fixed budget of $2.5 million. During the fourth month, you conduct an earned value analysis and find that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The sponsor asks you to forecast the final project cost assuming current performance continues. What is the most appropriate estimate to provide?
September 18, 2026
Your project team has completed the work breakdown structure (WBS) for a complex infrastructure project. During the activity definition process, a senior team member suggests that some work packages are still too large and should be decomposed further into smaller activities. Another team member argues that further decomposition is unnecessary and will create excessive administrative overhead. The work packages in question represent approximately 120 hours of work each. How should you proceed?
September 18, 2026
A project team is using a hybrid approach where high-level milestones and deliverables were defined upfront, but the team uses two-week sprints to deliver increments. At the end of each sprint, the team holds a review session with stakeholders. A key stakeholder has missed the last three sprint reviews and is now complaining that the project is not meeting their expectations. What should the project manager do?
September 18, 2026
A hybrid project has a fixed budget approved by the steering committee, but features are being delivered iteratively based on business value. After completing 40% of the planned iterations, the project has spent 50% of the budget due to higher than expected infrastructure costs. The remaining features in the backlog are all considered high priority by stakeholders. What should the project manager do next?
September 18, 2026
A project manager is leading a hybrid project where the design phase was completed using a predictive approach, and now the team is moving into iterative development sprints. Several team members who were not involved in the design phase are confused about the project requirements. Velocity has been lower than expected in the first sprint. What should the project manager do?
September 18, 2026
A project team is using a hybrid approach where requirements are gathered upfront but development is executed in two-week sprints. The product owner has just requested a new feature that was not in the original project scope. The team has completed three sprints and has five more planned. What should the project manager do first?
September 18, 2026
A software development project is using a hybrid approach with a defined budget and timeline, but iterative delivery of features. During the third iteration, the team discovers that a core architectural component needs to be redesigned, which will impact the overall project schedule. The project sponsor is concerned about meeting the fixed deadline. What is the best way for the project manager to address this situation?
September 18, 2026
You are managing a construction project with a 24-month timeline and a fixed budget of $8 million. During month 6, you calculate that the Earned Value (EV) is $2.1 million, the Planned Value (PV) is $2.4 million, and the Actual Cost (AC) is $2.3 million. The project sponsor asks you to forecast the final project cost based on current performance trends. What should you report as the Estimate at Completion (EAC) assuming current cost performance continues?
September 18, 2026
You are leading a software development project using a waterfall approach. The design phase has been completed and approved by stakeholders. As the development phase begins, a key stakeholder requests a significant change to the user interface that would require redesigning several approved components. The change would add value but was not included in the original scope. The stakeholder insists this is just a clarification of the original requirements. What is your BEST course of action?
September 18, 2026
You are managing a bridge construction project with a 36-month duration and multiple work packages. The project is in month 12, and you are conducting a quality audit. You discover that concrete testing procedures documented in the quality management plan have not been consistently followed by the construction subcontractor for the past two months. The subcontractor claims the alternative testing methods they used are equivalent and meet industry standards. No structural failures have occurred. What should you do?
September 18, 2026
During the execution phase of a pharmaceutical manufacturing project, you discover that a critical piece of equipment specified in the project scope has been discontinued by the manufacturer. Three alternative equipment options are available, each with different costs, lead times, and technical specifications. One option closely matches the original specifications but costs 30% more and has a 3-month longer lead time. Another option costs the same but has reduced capacity. A third option is cheaper and faster but requires modifications to the facility design. What should you do FIRST?
September 18, 2026
You are managing a manufacturing project to deliver 500 custom components over 10 months. After 4 months, you have delivered 180 components. The project budget is $500,000, and you have spent $195,000 so far. According to the baseline schedule, you should have delivered 200 components by now. Senior management wants to know if the project will meet its deadline. What is the Schedule Performance Index (SPI) and what does it indicate about schedule performance?
September 18, 2026
You are leading a hybrid project to modernize a manufacturing execution system. The data migration component follows a waterfall approach due to regulatory validation requirements, while new features are developed using Kanban. Three months into the project, your organization announces a merger that will require integrating data from the acquired company's systems - significantly expanding the data migration scope. The Kanban team has been delivering features steadily, but these features depend on the data migration being complete. The project budget is fixed, and the regulatory validation timeline cannot be compressed. Senior management wants to know how you will handle this change without delaying time-to-market. What is the BEST approach?
September 18, 2026
You are managing a hybrid product development project where the hardware components follow a predictive approach with a 12-month timeline, while the software team operates in 2-week sprints. The hardware team has just informed you that a critical component will be delayed by 6 weeks due to supply chain issues. This delay will impact the integration phase where both teams must work together. The software team has already completed 60% of their planned features and is on track. Several stakeholders are pressuring you to maintain the original go-live date. What should be your FIRST action to address this situation?
September 16, 2026
You are managing a pharmaceutical product launch project using a hybrid approach. Clinical trials and regulatory submissions follow a stage-gate predictive model due to FDA requirements, while the marketing campaign and digital presence are developed using Scrum. The regulatory team has just learned that the FDA will require an additional study, delaying approval by 9 months. Meanwhile, the Scrum team has completed the e-commerce platform, mobile app, and digital marketing materials scheduled for the original launch date. The program sponsor is concerned about losing competitive advantage and wants options for generating value from the completed digital work. What is the MOST appropriate strategy?
September 16, 2026
Your hybrid construction and technology project involves building a new data center facility (predictive) while simultaneously developing the cloud management platform (agile). The construction phase has clearly defined milestones tied to building permits and inspections. The software team works in 3-week sprints and has been delivering features ahead of schedule. A major stakeholder from the facilities group has started attending sprint reviews and is now requesting detailed Gantt charts for the software deliverables, claiming they need predictability to coordinate facility operations planning. The software team feels this contradicts agile principles and will slow them down with unnecessary documentation. The stakeholder insists they cannot plan operations without concrete dates. What should you do to resolve this conflict?
September 16, 2026
Your organization is implementing a new customer portal using a hybrid approach. The infrastructure and security components are being delivered predictively with detailed requirements and regulatory compliance needs, while the user interface and customer-facing features are developed using Scrum. During the third sprint review, the Product Owner accepts several UI features, but the security team identifies that these features cannot be deployed to production because the underlying security framework (managed predictively) won't be ready for another two months. The development team is frustrated that completed work cannot be released, and the Product Owner is concerned about demonstrating value to stakeholders. How should you address this situation going forward?
September 16, 2026