Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
715 questions found · page 18 of 29
You are facilitating sprint planning for a web development team. The product owner has prioritized 15 user stories for the upcoming sprint, but based on the team's velocity from the past three sprints (averaging 34 story points), this represents 52 story points of work. Several team members express concern about overcommitment. The product owner insists all stories are important and should be included. How should you proceed?
July 20, 2026
Your agile team is working on a healthcare application project. A critical regulatory requirement emerges mid-sprint that must be implemented before the product can be released. The team has already committed to several user stories for the current two-week sprint and is on track to complete them. The new requirement will take approximately one week of effort. What is the best approach to handle this situation?
July 20, 2026
You are the product owner for an e-commerce platform development project. The development team has completed several user stories related to the shopping cart functionality. During the sprint review, you notice that while the features work technically, they don't fully align with the customer experience you envisioned based on recent user feedback. The team is asking you to accept the stories as done. What should you do?
July 20, 2026
Your agile team has just completed their third sprint of a mobile app development project. During the sprint retrospective, team members express frustration that they keep discovering new technical dependencies mid-sprint, causing them to miss their sprint commitments. The team wants to improve their planning process. What should the team do first to address this issue?
July 20, 2026
You are managing a software development project using Scrum. During the daily standup, one team member mentions they are blocked because they are waiting for clarification from the product owner on a user story acceptance criterion. The product owner is not present at the standup meeting. Another team member suggests moving forward with their best interpretation of the requirement. What should you do as the Scrum Master?
July 20, 2026
You are managing a hybrid project with both agile and predictive components. During a project review, a senior stakeholder who prefers traditional project management approaches criticizes the agile team for not having detailed task assignments and individual accountability tracking. The stakeholder requests that you implement individual performance metrics and detailed task assignments for all team members, including those on the agile team. The agile team has been performing well with their current collaborative approach. How should you address this stakeholder's concern?
July 20, 2026
During a hybrid project, your Scrum team has been successfully delivering features every two weeks, but you notice that one team member consistently completes their tasks early and then appears disengaged until the next sprint begins. When you check in with them privately, they mention feeling underutilized and express interest in taking on more challenging work. The rest of the team is working at full capacity. What is the most appropriate action to take?
July 20, 2026
You are leading a hybrid project where software development follows Scrum sprints while infrastructure deployment follows a predictive schedule with fixed milestones. A key developer has requested to work remotely from another time zone for three months due to personal circumstances. This would mean missing most of the daily standups and having limited overlap with the rest of the team. Several team members have expressed concern about communication and collaboration challenges. How should you respond to this situation?
July 20, 2026
Your organization is transitioning to a hybrid project management approach. You have been assigned to lead a project team that includes members with extensive experience in traditional waterfall methods and others who have only worked in agile environments. During the kickoff meeting, you notice tension when discussing how the project will be structured. Some team members are uncomfortable with the lack of detailed upfront planning, while others resist creating comprehensive documentation. What is the best way to build team cohesion in this situation?
July 20, 2026
You are managing a hybrid project where the development team uses Scrum for product features while the compliance team works using a predictive approach for regulatory documentation. During a recent sprint review, several compliance team members expressed frustration that they were not informed about feature changes until after development was complete, causing rework in their documentation. The development team claims they are following their sprint process correctly. What should you do first to address this issue?
July 20, 2026
A project manager is leading a hybrid infrastructure modernization project for a multinational corporation. The network infrastructure replacement follows a predictive waterfall methodology with detailed planning across 15 countries, while cloud services implementation uses an agile approach with two-week sprints. During sprint planning, the development team identifies that they need network upgrades in three locations to proceed with planned cloud deployments, but those network upgrades are scheduled for completion in the waterfall plan three months from now. The development team suggests resequencing the network rollout to unblock their work. What should the project manager do?
July 14, 2026
A pharmaceutical company is executing a hybrid project to launch a new drug. The clinical trials and regulatory approval process follows a strict predictive approach due to FDA requirements, while the marketing strategy and patient education materials are being developed iteratively based on emerging market research. The regulatory team has just informed the project manager that the FDA has changed documentation requirements, which will delay the approval process by two months. The marketing team has already committed to a product launch date with major retailers. How should the project manager address this situation?
July 14, 2026
An IT project manager is leading a hybrid digital transformation initiative for a retail company. The data migration component follows a waterfall approach due to system dependencies, while the new mobile app is being developed iteratively. The marketing department, accustomed to traditional project reporting, is frustrated because they cannot get clear delivery dates for mobile features, while the IT operations team is concerned that agile releases might impact the data migration schedule. The project sponsor has asked the project manager to improve stakeholder confidence. What should the project manager implement?
July 14, 2026
A financial services organization is running a hybrid project to modernize their customer portal. The infrastructure and security components are being managed predictively due to regulatory compliance requirements, while the user interface is being developed using Scrum to enable rapid customer feedback. During a sprint review, customers request features that would require changes to the security architecture, which is governed by a change control board that meets monthly. The next CCB meeting is three weeks away. What is the best approach to maintain project momentum?
July 14, 2026
A manufacturing company is implementing a hybrid project to develop a new product line while simultaneously upgrading their production facilities. The predictive facility upgrade component is 60% complete and on track, but the agile product development team has discovered through customer feedback that the initial product specifications need significant revision. The product owner wants to pivot the product direction, but the facility design was based on the original specifications. Stakeholders are concerned about alignment between both project components. What should the project manager do first?
July 14, 2026
You are leading a pharmaceutical research project to develop a new drug formulation. During risk identification workshops, your team identifies a risk that a key regulatory approval might be delayed by up to 6 months due to recent policy changes. The probability is assessed at 40% and the impact on project completion would be significant. What should you do with this information?
July 13, 2026
You are managing a product development project with a fixed budget of $500,000. At the end of month 3, your earned value analysis shows: Planned Value (PV) = $150,000, Earned Value (EV) = $120,000, and Actual Cost (AC) = $130,000. The project sponsor asks for a status update. What should you report about the project performance?
July 13, 2026
Your team is developing a project schedule for a manufacturing facility upgrade. You have identified all activities, sequenced them, and estimated their durations. Several team members have been assigned to multiple concurrent activities. What should you do next to complete the schedule development process?
July 13, 2026
You are managing a software implementation project using a waterfall approach. The testing phase has just begun, and the QA team reports that 15% of test cases are failing due to missing requirements that were not included in the requirements specification document approved three months ago. The client insists these requirements are essential. What is the best course of action?
July 13, 2026
You are managing a construction project to build a new office building. During the planning phase, you identify that specialized steel beams must be ordered from an overseas supplier with a 12-week lead time. The beams are needed in week 20 of the project schedule. Your team is currently in week 2 of the project. What should you do first?
July 13, 2026
You are managing a critical infrastructure project for a utility company with a 36-month timeline and a highly structured governance framework. Six months into execution, your most senior electrical engineer, who serves as a technical authority and mentors three junior engineers, begins showing signs of stress and reduced engagement. Their deliverable quality remains acceptable, but they are increasingly absent from team meetings, less responsive to questions, and have stopped participating in design reviews. Two junior engineers have privately expressed concern. When you meet with the engineer, they acknowledge feeling overwhelmed but are reluctant to discuss specifics, saying 'it's personal' and they'll work it out. Your next major design milestone requiring their expertise is in five weeks. The project has no schedule buffer. What is the MOST appropriate course of action?
July 13, 2026
You are managing a complex manufacturing facility upgrade project for an automotive supplier. The project has a fixed-price contract with milestone-based payments. Your project team includes 12 full-time employees and 18 contractors from three different vendors. At the 60% complete point, you learn that two contractors from Vendor A have been socializing with your client's procurement director outside of work and have mentioned they could deliver certain components 'more efficiently' if contracted directly by the client, bypassing your organization. Your contracts manager confirms this would violate the exclusivity clause in your vendor agreement. The contractors are performing well technically, and replacing them now would delay the project by 4-6 weeks, risking a $200,000 milestone payment. What should you do?
July 13, 2026
You are managing a defense contract project with 35 team members across four locations. The contract includes specific earned value management (EVM) reporting requirements. At the month 9 performance review, you notice that one remote team of eight developers consistently reports 100% completion of planned tasks on time, yet integration testing repeatedly uncovers significant defects requiring rework. The team lead is well-liked and has been with the company for 15 years. Other teams have expressed frustration about the rework burden. Your SPI is 1.02 but CPI is 0.87, partly due to these rework costs. When you discuss this with the team lead privately, they explain their team is working hard and meeting their commitments as they understand them. What is the MOST effective way to address this performance issue?
July 13, 2026
You are leading a pharmaceutical product development project following a waterfall approach. During the detailed design phase, your quality assurance lead raises concerns that the technical lead is making design decisions without consulting the regulatory compliance specialist, potentially creating future audit risks. When you investigate, you discover the technical lead believes the compliance specialist is being overly cautious and slowing down progress. The technical lead has 20 years of experience and has successfully delivered similar projects. The compliance specialist is newer to the company but has deep regulatory expertise. Your project has strict regulatory submission deadlines with significant financial penalties for delays. How should you address this situation?
July 13, 2026
You are managing a large government infrastructure project with a baseline budget of $45 million and a 24-month timeline. At month 16, a critical team member who holds specialized knowledge about legacy system integration submits their resignation, citing personal reasons. This team member has been instrumental in interfacing with three key stakeholders and possesses undocumented institutional knowledge. The project is currently on schedule but slightly over budget (CPI 0.92). Your sponsor is concerned about the impact on the upcoming integration phase scheduled to begin in three weeks. What should be your FIRST action to address this situation?
July 13, 2026
