Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
120 questions found · page 1 of 5
An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?
November 11, 2026
Your agile team is developing a financial reporting system for a highly regulated industry. During the sprint, a new compliance regulation is announced that affects functionality planned for the next three sprints. The product owner wants to immediately pivot to address the compliance requirement, which would mean abandoning partially completed work from the current sprint. The team is five days into a two-week sprint and has completed about 60% of their committed work. What should the Scrum Master recommend?
November 11, 2026
A software development team is working on a cloud migration project using Scrum. During the sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though it meets all the acceptance criteria defined in the user stories. The product owner approved these acceptance criteria during backlog refinement two weeks ago. Several stakeholders express disappointment and suggest the team wasted the sprint. What is the most appropriate action for the team to take?
November 11, 2026
An agile project team is building a customer portal for an insurance company. During sprint planning, the development team estimates that the highest-priority user story will take 13 story points to complete, but the team's average velocity is only 35 points per two-week sprint and they have already committed to 28 points of other work. The product owner insists this story must be included because a major client has requested this feature for a demo in three weeks. The team is concerned about over-committing. How should the team proceed?
November 11, 2026
Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?
November 11, 2026
Your product has been in production for 18 months using continuous deployment with automated testing. The development team releases small increments to production multiple times per week. Recently, the operations team escalated concerns that production incidents have increased 40% over the past two months, with several customer-impacting outages. The VP of Engineering questions whether the continuous deployment approach is too risky and suggests returning to monthly release cycles with more comprehensive manual testing. Your analysis shows that while incident count increased, 85% of incidents are caught and auto-rolled back within 2 minutes before customers are affected. The remaining 15% that impact customers are primarily due to third-party API changes and infrastructure issues, not code defects. The team's automated test coverage is 87% and their mean time to recovery is 8 minutes. What should you recommend?
November 2, 2026
Your organization is scaling agile across five teams working on a complex financial services platform. Each team has been working independently using Scrum for eight months with their own Product Owner from different business units (Trading, Risk Management, Compliance, Customer Service, and Reporting). The architecture team reports increasing integration problems, with teams making conflicting technical decisions that require expensive rework. Dependencies between teams are causing 20% of stories to be blocked each sprint. The CTO wants better alignment but doesn't want to lose team autonomy or slow down delivery. Teams currently sync through a weekly Scrum of Scrums meeting. What structural change would most effectively address the integration and dependency issues?
November 2, 2026
Your product team has been using two-week sprints with good success. After four months, you notice a troubling pattern in the metrics: sprint burndowns show the team typically completes only 40% of story points in the first week, then rushes to finish the remaining 60% in the second week. Defect rates in the second week are 3x higher than the first week. The team's Definition of Done includes unit testing, code review, and integration testing. During retrospectives, team members mention they often wait for clarification from the Product Owner, who is only available for detailed questions during the sprint review on day 10. Sprint velocity remains consistent at about 50 points per sprint, and stakeholders are satisfied with deliveries. What underlying process issue should you address?
November 2, 2026
During a release planning session, your distributed agile team is estimating features for the next quarter. The team has historical data showing their velocity averages 60 story points per two-week sprint. Marketing has committed to customers that Features A, B, and C (totaling 380 story points) will be delivered in the next six sprints. The Development Team estimates there's a 30% risk that Feature B's technical complexity is underestimated and could require 40% more effort. The Product Owner asks you how to plan the release with confidence. Feature A is worth $500K in revenue, Feature B is worth $300K, and Feature C is worth $150K. What is the most appropriate recommendation?
November 2, 2026
Your agile team has been delivering increments successfully for six sprints, maintaining a stable velocity of 45 story points. In sprint 7, the Product Owner requests adding a critical regulatory compliance feature that requires immediate attention due to an unexpected government mandate. The feature is estimated at 55 story points and cannot be decomposed further without losing its compliance value. The Product Owner wants to add it to the current sprint backlog which already contains 45 story points of committed work. Team members express concern about overcommitment, but the Product Owner insists this is a business-critical emergency. What should the Scrum Master do first?
November 2, 2026
You are managing an agile project where the team has been experimenting with mob programming for the past three sprints to address knowledge silos. The practice has improved code quality and knowledge sharing, but velocity has dropped from 35 to 22 story points per sprint. The Product Owner is frustrated with the reduced output and demands the team return to individual work assignments to meet release commitments. Team members argue they need two more sprints for the investment to pay off, citing research on mob programming learning curves. Technical debt has decreased significantly, and team members report higher satisfaction. Senior management is questioning whether the agile approach is working. What should you do?
October 25, 2026
Your agile team has been working on a mobile application for eight months. During the current sprint review, stakeholders express significant disappointment with the user interface, saying it doesn't meet their expectations despite the team demonstrating completed user stories. The Product Owner is surprised by this feedback and insists the stories were implemented as written. Upon investigation, you discover that while the Product Owner wrote detailed acceptance criteria, they had not shared wireframes or mockups because they wanted to 'let the team be creative.' The team interpreted the stories differently than the Product Owner intended. This is the third sprint where similar misalignment has occurred. What should be done to prevent this recurring issue?
October 25, 2026
Your organization is transitioning from predictive to agile approaches. You're leading a complex product development effort with three agile teams working on interdependent components. After four sprints, you notice that each team is completing their individual sprint goals, but integration issues are causing significant delays. The teams have different sprint cadences (1-week, 2-week, and 3-week sprints) based on their component complexity. Dependencies are managed through a shared backlog, but teams frequently discover blocking issues during integration. The overall product delivery is falling behind schedule. What is the BEST approach to address this systemic integration problem?
October 25, 2026
During a sprint retrospective, your team identifies that their Definition of Done (DoD) is no longer adequate. Several production incidents in the past month were traced to inadequate security testing, which isn't explicitly required in the current DoD. The team wants to add comprehensive security scanning and penetration testing to the DoD. However, this would reduce the team's velocity by approximately 30% and would require security tools that take three weeks to procure and configure. The Product Owner is concerned about the impact on the product roadmap commitments made to stakeholders. How should this situation be handled?
October 25, 2026
Your agile team has been delivering consistently for six sprints with an average velocity of 42 story points. In the current sprint planning, the Product Owner insists on committing to 58 story points because several high-priority features need to be delivered for an upcoming regulatory deadline in three sprints. The team expresses concern about overcommitment, but the Product Owner argues that working extra hours is necessary. Historical data shows the team's maximum velocity was 48 points in one exceptional sprint. What should you do as the Scrum Master?
October 25, 2026
You are facilitating a sprint retrospective for a team that has just completed a challenging sprint where they missed their sprint goal. During the retrospective, two team members begin blaming each other for technical decisions that led to delays. Other team members become defensive, and the conversation is deteriorating into personal criticism rather than focusing on process improvement. The team has worked well together in the past, but the pressure of the missed goal is creating tension. As the facilitator, what should you do?
September 29, 2026
Your Kanban team has been tracking their flow metrics, and you notice the average cycle time has increased from 4 days to 7 days over the past month. The team's WIP limits haven't changed, and the work item types are consistent with previous months. During a team discussion, you discover that items are spending significantly more time in the 'Code Review' column, often waiting 2-3 days before being reviewed. Team members mention they're focused on completing their own work before reviewing others' contributions. What should the team do to address this issue?
September 29, 2026
Your agile team is three sprints into developing a mobile application. During the latest sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though the implemented features match the acceptance criteria in the user stories. The Product Owner explains they wrote the acceptance criteria based on their understanding but didn't include UI specifications. The team is frustrated because they'll need to rework completed features. How should this situation be addressed going forward?
September 29, 2026
During sprint planning, your development team is struggling to break down a large user story estimated at 21 story points. The Product Owner insists this story must be completed in the upcoming two-week sprint because it's critical for an upcoming trade show demonstration. The team expresses concern that they typically complete 25-30 story points per sprint, but this single story would consume most of their capacity and carries significant technical risk. The story cannot be demonstrated partially. What is the best approach?
September 29, 2026
Your Scrum team has completed their third sprint, and the Product Owner notices that the team's velocity has been inconsistent: 21 story points in Sprint 1, 15 in Sprint 2, and 18 in Sprint 3. The Product Owner is concerned about meeting the release deadline and asks you, as the Scrum Master, to commit to a specific velocity for the remaining sprints so stakeholders can plan accordingly. The team is still learning to work together and refining their estimation practices. What should you do?
September 29, 2026
Your agile project team has been using two-week sprints successfully for six months. A new regulatory requirement has been introduced that mandates monthly compliance reports with detailed documentation of all work completed. The compliance officer suggests moving to four-week sprints to align with the reporting cycle, arguing it will reduce administrative overhead. The team is concerned this will reduce their ability to adapt quickly to changing market conditions. How should you address this situation?
September 21, 2026
During a sprint, your development team discovers that implementing a user story as currently defined would require significant technical debt due to integration with a legacy system. The story is high priority for the product owner and represents 8 story points of the 40-point sprint commitment. Refactoring to avoid technical debt would increase the effort to 13 story points. The team is currently on day 3 of a 10-day sprint. What should happen next?
September 21, 2026
Your agile team is developing a customer portal and has received feedback from the product owner that the last three increments did not meet customer expectations, despite meeting acceptance criteria. The team followed all documented requirements and the product owner approved each user story before development. Customers are frustrated that features don't solve their actual problems. What should the team do to prevent this in future sprints?
September 21, 2026
You are managing an agile software development project with a distributed team across three time zones. During sprint planning, the team commits to 45 story points, which is significantly higher than their historical average of 32 story points per sprint. When you question this, the team explains they want to impress the new executive sponsor who will attend the sprint review. The product owner supports the ambitious commitment. What is the BEST action to take?
September 21, 2026
Your agile team has completed three sprints on a mobile application project. During the sprint retrospective, several team members mention that the Definition of Done (DoD) has become unclear, as some user stories are being marked complete without proper testing documentation. The product owner suggests loosening the DoD to improve velocity metrics. Team members are divided on this approach. What should you do as the Scrum Master?
September 21, 2026
