PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

85 questions found · page 2 of 4

26
ProcessHybridMedium

A project team is developing a customer portal using a hybrid approach. The infrastructure and security components are managed using predictive methods with detailed upfront planning, while the user interface features are developed iteratively using Scrum. During sprint planning, the development team realizes that a new security requirement from the infrastructure team will impact three user stories planned for the current sprint. The product owner wants to proceed with the original sprint plan. What should the project manager do first?

August 3, 2026

27
ProcessHybridMedium

An engineering project is using a hybrid delivery approach where hardware development follows a stage-gate process while software features are developed using Kanban. The project is preparing for the gate 3 review which requires demonstrable integration between hardware and software. The software team's Kanban board shows several features in progress, but only 40% of planned integration points have been completed. The hardware team is ready for the gate review and cannot proceed to the next stage without approval. Senior management is pressuring for the gate review to proceed as scheduled. What is the MOST appropriate action?

August 3, 2026

28
ProcessHybridMedium

A project team is implementing a new enterprise system using a hybrid approach. The data migration and infrastructure deployment are managed predictively with a detailed work breakdown structure, while the user training and change management activities are handled adaptively based on user feedback loops. The infrastructure team has completed their deployment two weeks ahead of schedule. The change management team is currently in their second iteration and has three more iterations planned. What should the project manager do to optimize value delivery?

August 3, 2026

29
ProcessHybridMedium

A software development project uses Scrum for application development while regulatory compliance and documentation follow a plan-driven approach with formal reviews and approvals. The compliance team has scheduled their milestone review for the end of the month, which coincides with the team's sprint 8 review. The Scrum team has discovered that two features scheduled for sprint 8 require additional compliance documentation that typically takes three weeks to prepare and approve. The product owner wants to keep both features in the sprint to meet customer commitments. How should the project manager address this situation?

August 3, 2026

30
ProcessHybridMedium

A manufacturing project is using a hybrid approach where the facility construction follows a waterfall methodology while the equipment installation and testing uses iterative cycles. The project is currently 60% complete based on the construction milestones. However, during the third iteration of equipment testing, the team discovers that several pieces of equipment require modifications to the facility layout that was already constructed. This discovery threatens both the budget and timeline. What is the BEST course of action?

August 3, 2026

31
ProcessHybridMedium

You are managing a construction and technology project using a hybrid approach. Physical construction follows a critical path method schedule, while the building automation system development uses Kanban. The construction team has identified that they will complete the electrical rough-in two weeks ahead of schedule, which would allow the automation team to begin installation earlier than planned. However, the automation team's Kanban board shows they are currently focused on software configuration and have not yet started the installation work packages. What should you do?

July 29, 2026

32
ProcessHybridMedium

Your hybrid project includes both traditional procurement activities managed through a stage-gate process and agile development work managed through Scrum. A critical vendor deliverable scheduled for the end of Stage 2 has been delayed by three weeks. The development team has planned the next two sprints based on receiving this deliverable at the originally scheduled time. The vendor cannot accelerate delivery, and the delay will impact six planned user stories. What should you do?

July 29, 2026

33
ProcessHybridMedium

You are leading a product development project using a hybrid approach where regulatory compliance work follows a predictive model and feature development follows an agile model. During a retrospective, the agile team expresses frustration that they completed several features in the last sprint, but these features cannot be released to customers until compliance documentation is approved, which takes four weeks. The team feels their work is not creating value quickly enough. What is the best way to address this concern?

July 29, 2026

34
ProcessHybridMedium

Your organization is implementing a new customer relationship management (CRM) system using a hybrid approach. The data migration and system configuration follow a waterfall methodology, while new feature development uses Scrum. After three sprints, the product owner reports that business stakeholders are confused about when they will see complete functionality because some features depend on data migration milestones that are tracked separately. Stakeholders are requesting a unified view of progress. How should you address this situation?

July 29, 2026

35
ProcessHybridMedium

You are managing a digital transformation project using a hybrid approach. The planning team has completed traditional infrastructure work breakdown structures (WBS) while the software development team operates in two-week sprints. During sprint planning, the development team identifies dependencies on infrastructure components that are scheduled to be delivered in three months according to the WBS. The development team wants to begin user interface work now, but the infrastructure team insists on following the original schedule. What should you do first?

July 29, 2026

36
ProcessHybridMedium

An insurance company is executing a hybrid project to modernize their claims processing system. Infrastructure and security hardening follow a predictive approach with stage gates, while claims processing features are delivered in two-week sprints with regular customer demos. During a retrospective, the development team expresses frustration that they frequently wait for infrastructure approvals that delay their ability to deploy completed features. The infrastructure team explains their governance process requires formal change advisory board reviews that occur monthly. What is the best approach to address this impediment?

July 20, 2026

37
ProcessHybridMedium

A retail company is implementing a hybrid project for a new inventory management system. The data migration follows a predictive schedule with specific cutover dates, while new features are developed using Kanban with continuous flow. A critical quality issue is discovered in the data migration test environment that could delay the cutover by six weeks. The development team using Kanban has been consistently delivering new features every week. Several stakeholders suggest accelerating feature delivery to compensate for the data migration delay. What should the project manager do?

July 20, 2026

38
ProcessHybridMedium

A healthcare organization is delivering a patient management system using a hybrid approach. Regulatory compliance components follow a waterfall methodology, while clinical workflow features are developed iteratively based on user feedback. During a quarterly steering committee meeting, executives request a comprehensive status report showing progress across both work streams. The adaptive team measures velocity and completed story points, while the predictive team tracks earned value and milestone completion. How should the project manager present this information?

July 20, 2026

39
ProcessHybridMedium

A manufacturing company is executing a hybrid project to implement a new production line. The engineering design follows a predictive approach with defined milestones, while the software automation team uses Scrum with three-week sprints. The engineering team has just completed their design phase two weeks ahead of schedule. The automation team's product owner wants to immediately begin working on advanced features that depend on the completed design, even though their current sprint has two weeks remaining and focuses on basic functionality. What should the project manager recommend?

July 20, 2026

40
ProcessHybridMedium

A financial services company is implementing a new customer portal using a hybrid approach. The predictive portion involves infrastructure setup and regulatory compliance documentation, while the adaptive portion covers user interface development with two-week iterations. During sprint planning, the infrastructure team reports they need three additional weeks to complete security certifications before the development team can begin integration testing. The project manager is concerned about the impact on the overall timeline. What should the project manager do first?

July 20, 2026

41
ProcessPredictiveMedium

You are managing a manufacturing project to develop a new production line. During a risk review meeting, the engineering team identifies a potential risk: a key piece of automated equipment might not integrate properly with existing systems, which could delay commissioning by four weeks. The probability is assessed at 40% and the impact would be $150,000 in additional costs. After discussing response strategies, the team proposes purchasing a backup manual system for $45,000 that could be used if the integration fails. What risk response strategy does this represent?

July 13, 2026

42
ProcessPredictiveMedium

You are managing an infrastructure project with a fixed budget of $2.5 million. At the end of month 4, your earned value analysis shows: PV = $800,000, EV = $750,000, AC = $825,000. The project is planned for 12 months total. Based on this information, senior management asks you to forecast the final project cost. What is the most appropriate estimate at completion (EAC) to present if you expect current performance to continue?

July 13, 2026

43
ProcessPredictiveMedium

You are managing a pharmaceutical research project with strict regulatory requirements. During quality inspections, you discover that 15% of the test samples from the last production batch do not meet the acceptance criteria defined in the quality management plan. The lab supervisor suggests reworking the samples, while the quality manager recommends disposing of the batch and starting over. The rework would save two weeks but carries some risk. What should you do?

July 13, 2026

44
ProcessPredictiveMedium

You are managing a software development project using a waterfall approach. During the design phase, your technical lead discovers that a third-party component you planned to integrate has been discontinued by the vendor. This component was included in the approved project scope and budget. The technical lead suggests two alternatives: building the component in-house or using a different vendor's solution with similar functionality but different technical specifications. What is the best course of action?

July 13, 2026

45
ProcessPredictiveMedium

You are managing a construction project to build a new office building. During the execution phase, a key supplier notifies you that the specialized steel components will be delayed by three weeks due to manufacturing issues. The critical path includes the steel frame installation, and this delay will impact the project completion date. Your project sponsor is very concerned about meeting the contractual deadline. What should you do first?

July 13, 2026

46
ProcessPredictiveMedium

You are managing a product development project using a stage-gate approach. The project is approaching the gate review for Phase 2 completion. During quality inspections, you discover that three of the fifteen deliverables have minor defects that do not prevent functionality but fall slightly below the quality standards documented in the quality management plan. Correcting these defects would take two weeks and consume the remaining schedule buffer. The gate review is scheduled for next week, and senior management is eager to proceed to Phase 3. What should you do?

July 10, 2026

47
ProcessPredictiveMedium

You are managing an infrastructure project with a detailed WBS and network diagram. A key stakeholder requests the addition of a new feature that was not included in the original scope baseline. The change would provide significant value to end users and has strong executive support. After analysis, you determine the change would add three weeks to the schedule and increase costs by 8%. The change control board (CCB) has approved the change request. What should you do next?

July 10, 2026

48
ProcessPredictiveMedium

Your manufacturing project has a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.10. The project is 60% complete with six months remaining until the planned completion date. During the monthly steering committee meeting, the CFO expresses concern about the budget overrun and asks whether the project can be completed within the approved budget. What should you present to the steering committee?

July 10, 2026

49
ProcessPredictiveMedium

You are leading a software development project using a waterfall methodology. During the testing phase, the QA team discovers that 15% of the delivered functionality does not meet the acceptance criteria defined in the requirements document. The development team claims the requirements were ambiguous and their interpretation was reasonable. The testing phase is scheduled to end in one week, and any rework will delay the go-live date. What is the most appropriate action?

July 10, 2026

50
ProcessPredictiveMedium

You are managing a construction project using a predictive approach. During the execution phase, a supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and push the project completion date beyond the contractual deadline. You have already exhausted schedule reserves on previous delays. The project sponsor is highly concerned about contractual penalties. What should you do first?

July 10, 2026