Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
340 questions found · page 3 of 14
You are managing an agile project where the team has been experimenting with mob programming for the past three sprints to address knowledge silos. The practice has improved code quality and knowledge sharing, but velocity has dropped from 35 to 22 story points per sprint. The Product Owner is frustrated with the reduced output and demands the team return to individual work assignments to meet release commitments. Team members argue they need two more sprints for the investment to pay off, citing research on mob programming learning curves. Technical debt has decreased significantly, and team members report higher satisfaction. Senior management is questioning whether the agile approach is working. What should you do?
October 25, 2026
Your agile team has been working on a mobile application for eight months. During the current sprint review, stakeholders express significant disappointment with the user interface, saying it doesn't meet their expectations despite the team demonstrating completed user stories. The Product Owner is surprised by this feedback and insists the stories were implemented as written. Upon investigation, you discover that while the Product Owner wrote detailed acceptance criteria, they had not shared wireframes or mockups because they wanted to 'let the team be creative.' The team interpreted the stories differently than the Product Owner intended. This is the third sprint where similar misalignment has occurred. What should be done to prevent this recurring issue?
October 25, 2026
Your organization is transitioning from predictive to agile approaches. You're leading a complex product development effort with three agile teams working on interdependent components. After four sprints, you notice that each team is completing their individual sprint goals, but integration issues are causing significant delays. The teams have different sprint cadences (1-week, 2-week, and 3-week sprints) based on their component complexity. Dependencies are managed through a shared backlog, but teams frequently discover blocking issues during integration. The overall product delivery is falling behind schedule. What is the BEST approach to address this systemic integration problem?
October 25, 2026
During a sprint retrospective, your team identifies that their Definition of Done (DoD) is no longer adequate. Several production incidents in the past month were traced to inadequate security testing, which isn't explicitly required in the current DoD. The team wants to add comprehensive security scanning and penetration testing to the DoD. However, this would reduce the team's velocity by approximately 30% and would require security tools that take three weeks to procure and configure. The Product Owner is concerned about the impact on the product roadmap commitments made to stakeholders. How should this situation be handled?
October 25, 2026
Your agile team has been delivering consistently for six sprints with an average velocity of 42 story points. In the current sprint planning, the Product Owner insists on committing to 58 story points because several high-priority features need to be delivered for an upcoming regulatory deadline in three sprints. The team expresses concern about overcommitment, but the Product Owner argues that working extra hours is necessary. Historical data shows the team's maximum velocity was 48 points in one exceptional sprint. What should you do as the Scrum Master?
October 25, 2026
You are managing a product development project that is currently in the testing phase. During a quality audit, the quality assurance team identifies that three deliverables do not meet the quality standards defined in the quality management plan, though they meet the customer's acceptance criteria as stated in the scope statement. The rework required to meet the quality standards would cost an additional $35,000 and delay the project by two weeks. The customer has not complained and seems satisfied with the current deliverables. What should you do?
October 12, 2026
Your project team has completed the WBS decomposition for a 14-month infrastructure project. During the Define Activities process, a senior team member suggests that some work packages are still too large and should be broken down further into activities. Another team member argues that the current work packages are appropriate and further decomposition would create unnecessary detail. The work packages in question represent 3-4 weeks of work each. As the project manager, how should you handle this situation?
October 12, 2026
You are managing a software implementation project for a government agency using a waterfall approach. The requirements documentation has been approved and baselined. During the design phase, the compliance officer identifies a new regulatory requirement that was published last month and will be effective in three months. Implementing this requirement would require changes to 15% of the approved requirements and add approximately $75,000 to the $500,000 budget. The project is currently on schedule and within budget. What should you do FIRST?
October 12, 2026
During the execution phase of a manufacturing facility upgrade project, a key supplier informs you that a critical component will be delayed by three weeks due to supply chain disruptions. This component is on the critical path and is needed for installation activities scheduled to begin in four weeks. You have a contingency reserve allocated in the budget, and the schedule baseline includes buffer time but not specifically for this activity. The delay will impact subsequent critical path activities. What is the BEST course of action?
October 12, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 12-month timeline. After six months, the project has completed 40% of the planned work and spent $1.3 million. The project sponsor is concerned about cost performance and asks you to provide an analysis. Based on earned value metrics, you calculate that CPI is 0.77 and SPI is 0.80. The sponsor wants to know if the project can be completed within the original budget if current performance continues. What should you recommend?
October 12, 2026
You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?
October 9, 2026
You are managing a defense contractor project using a firm-fixed-price contract worth $28M. During planning, you identified 47 risks and developed response plans with allocated contingency reserves totaling $2.1M. At the 60% completion point, you have consumed $1.85M of contingency reserves, primarily due to three risks that materialized with greater impact than anticipated. You identify a new high-probability, high-impact risk related to a critical supplier's financial instability that could halt production of a custom component with no alternative sources. The risk response would require $450K for a mitigation strategy (qualifying a second supplier). Your remaining contingency reserve is $250K, and management reserves are $800K controlled by the sponsor. What should you do?
October 9, 2026
Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?
October 9, 2026
You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. The design phase deliverables were approved three months ago, and construction is 40% complete. A new regulatory requirement has been published that mandates additional safety features in the HVAC system, requiring significant design changes. The change will cost $2.8M (8% of the total budget) and add 6 weeks to the critical path. The regulatory compliance officer insists this is a mandatory change and not subject to change control. Your project charter states that regulatory compliance changes require automatic approval. What should you do FIRST?
October 9, 2026
You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?
October 9, 2026
You are managing a pharmaceutical research project following a stage-gate process. Your project has just completed the Phase 2 clinical trials deliverable. According to the project management plan, a phase gate review is scheduled before proceeding to Phase 3 trials, which will require significant investment. During your preparation for the gate review, you discover that while the trials met their primary endpoint, two secondary endpoints showed concerning trends. The data is not conclusive but suggests potential issues. The project is currently on schedule and under budget. What should you do?
October 7, 2026
Your project team has completed the project scope statement and is now developing the work breakdown structure (WBS). One of your team members suggests creating work packages at different levels of decomposition across the WBS—some at a very detailed level that can be completed in days, and others at a higher level representing several weeks of work. The team member argues this will save time in the planning process. What is the best approach?
October 7, 2026
You are managing a software development project using a waterfall methodology. During the design phase, your technical lead identifies that implementing a requested feature will require a third-party library that introduces significant security vulnerabilities. The feature was explicitly defined in the approved scope baseline and is important to the customer. After analysis, your team proposes an alternative technical approach that provides similar functionality without the security risk but will add $15,000 to the project cost. What should you do?
October 7, 2026
Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?
October 7, 2026
You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?
October 7, 2026
You're managing a hybrid project to modernize a legacy system. Phase 1 (months 1-4) uses predictive approach for infrastructure and data architecture, while Phase 2 (months 5-10) uses Scrum for application development. You're now in month 3, and the infrastructure team has encountered unexpected complexity that will delay their completion by 6 weeks, pushing into month 5.5. The development team's sprint 0 is scheduled for month 5, and team members are already assigned. Waiting would idle 8 developers for 6 weeks at $180K cost. The development team suggests they could begin working on independent modules using simulated infrastructure. What factors should most heavily influence your decision?
October 6, 2026
Your hybrid project combines predictive hardware development with agile firmware iterations. The hardware team has completed their design phase and moved into manufacturing (month 8 of 14), while the firmware team is in sprint 12 of 20. During sprint 12, the firmware team discovers that achieving optimal performance requires a minor hardware modification that would cost $45K and delay manufacturing by 3 weeks. Without this change, the product will meet minimum specifications but perform 25% slower than competitors. The product owner wants to make the change, but the hardware lead argues the decision should follow the formal change control process with steering committee approval, which meets monthly. What should you do?
October 6, 2026
You're leading a digital transformation project using a hybrid approach where compliance and regulatory work follows predictive planning, while customer-facing features are developed iteratively. During the fifth sprint review, the product owner and development team demonstrate working features, but the compliance officer identifies that three completed user stories don't meet regulatory requirements that were documented in the initial project charter. The team claims they followed the acceptance criteria in the user stories. The compliance deliverables are managed separately and weren't scheduled for integration testing until next month. What is the root cause you should address?
October 6, 2026
Your organization is implementing a new ERP system using a hybrid approach: data migration and infrastructure use waterfall phases, while business process configuration uses iterative cycles. After the second iteration, stakeholders from finance request significant changes to the chart of accounts structure, which impacts both the completed data migration design and upcoming infrastructure specifications. The change would add substantial business value but requires rework across both predictive and adaptive streams. The project is at 40% completion with moderate schedule pressure. How should you proceed?
October 6, 2026
You are managing a hybrid project where the infrastructure team works in predictive mode with a 6-month timeline, while the application development team uses 2-week Scrum sprints. During sprint planning, the development team commits to features that depend on infrastructure components scheduled for delivery in month 5. The infrastructure team is currently on track but has no buffer. The development team argues they need these features in sprint 8 (month 4) to meet a critical market window. What should you do first?
October 6, 2026
