Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
105 questions found · page 1 of 5
You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?
November 11, 2026
During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?
November 11, 2026
You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?
November 11, 2026
Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?
November 11, 2026
You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?
November 11, 2026
You have just been assigned as the project manager for a bridge construction project that will take 18 months. The project charter has been signed by the sponsor, and you are beginning the planning phase. You need to identify all individuals, groups, and organizations that could impact or be impacted by the project. What process are you performing?
November 2, 2026
Your manufacturing project has been running for three months. During a quality inspection, you discover that 15% of the produced components do not meet the specifications defined in the quality management plan. Production is continuing, but you are concerned about the trend. What should be your immediate course of action?
November 2, 2026
You are managing a software implementation project for a healthcare client. During a requirements gathering session, the client's Chief Medical Officer requests a new feature that was not included in the original project scope statement or WBS. The feature would add significant value but also increase costs and timeline. What should you do first?
November 2, 2026
Your project to develop a new financial reporting system has a budget of $500,000 and is scheduled to take 10 months. You are currently at the end of month 4. According to your tracking, you have spent $220,000 and completed work that was budgeted at $180,000. What is the cost performance of your project at this point?
November 2, 2026
You are managing a construction project to build a new office building. During the planning phase, your team has identified all project activities and estimated their durations. You now need to determine when each activity should start and finish, considering their dependencies and resource constraints. What tool or technique should you use to create a visual timeline showing the project schedule?
November 2, 2026
You are managing a product development project with multiple external vendors. One vendor has submitted an invoice for $85,000 for completed work. Your procurement specialist reviews the invoice against the contract and identifies that the deliverables match the contract requirements, but notices the vendor applied a 5% price increase that was not in the original fixed-price contract. The vendor claims the increase was discussed verbally with a team member due to scope changes. Your team member confirms a conversation occurred but no formal change was processed. What should you do?
October 25, 2026
Your project team is developing a detailed project schedule for a 16-month infrastructure project. During schedule network analysis, you identify that the critical path has 18 months of duration, exceeding the required completion date by 2 months. You have identified a sequence of activities on the critical path where design and procurement activities could be overlapped to save time. However, overlapping these activities will increase project risk and may require additional design resources. What technique are you considering, and what is the most important factor to evaluate before implementing it?
October 25, 2026
You are managing a manufacturing facility expansion project. During a quality audit, the auditor identifies that three deliverables were completed without the required inspections documented in the quality management plan, though the deliverables appear to meet specifications. The project is currently on schedule and within budget. The construction manager argues that the inspections are bureaucratic and the work quality is evident. What should you do first?
October 25, 2026
During the planning phase of a software development project, your team has identified 47 risks. You've completed qualitative risk analysis and are now preparing for quantitative risk analysis. The project sponsor questions why you need to spend additional time and budget on quantitative analysis when risks have already been prioritized. The project has a firm deadline for regulatory compliance and a contingency reserve of 10% has been allocated. What is the strongest justification for conducting quantitative risk analysis?
October 25, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. After 6 months, the project has spent $1.1 million and completed work valued at $900,000 according to the baseline. The planned value at this point was $1 million. Senior management is concerned about project performance and asks for your assessment. What is the most critical performance issue you should address first?
October 25, 2026
You are managing a product development project that is currently in the testing phase. During a quality audit, the quality assurance team identifies that three deliverables do not meet the quality standards defined in the quality management plan, though they meet the customer's acceptance criteria as stated in the scope statement. The rework required to meet the quality standards would cost an additional $35,000 and delay the project by two weeks. The customer has not complained and seems satisfied with the current deliverables. What should you do?
October 12, 2026
Your project team has completed the WBS decomposition for a 14-month infrastructure project. During the Define Activities process, a senior team member suggests that some work packages are still too large and should be broken down further into activities. Another team member argues that the current work packages are appropriate and further decomposition would create unnecessary detail. The work packages in question represent 3-4 weeks of work each. As the project manager, how should you handle this situation?
October 12, 2026
You are managing a software implementation project for a government agency using a waterfall approach. The requirements documentation has been approved and baselined. During the design phase, the compliance officer identifies a new regulatory requirement that was published last month and will be effective in three months. Implementing this requirement would require changes to 15% of the approved requirements and add approximately $75,000 to the $500,000 budget. The project is currently on schedule and within budget. What should you do FIRST?
October 12, 2026
During the execution phase of a manufacturing facility upgrade project, a key supplier informs you that a critical component will be delayed by three weeks due to supply chain disruptions. This component is on the critical path and is needed for installation activities scheduled to begin in four weeks. You have a contingency reserve allocated in the budget, and the schedule baseline includes buffer time but not specifically for this activity. The delay will impact subsequent critical path activities. What is the BEST course of action?
October 12, 2026
You are managing a construction project with a fixed budget of $2.5 million and a 12-month timeline. After six months, the project has completed 40% of the planned work and spent $1.3 million. The project sponsor is concerned about cost performance and asks you to provide an analysis. Based on earned value metrics, you calculate that CPI is 0.77 and SPI is 0.80. The sponsor wants to know if the project can be completed within the original budget if current performance continues. What should you recommend?
October 12, 2026
You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?
October 9, 2026
You are managing a defense contractor project using a firm-fixed-price contract worth $28M. During planning, you identified 47 risks and developed response plans with allocated contingency reserves totaling $2.1M. At the 60% completion point, you have consumed $1.85M of contingency reserves, primarily due to three risks that materialized with greater impact than anticipated. You identify a new high-probability, high-impact risk related to a critical supplier's financial instability that could halt production of a custom component with no alternative sources. The risk response would require $450K for a mitigation strategy (qualifying a second supplier). Your remaining contingency reserve is $250K, and management reserves are $800K controlled by the sponsor. What should you do?
October 9, 2026
Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?
October 9, 2026
You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. The design phase deliverables were approved three months ago, and construction is 40% complete. A new regulatory requirement has been published that mandates additional safety features in the HVAC system, requiring significant design changes. The change will cost $2.8M (8% of the total budget) and add 6 weeks to the critical path. The regulatory compliance officer insists this is a mandatory change and not subject to change control. Your project charter states that regulatory compliance changes require automatic approval. What should you do FIRST?
October 9, 2026
You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?
October 9, 2026
