PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

85 questions found · page 1 of 4

1
ProcessPredictiveHard

You are managing a complex systems integration project with 12 external vendors and 45 internal team members. The network diagram shows 8 paths through the project, with the critical path having 14 months duration and 4 months total float across all activities. During month 6, you perform schedule compression analysis because a key stakeholder requests moving the completion date forward by 3 months. Your analysis shows: fast-tracking would create 18 new dependency relationships and increase risk significantly; crashing the critical path would cost $2.4M for a 2-month reduction; adding resources to near-critical Path B (currently 11 months with 3 months float) could reduce it to 8 months for $800K. The stakeholder has approved a budget increase of up to $1.5M for acceleration. What is the MOST effective approach?

October 9, 2026

→
2
ProcessPredictiveHard

You are managing a defense contractor project using a firm-fixed-price contract worth $28M. During planning, you identified 47 risks and developed response plans with allocated contingency reserves totaling $2.1M. At the 60% completion point, you have consumed $1.85M of contingency reserves, primarily due to three risks that materialized with greater impact than anticipated. You identify a new high-probability, high-impact risk related to a critical supplier's financial instability that could halt production of a custom component with no alternative sources. The risk response would require $450K for a mitigation strategy (qualifying a second supplier). Your remaining contingency reserve is $250K, and management reserves are $800K controlled by the sponsor. What should you do?

October 9, 2026

→
3
ProcessPredictiveHard

Your construction project has a 16-month duration with four major phase gates requiring customer sign-off. You are currently in month 11, approaching the third phase gate. Quality inspections reveal that 23% of the concrete structural work completed in the previous phase has microfractures that don't meet specifications, likely due to temperature control issues during curing. The work passed initial inspections but was caught during detailed pre-gate review. Remediation will cost $1.2M and delay the phase gate by 8 weeks. The customer relationship is already strained from previous minor delays. The quality manager suggests accepting the work since the microfractures are within building code minimums, though not project specifications. What is the BEST course of action?

October 9, 2026

→
4
ProcessPredictiveHard

You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. The design phase deliverables were approved three months ago, and construction is 40% complete. A new regulatory requirement has been published that mandates additional safety features in the HVAC system, requiring significant design changes. The change will cost $2.8M (8% of the total budget) and add 6 weeks to the critical path. The regulatory compliance officer insists this is a mandatory change and not subject to change control. Your project charter states that regulatory compliance changes require automatic approval. What should you do FIRST?

October 9, 2026

→
5
ProcessPredictiveHard

You are managing a large-scale infrastructure project with a 24-month timeline and a budget of $45 million. During the eighth month, earned value analysis shows: PV = $15M, EV = $12M, AC = $13.5M. Your sponsor is concerned about the schedule variance and asks whether the project can still finish on time within the original budget. You calculate TCPI based on BAC and determine it is 1.18. The project team's historical performance shows they typically achieve a CPI between 0.85 and 0.95 on similar projects. What is the MOST appropriate recommendation?

October 9, 2026

→
6
ProcessPredictiveMedium

You are managing a pharmaceutical research project following a stage-gate process. Your project has just completed the Phase 2 clinical trials deliverable. According to the project management plan, a phase gate review is scheduled before proceeding to Phase 3 trials, which will require significant investment. During your preparation for the gate review, you discover that while the trials met their primary endpoint, two secondary endpoints showed concerning trends. The data is not conclusive but suggests potential issues. The project is currently on schedule and under budget. What should you do?

October 7, 2026

→
7
ProcessPredictiveMedium

Your project team has completed the project scope statement and is now developing the work breakdown structure (WBS). One of your team members suggests creating work packages at different levels of decomposition across the WBS—some at a very detailed level that can be completed in days, and others at a higher level representing several weeks of work. The team member argues this will save time in the planning process. What is the best approach?

October 7, 2026

→
8
ProcessPredictiveMedium

You are managing a software development project using a waterfall methodology. During the design phase, your technical lead identifies that implementing a requested feature will require a third-party library that introduces significant security vulnerabilities. The feature was explicitly defined in the approved scope baseline and is important to the customer. After analysis, your team proposes an alternative technical approach that provides similar functionality without the security risk but will add $15,000 to the project cost. What should you do?

October 7, 2026

→
9
ProcessPredictiveMedium

Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?

October 7, 2026

→
10
ProcessPredictiveMedium

You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?

October 7, 2026

→
11
ProcessPredictiveMedium

You are managing a pharmaceutical research project following a stage-gate predictive methodology. Your project has just completed the design phase, and you are preparing for the gate review before entering the development phase. During preparation, you discover that one of the key assumptions documented in the project charter—that a specific research facility would be available—is no longer valid due to facility renovations. The next available equivalent facility is in a different location and would increase project costs by 8%. What should you do BEFORE the gate review?

September 29, 2026

→
12
ProcessPredictiveMedium

You are managing a large infrastructure project with multiple subcontractors. One of your key vendors has completed their deliverable, and you are conducting procurement closure activities. While reviewing the final deliverable, you notice it meets all technical specifications in the contract, but the vendor failed to submit three required progress reports during execution as stipulated in the contract terms. The vendor is requesting final payment and contract closure. What is the MOST appropriate action?

September 29, 2026

→
13
ProcessPredictiveMedium

You are managing a software implementation project for a financial institution using a waterfall approach. During quality testing, the QA team discovers that 12% of test cases are failing, primarily related to security authentication features. The quality management plan specified that no more than 5% of test cases should fail at this stage. The development team believes they can fix the issues within one week, but this will delay the scheduled user acceptance testing. What should you do?

September 29, 2026

→
14
ProcessPredictiveMedium

Your manufacturing project is in the planning phase, and you are developing the cost baseline. You have completed bottom-up estimating for all work packages and have aggregated these costs. The finance department requires a 10% management reserve for organizational risks, and historical data shows similar projects typically experience 15% cost variance. Your project sponsor asks what the final project budget should include. What is the MOST appropriate approach?

September 29, 2026

→
15
ProcessPredictiveMedium

You are managing a construction project using a predictive approach. During the execution phase, a key supplier informs you that critical materials will be delayed by three weeks due to manufacturing issues. The delay will impact the critical path and push the project completion date beyond the contractually agreed deadline. Several team members suggest crashing the schedule by adding overtime resources, while the sponsor wants to explore fast-tracking options. What should you do FIRST?

September 29, 2026

→
16
ProcessPredictiveEasy

You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?

September 24, 2026

→
17
ProcessPredictiveEasy

Your manufacturing project has a budget of $500,000 and is scheduled to last 10 months. You are currently at the end of month 4. According to the project management plan, you should have spent $200,000 by now, but you have actually spent $180,000. The value of the work completed is $190,000. What is the Cost Variance (CV) for this project?

September 24, 2026

→
18
ProcessPredictiveEasy

You are managing a government infrastructure project with strict documentation requirements. During a planning meeting, a stakeholder questions why you need to document lessons learned throughout the project rather than just at the end. The stakeholder is concerned about the additional administrative burden. What is the primary benefit of documenting lessons learned throughout the project lifecycle?

September 24, 2026

→
19
ProcessPredictiveEasy

You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?

September 24, 2026

→
20
ProcessPredictiveEasy

You are managing a construction project to build a new office facility. During project planning, you identify that concrete foundation work cannot begin until the excavation is complete and inspected. The concrete must cure for 7 days before framing can start. You need to document these relationships in your project schedule. What type of dependency exists between excavation and foundation work?

September 24, 2026

→
21
ProcessPredictiveMedium

You are managing a 14-month product development project currently in month 8. The project has a documented communications management plan that specifies monthly status reports to stakeholders. A key stakeholder who rarely attended review meetings or responded to status reports suddenly expresses strong dissatisfaction with the project direction during a chance meeting with your sponsor. The sponsor is now questioning your stakeholder management approach. Upon investigation, you discover this stakeholder's engagement level has dropped from 'supportive' to 'resistant' without your awareness. What should you have done differently?

September 18, 2026

→
22
ProcessPredictiveMedium

You are managing a software development project using a predictive approach. During a quality audit, the quality assurance team identifies that 15% of the deliverables from the development phase contain defects that meet the defined acceptance criteria but fall short of industry best practices for security standards. The project quality management plan specifies conformance to acceptance criteria as the measure of quality. Fixing these issues would require additional time and budget not currently allocated. What should you do?

September 18, 2026

→
23
ProcessPredictiveMedium

Your manufacturing project is in the execution phase. A critical supplier informs you that a key component will be delayed by three weeks due to material shortages. This component is on the critical path and was scheduled to be delivered in two weeks. You review your risk register and find that supplier delays were identified as a risk, with a mitigation strategy to identify alternate suppliers. However, no alternate suppliers were pre-qualified. What should you do first?

September 18, 2026

→
24
ProcessPredictiveMedium

You are managing a construction project with a 12-month timeline and a fixed budget of $2.5 million. During the fourth month, you conduct an earned value analysis and find that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The sponsor asks you to forecast the final project cost assuming current performance continues. What is the most appropriate estimate to provide?

September 18, 2026

→
25
ProcessPredictiveMedium

Your project team has completed the work breakdown structure (WBS) for a complex infrastructure project. During the activity definition process, a senior team member suggests that some work packages are still too large and should be decomposed further into smaller activities. Another team member argues that further decomposition is unnecessary and will create excessive administrative overhead. The work packages in question represent approximately 120 hours of work each. How should you proceed?

September 18, 2026

→