PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

715 questions found · page 9 of 29

201
PeoplePredictiveMedium

You are managing a predictive pharmaceutical project with strict regulatory deliverables. A team member consistently produces high-quality work but submits deliverables 2-3 days after agreed-upon deadlines, causing delays in the dependent review processes. When you discussed this previously, the team member explained they need extra time to ensure quality and compliance. Other team members are becoming frustrated with the repeated delays. How should you address this situation?

August 31, 2026

→
202
PeoplePredictiveMedium

You are three months into a 12-month predictive project when your most experienced business analyst announces she will be leaving the company in four weeks. She is the only team member who fully understands the complex regulatory requirements that drive 40% of project deliverables. The project baseline schedule shows her involvement is critical for the next six months. What is your best course of action?

August 31, 2026

→
203
PeoplePredictiveMedium

You are managing a predictive software implementation project with a team of 15 members. During a weekly status meeting, two senior developers publicly disagree about the technical approach for a critical module, and the discussion becomes heated. Other team members are visibly uncomfortable, and the meeting agenda is derailed. You need to restore team collaboration while ensuring the technical issue gets resolved. What should you do first?

August 31, 2026

→
204
PeoplePredictiveMedium

You are managing a predictive infrastructure project with a detailed resource management plan. Your functional manager informs you that one of your key team members will need to support a critical production issue for the next two weeks, reducing their availability to your project from 100% to 25%. This team member is scheduled to complete design activities that are on the critical path. What is the most appropriate action?

August 31, 2026

→
205
PeoplePredictiveMedium

Your predictive construction project team includes contractors from three different companies. You notice that team members primarily communicate within their own company groups and rarely collaborate across organizational boundaries. This siloed behavior is causing information gaps and coordination delays. Performance reports show the project is currently on schedule, but you're concerned about upcoming integration activities. What should you do?

August 31, 2026

→
206
PeoplePredictiveMedium

You are managing a manufacturing facility construction project with a detailed WBS and baseline schedule. During month 4 of the 18-month project, you receive the performance reviews for your project team members from their functional managers. You notice that one of your key electrical engineers received a below-average rating, citing lack of contribution to departmental initiatives. However, this engineer has been fully dedicated to your project, meeting all assigned deadlines and producing high-quality work. The functional manager suggests reducing this person's allocation to your project. What should you do?

August 31, 2026

→
207
PeoplePredictiveMedium

You are leading a government software development project using a waterfall approach. Three months into the project, you notice that two senior developers who were highly collaborative during planning have become increasingly adversarial, disagreeing on technical approaches during design reviews and making critical comments about each other's work. Their conflict is starting to affect team morale, and other team members are beginning to take sides. The design phase is scheduled to complete in two weeks. What is your best course of action?

August 31, 2026

→
208
PeoplePredictiveMedium

You are managing a complex infrastructure project with a 24-month timeline. During the planning phase, you identify that your team will need specialized database architects for months 8-12, but your functional manager can only commit these resources for months 10-14 due to competing organizational priorities. The project schedule shows critical database design activities starting in month 8, and any delay would impact the critical path. What should you do first?

August 31, 2026

→
209
PeoplePredictiveMedium

You are managing a bridge construction project with a 36-month timeline and a team of 45 people including engineers, construction workers, and safety officers. The project is performing well against the baseline, with CPI at 1.02 and SPI at 0.98. During month 12, your construction superintendent, who has 20 years of experience and has been instrumental in maintaining quality and safety standards, submits a resignation letter citing a better opportunity. The construction superintendent is not easily replaceable due to specialized knowledge of the bridge design and local regulations. What is your most important immediate action?

August 31, 2026

→
210
PeoplePredictiveMedium

You are managing a product development project for a new medical device. The project is in the execution phase, and you have a cross-functional team including engineers, regulatory specialists, and quality assurance professionals. During a weekly team meeting, you notice that the regulatory specialists consistently remain silent when technical decisions are being discussed, even though these decisions have significant regulatory implications. When you ask them directly for input, they provide valuable insights. The team is approaching a critical design decision milestone next week. How should you address this situation?

August 31, 2026

→
211
PeoplePredictiveMedium

You are managing a manufacturing project with a geographically distributed team across three countries and multiple time zones. The project follows a traditional waterfall methodology with detailed planning completed upfront. Team members have raised concerns about feeling disconnected and unclear about how their work contributes to overall project objectives. Team performance metrics show declining productivity and increasing miscommunication. What should you do to address this situation?

August 28, 2026

→
212
PeoplePredictiveMedium

You are managing a software development project using a stage-gate approach with formal phase reviews. During the design phase, you learn that three key team members will be pulled to support an emergency customer issue for approximately two weeks, starting next week. The design deliverables are due to the steering committee in three weeks for gate approval. What is the best course of action?

August 28, 2026

→
213
PeoplePredictiveMedium

Your predictive project has entered the execution phase, and you notice that one team member consistently delivers high-quality work but is frequently late with deliverables, causing delays to dependent tasks. During your one-on-one meeting, the team member reveals they are struggling with the technical complexity of their assignments but were hesitant to ask for help. What should be your primary response?

August 28, 2026

→
214
PeoplePredictiveMedium

You are leading a construction project following a waterfall methodology. One of your senior engineers, who has been with the company for 15 years, consistently questions your decisions in team meetings and undermines your authority in front of other team members. This behavior is affecting team morale and productivity. You have the project's RACI matrix clearly defining roles and responsibilities. What is the most appropriate action?

August 28, 2026

→
215
PeoplePredictiveMedium

You are managing a large infrastructure project using a predictive approach with a detailed WBS and resource-loaded schedule. During the planning phase, you identify that two critical team members have overlapping assignments during months 4-6, which will cause resource over-allocation. The project sponsor is pressuring you to maintain the current timeline. What should you do first?

August 28, 2026

→
216
ProcessPredictiveMedium

You are leading a pharmaceutical research project with strict regulatory requirements. During a risk review meeting, your team identifies a new risk: a potential change in regulatory standards that could require significant protocol modifications. The probability is estimated at 30% and the impact would be a 4-month delay and $200,000 in additional costs. The change, if it occurs, would happen in approximately 6 months. Your risk response strategy includes creating a contingency plan. What should you do NEXT?

August 28, 2026

→
217
ProcessPredictiveMedium

You are managing an infrastructure project with multiple external vendors. One vendor has consistently missed milestone dates, causing delays to dependent activities. You have documented these issues and discussed them in previous status meetings. The vendor's project manager claims their delays are due to incomplete information from your team, though your records show all required information was provided on schedule. The vendor is now 10 days behind on a critical path activity. What is the MOST appropriate next step?

August 28, 2026

→
218
ProcessPredictiveMedium

Your manufacturing project is in the execution phase with a CPI of 0.92 and an SPI of 1.05. During a quality audit, the quality assurance team discovers that several deliverables do not meet the specifications defined in the quality management plan. The project sponsor is pleased with the schedule performance and is pressuring you to maintain the current pace. Rework to fix the quality issues would cost an additional $40,000 and require 2 weeks. What should you do?

August 28, 2026

→
219
ProcessPredictiveMedium

You are managing a software development project following a waterfall methodology. The design phase has been completed and approved by stakeholders. During the development phase, the development team identifies that implementing a specific approved feature will require significant architectural changes that were not identified during design. The team estimates this will add 3 weeks to the schedule and $25,000 to the budget. The change would improve system performance but is not required to meet the original requirements. What is the BEST course of action?

August 28, 2026

→
220
ProcessPredictiveMedium

You are managing a construction project using a predictive approach. During the execution phase, a key supplier notifies you that they cannot deliver critical materials on the originally agreed date due to manufacturing delays. This delay will impact activities on the critical path. The supplier offers to expedite shipping at an additional cost of $15,000, which would maintain the original schedule. Your project has a management reserve of $50,000 and a contingency reserve of $30,000. What should you do first?

August 28, 2026

→
221
ProcessAgileEasy

Your agile team has completed a two-week sprint and is preparing for the sprint retrospective. This is the team's first retrospective, and some team members are unclear about the purpose of the meeting. One developer asks why they need to have a retrospective when they already completed a sprint review with stakeholders. How should you explain the PRIMARY purpose of the sprint retrospective?

August 28, 2026

→
222
ProcessAgileEasy

Your team is working on an e-commerce platform using Kanban. The team has a board with columns: To Do, In Progress, Code Review, Testing, and Done. The team notices that work items are piling up in the Code Review column, and the flow of work has slowed significantly. What is the BEST action the team should take to address this bottleneck?

August 28, 2026

→
223
ProcessAgileEasy

You are facilitating a daily standup for your agile development team. One team member begins explaining in detail the technical solution they are implementing and starts discussing code architecture with another developer. The conversation extends beyond 15 minutes, and other team members appear disengaged. As the Scrum Master, what should you do?

August 28, 2026

→
224
ProcessAgileEasy

Your agile team has just completed their third sprint of a mobile app development project. During the sprint review, stakeholders provide feedback and request several changes to features that were demonstrated. The product owner wants to incorporate this feedback. What should the product owner do NEXT with the feedback received during the sprint review?

August 28, 2026

→
225
ProcessAgileEasy

You are managing a software development project using Scrum. During the sprint planning meeting, the development team is estimating user stories for the upcoming sprint. One team member suggests using story points to estimate the relative effort required for each user story. Another team member asks why the team doesn't just estimate in hours instead. What is the PRIMARY benefit of using story points over hours for estimation in an agile project?

August 28, 2026

→