PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

340 questions found · page 6 of 14

126
ProcessAgileMedium

You are leading an agile project to develop a web portal. During the sixth sprint, a major competitor launches a similar product with features that make your planned functionality less competitive. The Product Owner wants to immediately pivot and add new differentiating features, which would require abandoning nearly half of the current sprint backlog. The development team is concerned about the disruption and waste of partially completed work. There are four days remaining in the ten-day sprint. What is the best course of action?

September 9, 2026

→
127
ProcessAgileMedium

Your agile team is working on a financial services application with strict regulatory compliance requirements. The compliance officer insists on reviewing and approving all completed work before it can be released, which takes 3-5 days. This has created a bottleneck, causing completed stories to pile up and not be truly 'done' by sprint end. Team morale is declining because their sprint goals are technically met, but nothing is actually reaching production. How should you address this situation?

September 9, 2026

→
128
ProcessAgileMedium

During sprint planning for a software development project, your team is estimating user stories for the upcoming two-week sprint. One critical story that the Product Owner wants included has significant technical uncertainty. Three developers provide estimates ranging from 3 to 13 story points, indicating vastly different understandings of the work involved. The team has already committed to 32 story points of well-understood stories, and their average velocity is 40 story points. What should the team do with this uncertain story?

September 9, 2026

→
129
ProcessAgileMedium

You are managing an agile project for developing a customer relationship management (CRM) system. After four iterations, the team has consistently delivered all committed story points, but customer feedback indicates that the features delivered are not addressing their most critical pain points. The Product Owner has been creating user stories based on what they think customers need rather than direct customer input. Velocity is stable, but customer satisfaction is declining. What is the most appropriate action to take?

September 9, 2026

→
130
ProcessAgileMedium

Your agile team has completed three sprints of a mobile app development project. During the retrospective, several team members mention that the Definition of Done (DoD) is unclear, leading to inconsistent quality across user stories. Some developers consider a story done after coding, while others include unit testing and code review. The Product Owner is frustrated that stories marked 'done' often require rework in subsequent sprints. What should the Scrum Master do first to address this issue?

September 9, 2026

→
131
ProcessAgileHard

Your organization is transitioning a large, multi-year infrastructure program to agile delivery. The program consists of five interdependent product teams, each running two-week sprints. After three program increments, dependencies between teams are causing frequent delays—Team A cannot complete their sprint commitments because they're waiting for API specifications from Team B, while Team C's database changes block Team D's integration testing. The program board shows 47 active dependencies across teams. Teams are becoming frustrated with blocked work and declining morale. What approach would best address these systemic dependency issues?

September 9, 2026

→
132
ProcessAgileHard

An agile team developing a healthcare platform has maintained consistent velocity at 38 story points for six consecutive sprints. During the retrospective, technical debt items are repeatedly raised but never addressed because the product owner prioritizes new features to maintain competitive advantage. The lead architect warns that accumulated technical debt is increasing the time required for new features by approximately 30%, and estimates two full sprints would be needed to address critical technical debt. Code quality metrics show increasing defect rates and decreasing test coverage. What is the most appropriate action?

September 9, 2026

→
133
ProcessAgileHard

A distributed agile team across four time zones is developing an API integration platform. During the daily standup conducted via video conference, developers in the Asia-Pacific region consistently remain silent or provide minimal updates. The product owner mentions that several critical defects discovered by APAC developers were not communicated until the weekly status report, causing a two-day delay in resolution. Team velocity metrics show APAC contributions are significantly lower than other regions despite having equal headcount. What is the most effective approach to improve team collaboration and information flow?

September 9, 2026

→
134
ProcessAgileHard

Your agile team has completed three sprints of a mobile application project. The product owner consistently adds new acceptance criteria during sprint reviews, claiming these represent newly discovered customer needs. The team's velocity has dropped from 45 to 28 story points, and team members are frustrated with rework. The product owner insists all changes are critical for market competitiveness. Sprint planning for the next iteration is scheduled for tomorrow. What should the Scrum Master do first to address this situation?

September 9, 2026

→
135
ProcessAgileHard

During the eighth sprint of a financial services product, a regulatory compliance requirement emerges that affects the system's data retention architecture. The compliance officer estimates implementation requires 320 hours of effort, equivalent to four full sprints of the eight-person team's capacity. The product owner has a committed release date in six sprints to support a major client contract worth $2.3M annually. The current product backlog contains 180 story points of features promised for this release. The team's average velocity is 45 story points per sprint. How should the team approach this situation?

September 9, 2026

→
136
ProcessPredictiveMedium

You are managing a pharmaceutical product development project following a predictive lifecycle with strict regulatory requirements. During the testing phase, a critical test reveals unexpected results that require investigation before proceeding. This was not anticipated in the risk register. The project schedule has no float, and any delay will impact the launch date that has been publicly announced to investors. The quality manager insists on a thorough investigation that will take three weeks, while the sponsor pressures you to proceed with limited investigation to maintain the schedule. What should you do?

September 9, 2026

→
137
ProcessPredictiveMedium

You are managing a manufacturing project using a predictive approach. During a quality inspection, you discover that 15% of the completed components do not meet the quality specifications defined in the quality management plan. The components are already installed, and removing them would require significant rework, causing a two-week delay and 20% cost increase. The defects are minor and do not affect functionality, but they do not meet documented specifications. Your team suggests accepting the components as-is. What should you do?

September 9, 2026

→
138
ProcessPredictiveMedium

Your software development project is following a predictive lifecycle with detailed upfront planning. You are currently in the execution phase, and the project is on schedule and within budget. A key stakeholder who was minimally involved during planning now requests a significant feature addition that would provide substantial business value but was not included in the original scope. The stakeholder insists this feature is critical and should be added immediately without formal approval processes. What is the most appropriate action?

September 9, 2026

→
139
ProcessPredictiveMedium

You are managing a construction project using a predictive approach. During the execution phase, a major supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. The project schedule shows this material is on the critical path, and the delay will impact the project completion date. You review the risk register and find this supplier delay was identified as a potential risk with a mitigation strategy documented. What should you do first?

September 9, 2026

→
140
ProcessPredictiveMedium

You are managing a telecommunications infrastructure project using a predictive methodology. The project is 60% complete when you conduct an earned value analysis. The results show: PV = $800,000, EV = $720,000, AC = $780,000, BAC = $1,200,000. Based on these metrics, the project team is concerned about performance. The sponsor asks you to forecast the total cost at completion and explain the project's current performance status. What is the most accurate assessment?

September 9, 2026

→
141
ProcessPredictiveHard

Your organization is executing a portfolio of projects, and you are managing a critical ERP implementation with a 18-month timeline. At month 10, the portfolio review board redirects your two most experienced technical resources to a new executive priority project for the next 90 days. These resources are currently assigned to critical path activities for database migration and integration testing. Your resource manager can provide three junior resources as replacements, but they lack ERP experience. The portfolio manager states this is non-negotiable due to business priorities. Your analysis shows that using junior resources will likely cause 6-8 weeks of schedule delay and increase risk of integration defects. What should be your PRIMARY response?

September 9, 2026

→
142
ProcessPredictiveHard

You are managing a government defense project with a fixed-price contract and strict security protocols. At the 40% completion point, a new regulation is published requiring additional cybersecurity controls that were not in the original scope. Implementing these controls will add $1.2M to project costs and 4 months to the schedule. Your contracts team confirms this qualifies as a changes in law provision under the contract. However, the government client's project office indicates their fiscal year budget cannot accommodate the increase and suggests descoping other requirements to offset costs. Your technical lead warns that descoping any current requirements will likely fail the final security certification. What is the MOST appropriate next step?

September 9, 2026

→
143
ProcessPredictiveHard

You are managing a large infrastructure project with a 24-month timeline and a $15M budget. During month 14, your Cost Performance Index (CPI) is 0.89 and Schedule Performance Index (SPI) is 0.92. The project has consumed $9.2M of the budget. Your sponsor is concerned about cost overruns and demands that you reduce spending immediately. The critical path activities for the next three months include foundation work that requires specialized equipment already procured and scheduled. What should be your PRIMARY response to the sponsor's demand?

September 9, 2026

→
144
ProcessPredictiveHard

You are leading a construction project that is 65% complete when a key subcontractor declares bankruptcy. This subcontractor was responsible for all electrical work, representing 20% of remaining project activities. Three alternative subcontractors have been identified: Vendor A can start immediately but costs 35% more; Vendor B matches the original cost but needs 45 days mobilization; Vendor C costs 15% more and needs 20 days mobilization. The electrical work is on the critical path, and contract penalties of $50,000 per week apply after the baseline completion date, which is 90 days away. Your analysis shows current electrical work would take 70 days. What is the BEST course of action?

September 9, 2026

→
145
ProcessPredictiveHard

Your pharmaceutical project is developing a new drug formulation with strict FDA validation requirements. The project is using a stage-gate approach with formal quality reviews at each phase. During the Phase 2 gate review, quality auditors identify that 12 of 47 deliverables from Phase 1 do not fully meet the documented acceptance criteria, though they passed initial reviews. Reworking these deliverables will cost $340,000 and delay the project by 6 weeks. The Phase 1 project manager, who has since left the company, approved these deliverables based on verbal agreements with stakeholders that differ from the documented requirements. What should you do FIRST?

September 9, 2026

→
146
ProcessAgileHard

Your organization is implementing SAFe (Scaled Agile Framework) across five agile teams working on an integrated product. During PI (Program Increment) Planning, the teams identified 23 dependencies between them. After three sprints, only 30% of planned features are completed because teams are waiting on each other. The Release Train Engineer asks you, as one of the Scrum Masters, how to address the delivery delays. Analysis shows that eight dependencies are technical integration points, ten are related to shared specialist resources, and five involve sequential work that cannot be parallelized. What is the most effective approach to improve flow?

September 2, 2026

→
147
ProcessAgileHard

You're leading an agile transformation initiative in a financial services company. After six months, eight teams are running sprints, but several dysfunctions have emerged: teams are consistently achieving 100% of sprint commitments but stakeholders report little business value is being delivered; sprint retrospectives focus on minor process tweaks rather than substantive improvements; technical debt is accumulating rapidly with no plan to address it; and teams report they're afraid to raise impediments because previous attempts resulted in blame from management. Velocity metrics are stable and high. Senior management considers the transformation successful based on these metrics. What is the most critical issue to address?

September 2, 2026

→
148
ProcessAgileHard

Your agile project team is developing a medical device software component that requires FDA regulatory approval. You're using two-week sprints with a definition of done that includes unit tests, integration tests, and code review. The regulatory affairs department insists that no code can be released to production without completing a validation protocol that takes 6-8 weeks and costs $50,000 per validation cycle. Marketing is pressuring for faster feature delivery to respond to competitive threats. The team is frustrated because completed increments sit unreleased for months. How should you adapt your agile approach to balance regulatory compliance with agile principles?

September 2, 2026

→
149
ProcessAgileHard

Your agile team has been delivering increments every two weeks for six months. The product owner recently left the company, and a new product owner has joined who has minimal agile experience. During the last three sprint reviews, the new product owner has been rejecting completed stories that meet all acceptance criteria, stating they don't align with their vision. The team's velocity has dropped by 40%, and morale is declining. Stakeholders are concerned about the lack of accepted deliverables. What should the Scrum Master do first to address this situation?

September 2, 2026

→
150
ProcessAgileHard

Your distributed agile team spans three time zones (San Francisco, New York, and London) with 3-4 members in each location. After four sprints, several patterns have emerged: the London team members are disconnected from decisions made during daily standups that occur at 9 AM Pacific; sprint planning sessions run 4-5 hours as teams debate estimates and approach; and sprint reviews lack engagement because stakeholders in Europe attend at 7 PM their time. The team's definition of done includes peer code review, but reviews are delayed 12-16 hours waiting for reviewers in other time zones. One team member has suggested abandoning agile practices in favor of a more asynchronous waterfall approach. What strategy would most effectively address these distributed team challenges?

September 2, 2026

→