PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

145 questions found · page 1 of 6

1
ProcessPredictiveMedium

You are managing a pharmaceutical research project following a stage-gate process. Your project has just completed the Phase 2 clinical trials deliverable. According to the project management plan, a phase gate review is scheduled before proceeding to Phase 3 trials, which will require significant investment. During your preparation for the gate review, you discover that while the trials met their primary endpoint, two secondary endpoints showed concerning trends. The data is not conclusive but suggests potential issues. The project is currently on schedule and under budget. What should you do?

October 7, 2026

→
2
ProcessPredictiveMedium

Your project team has completed the project scope statement and is now developing the work breakdown structure (WBS). One of your team members suggests creating work packages at different levels of decomposition across the WBS—some at a very detailed level that can be completed in days, and others at a higher level representing several weeks of work. The team member argues this will save time in the planning process. What is the best approach?

October 7, 2026

→
3
ProcessPredictiveMedium

You are managing a software development project using a waterfall methodology. During the design phase, your technical lead identifies that implementing a requested feature will require a third-party library that introduces significant security vulnerabilities. The feature was explicitly defined in the approved scope baseline and is important to the customer. After analysis, your team proposes an alternative technical approach that provides similar functionality without the security risk but will add $15,000 to the project cost. What should you do?

October 7, 2026

→
4
ProcessPredictiveMedium

Your construction project is 60% complete when you conduct an earned value analysis. The results show: PV = $500,000, EV = $450,000, AC = $480,000. The project sponsor asks you to provide a forecast of the final project cost. Based on current performance trends, you believe the cost variance is atypical and future work will be performed at the planned rate. What estimate at completion (EAC) should you report?

October 7, 2026

→
5
ProcessPredictiveMedium

You are managing a large infrastructure project using a predictive approach. During the execution phase, a key vendor informs you that a critical component will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and potentially the project's contractual completion date. The project sponsor is highly concerned about meeting the deadline. What should you do first?

October 7, 2026

→
6
ProcessHybridMedium

Your organization is executing a hybrid project to implement a new financial system. The software configuration follows an adaptive approach with two-week iterations, while data migration and cutover activities are planned predictively due to strict regulatory windows. You're currently in iteration 5 of 10. During a governance review, the CFO requests a detailed status report showing percentage complete for the entire project and exact completion dates for all remaining work. Your adaptive team tracks progress using velocity and burndown charts. How should you respond to this request?

September 30, 2026

→
7
ProcessHybridMedium

You're managing a product development project using a hybrid approach where research and design follow a stage-gate process, while development and testing use Scrum. The design team has just completed the design phase and handed off detailed specifications to the development team. During sprint planning, the development team identifies several design elements that are technically infeasible with current technology and proposes alternative approaches that would require design changes. The design lead is resistant, stating that the design was approved through the formal gate review and shouldn't change without going back through governance. What should you do?

September 30, 2026

→
8
ProcessHybridMedium

You are leading a hybrid project where marketing campaigns follow a waterfall approach with fixed launch dates, while the supporting digital platform is developed using Kanban. The platform team has adopted a continuous flow model and deploys features as they're completed. The marketing director is frustrated because features are being released without coordination with campaign timelines, resulting in promotional materials that don't match current functionality. The platform team argues that continuous delivery provides faster value. What is the best way to resolve this conflict?

September 30, 2026

→
9
ProcessHybridMedium

Your hybrid project uses iterative development for customer-facing features and predictive planning for regulatory compliance activities. During a retrospective, the development team reports that compliance reviews are causing significant delays because compliance work is scheduled in sequential phases without team input. The compliance manager insists on following the approved plan to ensure audit readiness. Team morale is declining as they feel the rigid compliance process contradicts the adaptive approach they use for features. How should you address this situation?

September 30, 2026

→
10
ProcessHybridMedium

You are managing a hybrid project where the development team uses Scrum for software components while infrastructure deployment follows a predictive approach. The software team has completed three sprints successfully, but the infrastructure team is two weeks behind schedule due to unexpected vendor delays. Stakeholders are concerned about integration timelines. The next sprint planning meeting is in two days, and the infrastructure team's delay will impact the planned software features that depend on the new servers. What should you do first?

September 30, 2026

→
11
ProcessAgileMedium

You are facilitating a sprint retrospective for a team that has just completed a challenging sprint where they missed their sprint goal. During the retrospective, two team members begin blaming each other for technical decisions that led to delays. Other team members become defensive, and the conversation is deteriorating into personal criticism rather than focusing on process improvement. The team has worked well together in the past, but the pressure of the missed goal is creating tension. As the facilitator, what should you do?

September 29, 2026

→
12
ProcessAgileMedium

Your Kanban team has been tracking their flow metrics, and you notice the average cycle time has increased from 4 days to 7 days over the past month. The team's WIP limits haven't changed, and the work item types are consistent with previous months. During a team discussion, you discover that items are spending significantly more time in the 'Code Review' column, often waiting 2-3 days before being reviewed. Team members mention they're focused on completing their own work before reviewing others' contributions. What should the team do to address this issue?

September 29, 2026

→
13
ProcessAgileMedium

Your agile team is three sprints into developing a mobile application. During the latest sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though the implemented features match the acceptance criteria in the user stories. The Product Owner explains they wrote the acceptance criteria based on their understanding but didn't include UI specifications. The team is frustrated because they'll need to rework completed features. How should this situation be addressed going forward?

September 29, 2026

→
14
ProcessAgileMedium

During sprint planning, your development team is struggling to break down a large user story estimated at 21 story points. The Product Owner insists this story must be completed in the upcoming two-week sprint because it's critical for an upcoming trade show demonstration. The team expresses concern that they typically complete 25-30 story points per sprint, but this single story would consume most of their capacity and carries significant technical risk. The story cannot be demonstrated partially. What is the best approach?

September 29, 2026

→
15
ProcessAgileMedium

Your Scrum team has completed their third sprint, and the Product Owner notices that the team's velocity has been inconsistent: 21 story points in Sprint 1, 15 in Sprint 2, and 18 in Sprint 3. The Product Owner is concerned about meeting the release deadline and asks you, as the Scrum Master, to commit to a specific velocity for the remaining sprints so stakeholders can plan accordingly. The team is still learning to work together and refining their estimation practices. What should you do?

September 29, 2026

→
16
ProcessPredictiveMedium

You are managing a pharmaceutical research project following a stage-gate predictive methodology. Your project has just completed the design phase, and you are preparing for the gate review before entering the development phase. During preparation, you discover that one of the key assumptions documented in the project charter—that a specific research facility would be available—is no longer valid due to facility renovations. The next available equivalent facility is in a different location and would increase project costs by 8%. What should you do BEFORE the gate review?

September 29, 2026

→
17
ProcessPredictiveMedium

You are managing a large infrastructure project with multiple subcontractors. One of your key vendors has completed their deliverable, and you are conducting procurement closure activities. While reviewing the final deliverable, you notice it meets all technical specifications in the contract, but the vendor failed to submit three required progress reports during execution as stipulated in the contract terms. The vendor is requesting final payment and contract closure. What is the MOST appropriate action?

September 29, 2026

→
18
ProcessPredictiveMedium

You are managing a software implementation project for a financial institution using a waterfall approach. During quality testing, the QA team discovers that 12% of test cases are failing, primarily related to security authentication features. The quality management plan specified that no more than 5% of test cases should fail at this stage. The development team believes they can fix the issues within one week, but this will delay the scheduled user acceptance testing. What should you do?

September 29, 2026

→
19
ProcessPredictiveMedium

Your manufacturing project is in the planning phase, and you are developing the cost baseline. You have completed bottom-up estimating for all work packages and have aggregated these costs. The finance department requires a 10% management reserve for organizational risks, and historical data shows similar projects typically experience 15% cost variance. Your project sponsor asks what the final project budget should include. What is the MOST appropriate approach?

September 29, 2026

→
20
ProcessPredictiveMedium

You are managing a construction project using a predictive approach. During the execution phase, a key supplier informs you that critical materials will be delayed by three weeks due to manufacturing issues. The delay will impact the critical path and push the project completion date beyond the contractually agreed deadline. Several team members suggest crashing the schedule by adding overtime resources, while the sponsor wants to explore fast-tracking options. What should you do FIRST?

September 29, 2026

→
21
ProcessHybridMedium

You are managing a marketing campaign project using a hybrid approach where creative content is developed iteratively with weekly reviews, while media buying and contracts follow a predictive schedule with fixed commitments. Three weeks before launch, the iterative creative reviews reveal that the campaign messaging needs significant changes based on stakeholder feedback. However, media placements worth $200,000 have already been contracted based on the original creative concept, and changing them would incur 25% cancellation fees. The CMO insists the new messaging is essential for campaign success. How should you proceed?

September 22, 2026

→
22
ProcessHybridMedium

Your hybrid project uses iterative development for software components and predictive planning for regulatory submissions. During a retrospective, the development team reports that 40% of their completed work from the last two sprints cannot be deployed because regulatory documentation hasn't kept pace with development velocity. The regulatory specialist, who works part-time on your project, states she can only document work after it's fully tested and stabilized. This creates a growing backlog of undocumented, undeployable features. What should you address first?

September 22, 2026

→
23
ProcessHybridMedium

You are leading a hybrid project where software features are developed using Scrum while hardware components follow a stage-gate process. During a sprint review, the software team demonstrates a new feature that requires a hardware modification the hardware team didn't anticipate. The hardware team's next gate review isn't scheduled for six weeks, and making changes outside the stage-gate process violates organizational governance. The software feature cannot be released without the hardware change. What is the best way to handle this situation?

September 22, 2026

→
24
ProcessHybridMedium

Your organization is implementing a new customer portal using a hybrid approach. The infrastructure and security components follow a predictive lifecycle with a fixed release date in six months, while the user interface features are being developed iteratively in two-week sprints. The product owner wants to release features to users as soon as they're ready, but the infrastructure team insists nothing can go live until the full security framework is complete. Stakeholders are pressuring you to show early value. How should you proceed?

September 22, 2026

→
25
ProcessHybridMedium

You are managing a hybrid project where the product development team works in two-week sprints while the regulatory compliance team follows a waterfall approach with predefined milestones. During sprint planning, the development team commits to features that require compliance documentation, but the compliance team indicates they need four weeks' advance notice to complete their reviews. This misalignment has caused delays in three consecutive sprints. What should you do to address this integration challenge?

September 22, 2026

→