PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

180 questions found · page 1 of 8

1
ProcessHybridMedium

A project manager is overseeing a hybrid project to build a new e-commerce platform. The database architecture and payment integration are being developed using a predictive approach due to security requirements and third-party dependencies, while the website features are being delivered through Scrum sprints. The project has a fixed budget of $800,000 and a target completion date in nine months. After four months, earned value analysis shows the predictive components are over budget by 15% with an SPI of 0.85, while the Scrum team is delivering consistently within their sprint budgets. What should the project manager do?

November 23, 2026

→
2
ProcessHybridMedium

A financial services company is running a hybrid project to upgrade its payment processing system. Regulatory compliance and security components are managed predictively with extensive documentation and formal approvals, while the customer-facing features are developed using Kanban. During a compliance audit, auditors request complete traceability of all requirements to test cases and deployment records. The Kanban team has been tracking work items and testing informally through their board and daily standups. What is the best way for the project manager to address the audit requirements?

November 23, 2026

→
3
ProcessHybridMedium

A project manager is leading a hybrid project to develop a new mobile application with backend infrastructure upgrades. The infrastructure work uses a predictive approach with detailed plans and change control, while the application development follows Scrum practices. Three months into the project, the cumulative flow diagram shows that work items in the 'testing' state have been increasing steadily, while the 'done' column shows minimal progress. The predictive infrastructure tasks are on schedule. What should the project manager do to address this situation?

November 23, 2026

→
4
ProcessHybridMedium

A manufacturing company is executing a hybrid project to modernize its production line. The hardware installation follows a predictive waterfall approach due to vendor constraints and safety regulations, while software configuration is managed through two-week sprints. During the fourth sprint review, stakeholders request significant changes to the reporting dashboard that would require three additional sprints to implement. However, the hardware installation is scheduled to complete in five weeks, and production must begin immediately afterward. How should the project manager address this situation?

November 23, 2026

→
5
ProcessHybridMedium

A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The infrastructure and data migration components are being delivered using a predictive approach with fixed milestones, while the user interface customization is being developed iteratively using Scrum. During sprint planning, the development team identifies dependencies on the data migration work, which is running two weeks behind schedule. The team is concerned they won't be able to complete their committed sprint work without the migrated data. What should the project manager do first?

November 23, 2026

→
6
ProcessAgileMedium

An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?

November 11, 2026

→
7
ProcessAgileMedium

Your agile team is developing a financial reporting system for a highly regulated industry. During the sprint, a new compliance regulation is announced that affects functionality planned for the next three sprints. The product owner wants to immediately pivot to address the compliance requirement, which would mean abandoning partially completed work from the current sprint. The team is five days into a two-week sprint and has completed about 60% of their committed work. What should the Scrum Master recommend?

November 11, 2026

→
8
ProcessAgileMedium

A software development team is working on a cloud migration project using Scrum. During the sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though it meets all the acceptance criteria defined in the user stories. The product owner approved these acceptance criteria during backlog refinement two weeks ago. Several stakeholders express disappointment and suggest the team wasted the sprint. What is the most appropriate action for the team to take?

November 11, 2026

→
9
ProcessAgileMedium

An agile project team is building a customer portal for an insurance company. During sprint planning, the development team estimates that the highest-priority user story will take 13 story points to complete, but the team's average velocity is only 35 points per two-week sprint and they have already committed to 28 points of other work. The product owner insists this story must be included because a major client has requested this feature for a demo in three weeks. The team is concerned about over-committing. How should the team proceed?

November 11, 2026

→
10
ProcessAgileMedium

Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?

November 11, 2026

→
11
ProcessPredictiveMedium

You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?

November 11, 2026

→
12
ProcessPredictiveMedium

During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?

November 11, 2026

→
13
ProcessPredictiveMedium

You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?

November 11, 2026

→
14
ProcessPredictiveMedium

Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?

November 11, 2026

→
15
ProcessPredictiveMedium

You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?

November 11, 2026

→
16
ProcessHybridMedium

You are managing a digital transformation project using a hybrid approach. The enterprise architecture team works in a predictive manner with quarterly milestones, while multiple product teams use Scrum. During PI (Program Increment) planning, you discover that two product teams have dependencies on an architectural component that the enterprise team planned to deliver in Q3, but the product teams need it in Q2 to meet their commitments. The enterprise architect states that accelerating this component would require deferring other architectural work that supports different initiatives. How should you proceed?

November 2, 2026

→
17
ProcessHybridMedium

Your hybrid project combines predictive planning for hardware procurement and facilities setup with agile development for the software components. You're three months into the project, and the predictive track is on schedule, but the agile teams have consistently delivered only 60% of their planned story points each sprint. The cumulative flow is trending behind, and stakeholders are concerned about meeting the fixed launch date in six months. The teams report that integration testing with hardware prototypes takes longer than expected. What is the most appropriate action?

November 2, 2026

→
18
ProcessHybridMedium

You are leading a product development project using a hybrid approach where research and regulatory approval follow a waterfall process, while feature development uses Kanban. The regulatory team has just received approval for the product specifications, which is a major milestone. However, during the regulatory review process, the development team continued building features based on the submitted specifications and has now completed 60% of the planned features. The approved specifications include three changes from what was originally submitted. What should you do next?

November 2, 2026

→
19
ProcessHybridMedium

Your organization is implementing a new customer portal using a hybrid approach. The compliance and security requirements are being managed predictively with detailed documentation and stage-gate approvals, while the user interface features are developed iteratively using two-week sprints. During a sprint review, stakeholders request significant changes to the authentication flow that would require modifications to the security architecture currently in the design phase. The security architect says these changes would delay the security deliverables by one month. What is the best way to handle this situation?

November 2, 2026

→
20
ProcessHybridMedium

You are managing a hybrid project where the infrastructure team uses predictive methods while the software development team uses Scrum. During sprint planning, the infrastructure lead informs you that a critical server installation scheduled for next week has been delayed by two weeks due to vendor issues. This delay will impact the development team's ability to deploy features in the next three sprints. The development team has already committed to their sprint goals. What should you do first?

November 2, 2026

→
21
ProcessHybridMedium

Your organization is implementing a new ERP system using a hybrid approach: core system configuration follows predictive methodology while custom integrations use Scrum. During the third sprint review, stakeholders request a demonstration of the complete system including both core and custom components. However, the predictive track won't have testable deliverables for another two months. Stakeholders express frustration about not seeing the 'whole picture.' How should you address this?

October 29, 2026

→
22
ProcessHybridMedium

Your hybrid project uses iterative development for product features while marketing and compliance activities follow a predictive timeline. The compliance team has just informed you that a regulatory requirement will change in three months, affecting features currently in the product backlog. The change is mandatory but the detailed requirements won't be available for six weeks. How should you respond?

October 29, 2026

→
23
ProcessHybridMedium

You're managing a construction project with a hybrid approach: building construction uses predictive methods while the smart building technology implementation uses agile sprints. The construction is running two weeks behind schedule due to weather delays, which will impact the technology team's access to spaces where they planned to work next sprint. The technology team wants to reprioritize their backlog to work on components they can complete off-site. What should you evaluate first before approving this change?

October 29, 2026

→
24
ProcessHybridMedium

You're leading a hybrid project where design work follows a waterfall approach while development uses two-week sprints. The design team has completed 70% of their deliverables, but recent customer feedback suggests significant changes are needed. The development team has already built features based on the completed designs. The project sponsor wants to incorporate the feedback but is concerned about budget overruns. What is your best course of action?

October 29, 2026

→
25
ProcessHybridMedium

You are managing a hybrid project where the software development team uses Scrum while the infrastructure team follows a predictive approach. During sprint planning, the development team commits to features that require infrastructure components not yet scheduled in the infrastructure team's plan. This misalignment has caused delays in the past two sprints. What should you do to address this recurring issue?

October 29, 2026

→